2016-Aug-19 Accel. Phys. Biweekly Report

From Administrative
Revision as of 13:53, 7 February 2017 by Anichols (talk | contribs) (Created page with "Todd Satogata Previous two weeks (Aug 8-Aug 19) - OPS: BTeam, training advice, Hall D energy correlation work, DarkLight prep, RSRBPH review - JLEIC: Continue lin...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search

Todd Satogata

  Previous two weeks (Aug 8-Aug 19)
    - OPS: BTeam, training advice, Hall D energy correlation work, DarkLight prep, RSRBPH review
    - JLEIC: Continue linac lattice evaluation, document in spreadsheet/wiki
    - JLEIC/ODU: Randy meetings re ion bunch splitting
    - ADMIN: Biweekly, leadership meet, Dave back to work
    - JACOW: IPAC'18 SPC start org, NAPAC'16 registration assistance
    - ODU: Start Fall PHYS 231 class prep start, REU future project list
    - PERS: Sick time PM Aug 19
  Next two weeks (Aug 22-Sep 2)
    - ODU: Continue Fall PHYS 231 class prep, start classes (Aug 29)
    - JLEIC: Continue evaluating/documenting ion linac lattice, extend to high energy option
    - JACOW: Start Team Meeting planning
    - OPS: BTeam, DarkLight shift support
    - ER@CEBAF: Continue peer-review paper, CERN/Cornell engagement
    - JLEIC/ODU: Figure out impedance model in esme for debunched beam instability sims
    - PERS: Vacation (Sep 1-2)

Alex Bogacz

  Previous two weeks (Aug 8-Aug 19)
    - ADMIN: PRST:AB article review
    - JLEIC: Booster to ion ring transfer line to wiki
    - PERS: Medical leave
  Next two weeks (Aug 22-Sep 2)
    - NUFACT'16: Vietnam, Aug 21-27
    - VACATION: To Sep 3

David Douglas

  Previous two weeks (Aug 8-Aug 19)
    - PERS: Medical leave (to Aug 12 full time, half time to Aug 19)
    - ADMIN: Finish PRST:AB review, start PRL review, accepted NWO review
    - ADMIN: Completed standards of conduct training
    - OPS: DarkLight run planning, solenoid field imperfection tracking
  Next two weeks (Aug 22-Sep 2)
    - PERS: Medical leave (part time)
    - OPS: DarkLight operations support
    - ADMIN: Rad I training refresher
    - ADMIN: Finish PRL review, start NWO review

Ed Nissen

  Previous two weeks (Aug 8-Aug 19)
    - JLEIC: Beam-beam update at R&D meeting
    - JLEIC: Lyapunov check of gear changing
    - JLEIC: Climbing learning curve on Vasiliy code for beam tuning
  Next two weeks (Aug 22-Sep 2)
    - JLEIC: Integrate/document existing packages for optimization runs
    - JLEIC: Integration of Cosy Infinity/MAD for beam-beam tune scan

Chris Tennant

  Previous two weeks (Aug 8-Aug 19)
    - MARIE workshop: Los Alamos, Aug 8-11
    - Met with Auralee/Stephen Milton at workshop re her diss work
    - JLEIC: Worked with Cheng-Ying on cooler arc lattices to test ubunch code
       for magnetized beam
    - OPS: DarkLight run planning, difference orbit evaluation, procedure reviews
  Next two weeks (Aug 22-Sep 2)
    - MARIE workshop (LANL Aug 8-11)
    - OPS: DarkLight: Data analysis, run planning

Randy Gamage

  Previous two weeks (Aug 8-Aug 19)
    - JLEIC: Continue writing outlines of initial dissertation chapters
    - JLEIC: Start GA simulations of bunch splitting optimization
  Next two weeks (Aug 22-Sep 2)
    - JLEIC: Continue writing outlines of initial dissertation chapters
    - JLEIC: Continue esme simulations of debunch/rebunch with impedance
    - JLEIC: Continue GA simulations of bunch splitting optimization