Difference between revisions of "2019-10-25-LeadershipReports"

From Administrative
Jump to navigation Jump to search
Line 29: Line 29:
 
Alex Bogacz
 
Alex Bogacz
 
    
 
    
   Previous two weeks (Sept 30 - Oct 11)
+
   Previous two weeks (Oct 14 - Oct 25)  
      - Writing ERL’19 paper
 
      - Writing a CDR chapter on the LHeC ERL design
 
      - Preparing talks on 50 GeV ERL and PERLE for the LHeC/PERLE workshop at CERN
 
  Next two weeks (Oct 14 - Oct 25)
 
 
       - Finishing a CDR chapter on the LHeC ERL design
 
       - Finishing a CDR chapter on the LHeC ERL design
 
       - PRAB paper review
 
       - PRAB paper review
 
       - Attending nuSTORM mtg at CERN
 
       - Attending nuSTORM mtg at CERN
       - Attending Workshop on the LHeC, FCC-eh and PERLE, Chevennes de Bogis
+
       - Attending Workshop on the LHeC, FCC-eh and PERLE, Chavannes-de-Bogis
 +
  Next two weeks (Oct 28 - Nov 8)
 +
      - Alternative lattice for the LHeC ERL
 +
      - Invention disclosures review
 +
      - Appraisals
 +
      - Vac
 +
 
  
  
Line 44: Line 46:
 
Rui Li
 
Rui Li
 
    
 
    
   Previous two weeks (Sept 30 - Oct 11)
+
   Previous two weeks (Oct 14 - Oct 25)
       - Prepare presentation on "Collective Effects in JLEIC" for the EIC collaboration meeting at ANL
+
       - Discuss/explore Hassinski solution and Robinson instability with Bob Warnock (SLAC) and Marco Venturini (LBL)
       - Participate in the EIC Hadron Cooling Workshop in Fermilab (10/7-8) and the EIC Collaboration Meeting (10/9-11)
+
       - Participate in the ALS-U impedance meeting and discussions
       - Presented my talk at the EIC collaboration meeting, and had multiple discussions with colleagues at the meetings
+
       - Schedule/plan the next JLEIC impedance meeting and potential talks
   Next two weeks (Oct 14 - Oct 25)  
+
      - Assist ALS-U people to teach JLAB/ODU people on broadband impedance modeling using CST
       - Schedule and organize the next JLEIC Impedance Meeting
+
   Next two weeks (Oct 28 - Nov 8)  
       - Work on microwave instability simulation in the e-ring of JLEIC
+
       - Prepare and present JLEIC impedance studies at JLEIC R&D meeting
       - Write up technote on spectra for uneven bunch fill, which will play a role in the coupled bunch instability growth rate analysis.
+
      - Participate multi-lab (LBL/SLAC/APS/NSLS-II) monthly seminar on collective effects in electron storage rings (I'm asked
 +
        to present the next monthly seminar on collective effects in JLEIC)
 +
       - Continue my collaboration with ALS-U and SLAC on impedance and instability
 +
       - Finish writing up the technote on spectra for uneven bunch fill
 +
 
  
  
Line 62: Line 68:
 
       - Mostly coordinated with the people at DESIREE for the measurements they made for me on October 21, and 22.
 
       - Mostly coordinated with the people at DESIREE for the measurements they made for me on October 21, and 22.
 
       - Analyzed the data they sent me and worked to finalize the proposal for beam time which is due the 31st.
 
       - Analyzed the data they sent me and worked to finalize the proposal for beam time which is due the 31st.
     Next two weeks (Oct 14 - Oct 25)
+
     Next two weeks (Oct 28 - Nov 8)
 
       - I will submit the proposal
 
       - I will submit the proposal
 
       - Determine priorities for my work in the next two weeks.
 
