2015-Aug-21 Accel. Phys. Biweekly Report

From Administrative
Jump to navigation Jump to search

Todd Satogata

 Previous two weeks (Aug 10-21)
   - CEBAF: Hall D FFB evaluation; BPM data analysis (w/Alexandre Deur); BTeam;
     fopt optics tuning development (w/Eric Thompson)
   - ER@CEBAF: biweekly meeting; BBU model development (w/Yue Hao); trip planning
   - ADMIN: IPAC'15 proceedings finalization; COOL'15 program work
   - MEIC: Gear-changing summary report contribution; beam-beam model development
   - ODU/MEIC: Continue bunch-splitting simulations, education with Randy
   - ODU: NNSA funding proposal development (biweekly telecon)
   - VACATION: 8/10(pm), 8/12, 8/14(am)
 Next two weeks (Aug 24-Sep 4)
   - CEBAF: ORFP editing; BTeam; fopt optics tuning development (w/Eric
     Thompson); Hall D weekly meeting
   - ER@CEBAF: biweekly meeting; BBU model development (w/Yue Hao); trip
     planning (BNL Sep 4-11)
   - ADMIN: JACoW documentation development (Board of Directors)
   - MEIC: Continue beam-beam model development
   - ODU/MEIC: Continue bunch-splitting simulations, education with Randy
   - ODU: NNSA funding proposal development (biweekly telecon)
   - FMLA: 08/28

Alex Bogacz

 Previous two weeks (Aug 10-21)
   - NuFact15 (Aug 10-15)
   - Vacation (Aug 16-21)
 Next two weeks (Aug 24-Sep 4)
   - CEBAF: Check M56=0 lattices from Yves for fall run
   - ER@CEBAF: continue optics longitudinal match, extraction considerations

Dave Douglas

 Previous two weeks (Aug 10-21)
   - MEIC: Wrote up magnetized beam matching note; arc to Chris for space
     charge simulations; DIMAD model developed to work out dechirp.
   - Project E: Thinking about compressors in new optics, kibitzing to ASML
   - ER@CEBAF: Meetings
   - Other: DOE FWP review for LK Len
 Next two weeks (Aug 24-Sep 4)
   - MEIC: Deliver magnetized beam matching note; finish DIMAD model for
     dechirp; start writing technote on magnetized arc transport design.
   - LERF: Clean up DIMAD deck for IR region (remove W55 wiggler and THz
     chicane); start reconfiguring optis to integrate detector/isotope
     production.
   - Project E: Possibly start developing diagnostics lines pending
     guidance; trip planning for September.
   - ER@CEBAF: Meetings, start writing on motivation section
   - Other: PRL Review

Chris Tennant

 Previous two weeks (Aug 10-21)
   - MEIC: magnetized beam transport/matching, including adaption to Tstep and
     incorporation of Douglas optics for space charge simulation
   - LERF: Continue FEL lattice to CED/LED with Michele Joyce/Theo
   - Bubble Chamber: 5D line to elegant, configured zigzag harp scans for
     5 MeV region, shifts awaiting measurement opportunities.
   - ER@CEBAF: Meetings, measurements planning
 Next two weeks (Aug 24-Sep 4)
   - MEIC: Continued magnetized beam transport, start technote documentation
   - LERF: Check FEL lattice in LED
   - Project E: start evaluating momentum aperture of lattice, Touschek impact,
     compare to Rui's predictions
   - Bubble Chamber: run planning for September, guidance for tuning (e.g.
     small spot size on radiator)

Alex Castilla

 Previous two weeks (Aug 10-21)
   - Dissertation writing
   - Continue preparations for MEPAS teaching in Nov
 Next two weeks (Aug 24-Sep 4)
   - Dissertation writing
   - Start preparations for MEPAS teaching in Nov

Randy Gamage

 Previous two weeks (Aug 10-21)
   - MEIC: Longitudinal model development
 Next two weeks (Aug 24-Sep 4)
   - MEIC: Longitudinal model development