Jan 7-Jan 18
Director - Todd Satogata
Previous two weeks () - Next two weeks () -
Alex Bogacz
Previous two weeks () - Next two weeks () -
Rui Li
Previous two weeks () - Next two weeks () -
Ed Nissen
Previous two weeks () - Next two weeks () -
Chris Tennant
Previous two weeks () - Next two weeks () -
Accelerator R & D - Y. Zhang
Fanglei Lin
Previous two weeks (Jan 7 - Jan 18) - Optimizing the electron collider ring design with PEP-II magnets - Working on the storage ring cooler project - Miscellaneous: attended the spin transparency test teleconference, attended the Pre-CDR Update meeting, attended the JLEIC R&D meeting, attended the Innovative HE Cooling Project Status meeting, attended the Storage Ring Cooler meeting, attended JLEIC general meeting Next two weeks (Jan 18 - Feb 1) - Work on the electron collider ring design with PEP-II magnets - Work on the storage ring cooler project - Electron spin study using BMAD
Vasiliy Morozov
Previous two weeks (Jan 7 - Jan 18) - Next two weeks (Jan 18 - Feb 1) -
Amy Sy
Previous two weeks (Jan 7 - Jan 18) - Next two weeks (Jan 18 - Feb 1) -
Computational Physics - Y. Roblin
Yves Roblin
CEBAF
OTHER
He Zhang
Previous two weeks (Jan 7 - Jan 18) - Development of JSPEC code - DeCooling Rate Calculation for JLEIC with New Parameters - BeamBeam3D Next two weeks (Jan 18 - Feb 1) - Finish th core-tail model - Finish space charge effect in friction force calculation - Continue documenting JSPEC development Others - Write for three FOA quarterly reports
Diagnostic Development - K. Jordan
No report.
LERF - S. Benson
- May 14-25
- Derived draft budget for isotope production
- Went over isotope project with DOE site office staff
- Summarized labor resources needed for FOA proposal
- Continued cleaning up the LERF for isotope visit.
- Attended teleconference with DOE for isotope project.
- Hosted Cooling ring meetings on May 16 and 23rd and wrote up minutes
- Established CCR circumference for Pre-CDR
- Reviewed IRMMW paper, LDRD proposals and IPAC contribution
- May 29-June 8
- Arrange for collaboration with HZDR for Elbe II facility.
- Submit budget for isotope project
- Complete AWP for FOA proposal
- Revise LOD to match new ASE document.
- Complete question answers for LDRD proposals
- Review a couple of AIP papers