       - Determine priorities for my work in the next two weeks.
Line 78: Line 84:
 
       - Participated in initial telecon about using ML for magnetized beams (with ANL, SLAC)
 
       - Participated in initial telecon about using ML for magnetized beams (with ANL, SLAC)
 
       - Start outline, initial sections for draft of SRF classifier paper (to be submitted for peer-review later in the year)
 
       - Start outline, initial sections for draft of SRF classifier paper (to be submitted for peer-review later in the year)
     Next two weeks (Oct 28 Nov 8)
+
     Next two weeks (Oct 28 - Nov 8)
 
       - Finish Accelerator Seminar talk
 
       - Finish Accelerator Seminar talk
 
       - Continue work on SRF classifier paper
 
       - Continue work on SRF classifier paper
Line 105: Line 111:
 
Max Bruker
 
Max Bruker
  
   Previous (Sept 30 - Oct 11)
+
   Previous (Oct 14 - Oct 25)
       - Prepared presentation for cooling workshop
+
       - Read up on electron cooling theory (but didn't get very far)
       - Finished Jspec simulations with current Heb lattice at different energies to evaluate cooling energy tradeoff
+
      - Got Radworker I certification
       - Attended cooling workshop and collaboration meeting
+
       - Cleaned up lattice plotting code
   Next (Oct 14 - Oct 25)
+
       - Contribution to DOE quarterly report on electron cooling
       - Find reason for alleged discrepancy between Jspec and theory / Fermilab cooler experience
+
   Next (Oct 28 - Nov 8)
       - Revisit weakly magnetized cooler
+
       - More electron cooling and collective effects theory
 
+
       - Become familiar with Kevin's work on electronics for the IMP experiment
 
 
  
  
Line 135: Line 140:
 
Bhawin Dhital
 
Bhawin Dhital
 
    
 
    
     Previous two weeks (Sept 30 - Oct 11)
+
     Previous two weeks (Oct 14 - Oct 25)
       - PWorking on longitudinal dynamics and stability in two energy storage ring cooler.
+
       -  
      - Working on simulation to get the longer bunch length in the cooling section.
+
     Next two weeks (Oct 28 - Nov 8)
      - Introducing harmonic cavity and bunching cavity in two energy ring to get the longer bunch length in the cooling section. Bunching cavity provides the focusing.
+
       -  
      - Results shows that we should go with shorter bunch length ~ 1 cm.
 
     Next two weeks (Oct 14 - Oct 25)
 
       - Will be working on longitudinal dynamics and stability in two energy storage ring
 
      - Making clear presentation based on calculation and simulations for future plan.
 
      - Meeting with Dr Krafft for more discussion.
 
      - Should go with chirping and de-chirping along with other scheme in two energy ring.
 
      - Working with new lattice for two energy storage ring.(Dr Fanglei Lin has designed the new lattice).
 
  
  
Line 151: Line 149:
 
Vasiliy Morozov
 
Vasiliy Morozov
  
     Previous two weeks (Sept 30 - Oct 11)
+
     Previous two weeks (Oct 14 - Nov 8)
 
       - Optimization of the IBS rate in the ion collider ring -IR design: modeling of the detector region in GEMC and GEANT4 -Preparation for and attendance of the EIC
 
       - Optimization of the IBS rate in the ion collider ring -IR design: modeling of the detector region in GEMC and GEANT4 -Preparation for and attendance of the EIC
 
         collaboration meeting     
 
         collaboration meeting     
Line 165: Line 163:
 
Amy Sy
 
Amy Sy
  
     Previous two weeks (Sept 25 - Oct 11)
+
     Previous two weeks (Oct 14 - Oct 25):
      - Some preliminary work preparing for LBNF/DUNE review, including review of prior report and teleconference with Beamline L2 manager.
 
      - Continued work on heavy ion stripping chicane design in MADX and TRACK. Testing stripping module in TRACK and resultant transport through the nominal ion linac. Working on
 
        an insertion to ion linac as laid out in chicane schematic in preCDR. Current ion linac design has stripping location before quad triplet - looking at optics at this
 
        position, modifications for Pb30+ versus stripped Pb67+, and other parameters as part of the chicane design.
 
      - Remote attendance of EIC Accelerator Collaboration Meeting.
 
    Next two weeks (Oct 14 - Oct 25)
 
 
       - DOE pre-review teleconference for planning for LBNF/DUNE review.
 
       - DOE pre-review teleconference for planning for LBNF/DUNE review.
      - Continued work on linac optimization for reduced transverse emittance.
 
 
       - Continued work on heavy ion stripping chicane design in TRACK and PyORBIT.
 
