2015-10-26 to 2015-11-09 Accelerator Physics Biweekly Report

From Administrative
Jump to navigation Jump to search
The printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.

Todd Satogata

  Previous two weeks (Oct 26-Nov 9)
    - OPS: BTeam/Model meeting, operations training and engagement
    - OPS: ATLis reviews, Hall D optics ATLis, optician schedules
    - LERF: Fall two week restart/operations run (observer for a few shifts)
    - ER@CEBAF: biweekly meeting org, coordination telecons with Francois Meot
    - ODU/MEIC: Continue bunch-splitting simulations, education with Randy
    - MEIC: Simple coding simulation development for exploring gear changing
    - JACoW: Team Meeting (Nov 13-22) talk preparation
  Next two weeks (Nov 9-23)
    - JACoW: Team Meeting (Nov 13-22, Padova Italy)
    - CEBAF: AutoQuad commissioning, optics matching configuration
    - OPS: BTeam/Model meetings
    - ADMIN: Interviews (Staff I, position 11639)
    - ADMIN: Employee annual review processing

Alex Bogacz

  Previous two weeks (Oct 26-Nov 9)
    - ER@CEBAF: CEBAF ER chicane option
    - ADMIN: Tech Transfer Committee: Invention Disclosure Reviews
    - ADMIN: SBIR/STTR reviews
    - CEBAF: Restart meetings
  Next two weeks (Nov 9-23)
    - CEBAF: Startup, optics
    - ADMIN: editing JINST chapter on 'Fundamental Aspects of Muon Decay Rings'
    - ER@CEBAF: CEBAF ER transverse optics, matching to the arcs
    - ADMIN: Review  a PRST-AB paper

Dave Douglas

  Previous two weeks (Oct 26-Nov 9)
    - LERF: Fall two week restart/operations run (organization, documentation)
  Next two weeks (Nov 9-23)
    - LERF: Fall two week restart/operations run (organization, documentation),
      beam reanimation
    - LERF: energy recovery analysis for DarkLight - accommodating beam
      scattering in target (needs matching/coupling compensation as
      described above)
    - LERF: diagnostics/corrections package & operations procedures for
      DarkLight
    - LERF: Isotope kibitzing
    - MEIC: Cooler ERL design: need spec for longitudinal phase space,
      need to determine why "real" beam comes apart

Chris Tennant

  Previous two weeks (Oct 26-Nov 9)
    - LERF: operations
    - ASML: mostly completed various aperture studies for lattice
      3.0.0, still investigating some "mysteries" in results,
      computing uBI gain in compressor arcs
    - MEIC: investigating different mysteries (i.e. understanding
      behavior of transporting a magnetized beam in TStep/PARMELA)
  Next two weeks (Nov 9-23)
    - LERF: operations
    - ASML: repeat aperture study analysis for lattice 2.1 (if
      lattice becomes available and time is available)

Randy Gamage

  Previous two weeks (Oct 26-Nov 9)
    - MEIC: Longitudinal model development, elegant/esme comparisons,
      bunch merge/split parameterization
  Next two weeks (Nov 9-23)
    - MEIC: Longitudinal model development, continue bunch merge/split
      parameterization and optimization scans