       - Continued work on heavy ion stripping chicane design in TRACK and PyORBIT.
       - Continued work on TRACK vs PyORBIT comparison for linac simulations.
+
       - Continued work on TRACK vs PyORBIT comparison for linac simulations. Compared longitudinal phase behavior at the
 +
        transition between QWR and HWR sections in TRACK to the PyORBIT case, and will need to create a JLEIC-specific module
 +
        to properly evaluate this parameter, rather than relying on the SNS linac bunch module that is currently being used.
 +
        Currently refining the RF cavity parameters in PyORBIT to better match the TRACK simulations, including working with
 +
        multiple RF gaps per cavity for better approximation of field maps used in TRACK. 
 +
    Next two weeks (Oct 28 - Nov 8)
 +
      - Participating in the DOE independent project review of LBNF/DUNE.
 +
      - Continued work on ion linac simulations.
 +
 
  
  
Line 212: Line 211:
 
Randi Gamage
 
Randi Gamage
  
     Previous two weeks (Sept 30 - Oct 11)
+
     Previous two weeks (Oct 14 - Oct 25)
       - Multipole correction optimization
+
       - Next step of the orbit correction - correcting the beta function distortion
       - Re-tune ion collider lattice to fix dispersion at IP
+
       - Investigating different multipole correction schemes.
       - EIC hadron cooling workshop(at Fermilab) and EIC collaboration meeting(at Argonne lab)
+
       - Jlab contribution to the quarterly report
     Next two weeks (Oct 14 - Oct 25)
+
     Next two weeks (Oct 28 - Nov 8)
       - Continue to optimize the orbit correction
+
       - Add ion quad data in to DA studies (from last week)
      - Continue multipole correction and DA studies (New ion quad data from GianLuca at LBNL)
+
       - Continue to correct beta function distortion
       - Add optics correction
+
      - Continue to investigate different Multipole corrector schemes
 +
 
 
   
 
   
  
Line 255: Line 255:
 
Dennis Turner
 
Dennis Turner
  
     Previous two weeks (Sept 30 - Oct 11)
+
     Previous two weeks (Oct 14 - Oct 25)
       - 12GeV PRAB paper - Submitted two sections to SharePoint; started work on a third.
+
       - Submitted ATLis for MultiWire testing.
       - Received new computer and set it up with elegant, MacPorts, etc.
+
       - qsUtility improvements.
       - Attended AI lunch meetings
+
       - Submitted ATLis for 6MeV matching.
       - Continued work on Multiwire
+
       - Completed 130keV emittance measurements.
            - While working on MultiWire, saw opportunity for improvement to qsUtility and chased that squirrel.  
+
       - Discussed handing some of my non-CASA software tools back to HLA with Michele.
       - Emailed Janet to fix my timesheet so that it no longer thinks I'm on the Ops shift schedule.
+
       - Discussed future plans for rfHealthCheck with Clyde.
       - Completed the new Laser Safety Training.
+
       - Generated elegant layout for Injector upgrade.
       - Attended BTeam meeting
+
       - Had a CED workspace created for the Injector upgrade
            - Generated qsUtility measurement and matching templates for IHA0L03.
+
      - Setup computer with Keras and TensorFlow to start exploring ML.
       - Attended Injector Upgrade Meeting
+
       - Attended BTeam, 12GeV paper, Injector Upgrade, and AI lunch meetings.  
            - Met with Joe Grames to walk the Injector beamline and discuss the upgrade plan.
+
     Next two weeks (Oct 28 - Nov 8)
            - Touched base with Alicia to talk about GPT modeling, etc.
+
      - Analyze 130keV emittance measurement data.
       - Helped the new operator get started with CSUE and software development so he can perhaps take over some of my software tools that are not related to CASA.
+
       - Continue work on assigned sections for the 12GeV PRAB paper.
      - Sick day 10/7
+
       - Configure optics for the Injector upgrade elegant deck.
     Next two weeks (Oct 14 - Oct 25)
+
       - Start populating the Injector upgrade CED workspace.
       - Continue work on assigned sections of the 12GeV PRAB paper.
+
      - Continue exploring ML with Keras and TensorFlow.
       - Get more familiar with the upgraded Injector beamline, get started with elegant deck, etc.
 
       - Finish MultiWire
 
            - Create templates for all the Hall lines and Injector.
 
            - Write ATLis for testing.
 
            - Write documentation.
 
 
       - Finish QTSnyder upgrade and write ATLis for testing
 
       - Finish QTSnyder upgrade and write ATLis for testing
      - Make sure qsUtility works with Injector solenoids once and for all.
 
      - Resurrect work on rayTrace.
 
 
       - Attend BTeam, 12GeV paper, Injector Upgrade, and AI lunch meetings.  
 
       - Attend BTeam, 12GeV paper, Injector Upgrade, and AI lunch meetings.  
 +
  
 
   
 
   
Line 288: Line 282:
 
He Zhang
 
He Zhang
  
     Previous two weeks (Oct 14 - Oct 28)     
+
     Previous two weeks (Oct 14 - Oct 25)     
 
       - JSPEC - Updated the TWISS parameter loading function to improve the flexibility. Now the data column MUX and MUY are
 
       - JSPEC - Updated the TWISS parameter loading function to improve the flexibility. Now the data column MUX and MUY are
 
         not required since they are not used in IBS calculation. TWISS parameter tables missing DY nad DPY are acceptable since
 
         not required since they are not used in IBS calculation. TWISS parameter tables missing DY nad DPY are acceptable since
Line 346: Line 340:
 
LERF - Steve Benson  
 
LERF - Steve Benson  
 
   
 
   
     Previous two weeks (Sept 30 - Oct 11)
+
     Previous two weeks (Oct 14 - Oct 25)
       - Previous (Sept. 30-Oct. 11)
+
       - Submitted proposal for change of SOW for the Cooling FOA for IMP work
       - Analyzed R&D needs for EIC for W. Wittmer
+
       - Prepared quarterly report for Strong Cooling FOA project
       - Analyzed damping wiggler needs for the JLEIC electron storage ring
+
       - Prepared budget for isotope project quarterly and assist PI in submitting the report.
       - Prepared two talks for Hadron Cooling workshop
+
       - Prepared and gave talk on LERF Activities at the JLAAC meeting.
       - Attended Hadron Cooling workshop, gave two talks, chaired one session, and helped write up working group summary.
+
       - Set up seminars by Chris Tennant, Pavel Chevtsov, and Michael Famiano
       - Attended EIC Collaboration meeting.
+
      - Discussed non-beam hazards and Lock,Tag&Try issues with Laser Safety personnel.  
       - Had discussions with P. Piot about using AWA to do RF merge study
+
       - Reviewed Class 3R laser status int he LERF and disabled several unused lasers.
       - Set up seminar for Uttar Pudasaini.
+
       - Reviewed Isotope program and run plans with Operations Staff
     Next two weeks (Oct 14 - Oct 25)
+
       - Prepared AWPs for Cooling FOA project and Isotope production program.
      - Submit proposal for change of SOW for the Cooling FOA for IMP workAttend Hadron Cooling Workshop
+
     Next two weeks (Oct 28 - Nov 8)
 
       - Certify User Lab 4 in the LERF
 
       - Certify User Lab 4 in the LERF
      - Prepare quarterly report for Strong Cooling FOA project
 
      - Prepare budget for isotope project quarterly and assist PI in submitting the report.
 
 
       - Submit papers for ERL workshop
 
       - Submit papers for ERL workshop
 +
      - Assist in run to the 1G dump with CW beam.
 +
      - Work on punch list items for the Isotope ERR
 +
      - Get kicker coils for RF merge test completed
 +
      - Prepare slides for and the attend the NP Accelerator R&D PI Exchange meeting in Gaithersburg MD.
 +
  
  

Revision as of 17:31, 21 November 2019

Oct 2019 Report - Oct 14 - Nov 8 Director - Todd Satogata

Todd Satogata

  Previous two weeks (Oct 14 - Oct 25)
     - ADMIN 12 GeV PRAB paper planning
     - ADMIN JLAAC review (Oct 22-24)
     - ADMIN FY20 AWP planning
     - ADMIN Xelera SBIR support planning
     - JLEIC/ER@CEBAF JLAAC dry runs and planning
     - JLEIC FOA quarterly report planning
     - ODU PHYS854 teaching (with Geoff Krafft)
     - OPS Walk Hall D line, run readiness evaluation
     - OPS Pre-brief half-day operator meeting (Oct 21)
     - VACATION Oct 14, half-day Oct 25
  Next two weeks (Oct 28 - Nov 8)
     - ADMIN 12 GeV PRAB paper planning
     - ADMIN FY20 AWP planning
     - ADMIN Review PRAB paper
     - ADMIN Recommendation letters (Deepsana Shahi, Mike Lafky)
     - ER@CEBAF post-JLAAC planning for summer 2020 chicane install
     - JACOW Team Meeting travel preparation
     - IPAC'20 SPC/3 Meeting travel preparation
     - ODU PHYS854 teaching (with Geoff Krafft)


Alex Bogacz

  Previous two weeks (Oct 14 - Oct 25) 
     - Finishing a CDR chapter on the LHeC ERL design
     -	PRAB paper review
     -	Attending nuSTORM mtg at CERN
     -	Attending Workshop on the LHeC, FCC-eh and PERLE, Chavannes-de-Bogis
  Next two weeks (Oct 28 - Nov 8)
     - Alternative lattice for the LHeC ERL
     -	Invention disclosures review
     -	Appraisals
     -	Vac



Rui Li

  Previous two weeks (Oct 14 - Oct 25)
     - Discuss/explore Hassinski solution and Robinson instability with Bob Warnock (SLAC) and Marco Venturini (LBL)
     - Participate in the ALS-U impedance meeting and discussions
     - Schedule/plan the next JLEIC impedance meeting and potential talks
     - Assist ALS-U people to teach JLAB/ODU people on broadband impedance modeling using CST
  Next two weeks (Oct 28 - Nov 8) 
     - Prepare and present JLEIC impedance studies at JLEIC R&D meeting
     - Participate multi-lab (LBL/SLAC/APS/NSLS-II) monthly seminar on collective effects in electron storage rings (I'm asked
       to present the next monthly seminar on collective effects in JLEIC)
     - Continue my collaboration with ALS-U and SLAC on impedance and instability
     - Finish writing up the technote on spectra for uneven bunch fill



Edy Nissen

   Previous two weeks (Oct 14 - Oct 25)
     - Did some work with the LEB, trying to see if I can get more space in the lattice
     - Mostly coordinated with the people at DESIREE for the measurements they made for me on October 21, and 22.
     - Analyzed the data they sent me and worked to finalize the proposal for beam time which is due the 31st.
   Next two weeks (Oct 28 - Nov 8)
     - I will submit the proposal
     - Determine priorities for my work in the next two weeks.



Chris Tennant

   Previous two weeks (Oct 14 - Oct 25)
     - Accelerator Advisory Committee meeting (slide preparation/dry-run/talk)
     - Employee self-evaluations
     - Wrote draft of ML section for CEBAF PRAB paper
     - Preparing slides for Accelerator Seminar (11/14)
     - Participated in initial telecon about using ML for magnetized beams (with ANL, SLAC)
     - Start outline, initial sections for draft of SRF classifier paper (to be submitted for peer-review later in the year)
   Next two weeks (Oct 28 - Nov 8)
     - Finish Accelerator Seminar talk
     - Continue work on SRF classifier paper
     - CeC effort starting up in earnest again (?)
     - JLEIC cooler effort ramping up again



Accelerator R & D - Yuhong Zhang

Yuhong Zhang

  Previous two weeks (Sept 30 - Oct 11)
     - Worked on IBS
     - Studied 10^35 JLEIC
     - Work on DC cooler
     - Wrote slides for two talks in the EIC collaboration meeting 5. Attended EIC Hadron Cooling Workshop and EIC Collaboration 
  Next two weeks (Oct 14 - Oct 25)
     - Write slides for JLAAC review 
     - FOA quarterly report    
     - JLEIC R&S (IBS/cooling, DC cooler, IMP paper. etc)


Max Bruker

  Previous (Oct 14 - Oct 25)
     -	Read up on electron cooling theory (but didn't get very far)
     -	Got Radworker I certification
     -	Cleaned up lattice plotting code
     - Contribution to DOE quarterly report on electron cooling
  Next (Oct 28 - Nov 8)
     -	More electron cooling and collective effects theory
     -	Become familiar with Kevin's work on electronics for the IMP experiment



Fanglei Lin

  Previous two weeks (Oct 14 - Oct 25)
       - Worked on the storage ring cooler project, and provided a quarterly report
       - Revisiting electron top-off injection scheme for JLEIC
       - Miscellaneous: attended JLEIC R&D meeting, discussed introducing computation of DK depolarization rate using Zgoubi
         with Radiasoft collages, attended JLEIC general meeting, finished employee appraisal. 
  Next two weeks (Oct 28 - Nov 8)
       - Work on updating the interaction region design
       - Work on the storage ring cooler project



Bhawin Dhital

   Previous two weeks (Oct 14 - Oct 25)
     - 
   Next two weeks (Oct 28 - Nov 8)
     - 



Vasiliy Morozov

   Previous two weeks (Oct 14 - Nov 8)
     - Optimization of the IBS rate in the ion collider ring -IR design: modeling of the detector region in GEMC and GEANT4 -Preparation for and attendance of the EIC
       collaboration meeting     
   Next two weeks (Oct 14 - Oct 25)
     - Attending APS DNP meeting
     - Preparation for JLAAC meeting
     - Preparation for EINN meeting




Amy Sy

   Previous two weeks (Oct 14 - Oct 25):
     - DOE pre-review teleconference for planning for LBNF/DUNE review.
     - Continued work on heavy ion stripping chicane design in TRACK and PyORBIT.
     - Continued work on TRACK vs PyORBIT comparison for linac simulations. Compared longitudinal phase behavior at the 
       transition between QWR and HWR sections in TRACK to the PyORBIT case, and will need to create a JLEIC-specific module
       to properly evaluate this parameter, rather than relying on the SNS linac bunch module that is currently being used.
       Currently refining the RF cavity parameters in PyORBIT to better match the TRACK simulations, including working with
       multiple RF gaps per cavity for better approximation of field maps used in TRACK.  
   Next two weeks (Oct 28 - Nov 8)
     - Participating in the DOE independent project review of LBNF/DUNE.
     - Continued work on ion linac simulations.






Computational Physics - Yves Roblin
Yves Roblin

   Previous two weeks (Oct 14 - Oct 25)
     - CEBAF:
          - RAR reports 
          - Bteam preparation/meetings
          - AI meetings 
          - Optics for upcoming run
          - RF Pit meeting
          - Walking the beam line BSY/HALLA to reconcile with CED
          - Group meeting
     - JLEIC:
          - Beam-Beam meetings with Isurumali
          - Preparing for PI meeting
          - 4th quarter report prep for FOA        
     - OTHER
          - AWP preparations
          - Evaluations
          - SLLP meetings/prepare for presentation in november
   Next two weeks (Oct 28 - Nov 8)
     - Complete evaluations
     - Prepare optics for startup CEBAF
     - AI workshop local organizing committee meetings



Randi Gamage

   Previous two weeks (Oct 14 - Oct 25)
     - Next step of the orbit correction - correcting the beta function distortion 
     - Investigating different multipole correction schemes.
     - Jlab contribution to the quarterly report
   Next two weeks (Oct 28 - Nov 8)
     - Add ion quad data in to DA studies (from last week)
     - Continue to correct beta function distortion
     - Continue to investigate different Multipole corrector schemes 




River Huang

   Previous two weeks (Oct 14 - Oct 25)
     - Transparent Spin Mode using Zgoubi - OPERA field maps with snakes’ parallel (the snake currents were varied using a
       fitting procedure to adjust the snake axis to 0°) has been put into RHIC’s lattice. After precisely adjusting the total
       bending angle of all of the dipole magnets to sum up to 2π, we tried to realize the spin transparent in a simulation
       for the RHIC’s configuration: all of the spin components are constant from turn to turn with a good numerical
       precision. After precisely adjusting, the spin resonance-strength was much smaller than before. Again, we also
       introduced random transverse quadrupole misalignments Δ𝑦 and dipole roll Δ𝜑 with rms magnitudes that provide 0.2 mm
       vertical closed orbit distortion ac-cording to a statistical model prediction. Averaging over all seeds gives a rms
       vertical closed orbit excursion of about 0.18~mm.
     - CASA Beam-Beam package - We are working on coding to convert the symbolic expressions to python to solve nonlinear
       equations。 
   Next two weeks (Oct 28 - Nov 8)
      - Continue working on EIC project


Isurumali Neththikumara

   Previous two weeks ()
     - 
   Next two weeks ()
     - 



Dennis Turner

   Previous two weeks (Oct 14 - Oct 25)
     - Submitted ATLis for MultiWire testing.
     - qsUtility improvements.
     - Submitted ATLis for 6MeV matching.
     - Completed 130keV emittance measurements.
     - Discussed handing some of my non-CASA software tools back to HLA with Michele.
     - Discussed future plans for rfHealthCheck with Clyde.
     - Generated elegant layout for Injector upgrade.
     - Had a CED workspace created for the Injector upgrade
     - Setup computer with Keras and TensorFlow to start exploring ML.
     - Attended BTeam, 12GeV paper, Injector Upgrade, and AI lunch meetings. 
   Next two weeks (Oct 28 - Nov 8)
     - Analyze 130keV emittance measurement data.
     - Continue work on assigned sections for the 12GeV PRAB paper.
     - Configure optics for the Injector upgrade elegant deck.
     - Start populating the Injector upgrade CED workspace.
     - Continue exploring ML with Keras and TensorFlow.
     - Finish QTSnyder upgrade and write ATLis for testing
     - Attend BTeam, 12GeV paper, Injector Upgrade, and AI lunch meetings. 



He Zhang

   Previous two weeks (Oct 14 - Oct 25)     
     - JSPEC - Updated the TWISS parameter loading function to improve the flexibility. Now the data column MUX and MUY are
       not required since they are not used in IBS calculation. TWISS parameter tables missing DY nad DPY are acceptable since
       in many cases the ring does not have vertical dispersion. I’m also adding the function of calculation and output the
       IBS contribution elememt by element to the UI. The other relatively large change in progress is revising the cooling
       rate calculation and the particle model, so that the average cooling rate for varying electron bunch can be used in the
       particle model.   
     - Beam beam effect - Help Yun Luo to set up and test the simulations using BB3D with high order map tracking or
       symplectic tracking. Find and fixed a bug in the TPSA lib which happens when all the elements are zero in a DA vector
       and caused an error in symplectic tracking using the 2nd kind of generating function.  
   Next two weeks (Oct 28 - Nov 8) 
     - Start working on JSPEC benchmarking with Lanzhou experimental data.
     - Finish a few changes of JSPEC




Diagnostic Development - Kevin Jordan

Kevin Jordan

   Previous two weeks (Sept 30 - Oct 11)
     - 
   Next two weeks (Oct 14 - Oct 25)
     - 



Joe Gubeli

   Previous two weeks (Sept 30 - Oct 11)
     - Isotope Experiment – Uploaded 1F, 2F and 1X region drawings for beamline components to Document Control. Uploaded the shielding mechanical presentation to Document Control
       as well.
     - ITV7A09 – Received parts, assembled, aligned, documented and installed new imaging system for the 7A09 Viewer. 
   Next two weeks (Oct 14 - Oct 25)
     - Isotope Experiment – Work on completing the shielding and instrumentation for the experiment. Address items that comes out of the review
     - Halo monitor – Finish aligning the camera/fiber optics and install it on LDRDS




Michael Tiefenback

   Previous two weeks ()
     - 
   Next two weeks ()
     - 



CASA Fellows
LERF - Steve Benson

   Previous two weeks (Oct 14 - Oct 25)
     - Submitted proposal for change of SOW for the Cooling FOA for IMP work
     - Prepared quarterly report for Strong Cooling FOA project
     - Prepared budget for isotope project quarterly and assist PI in submitting the report.
     - Prepared and gave talk on LERF Activities at the JLAAC meeting.
     - Set up seminars by Chris Tennant, Pavel Chevtsov, and Michael Famiano
     - Discussed non-beam hazards and Lock,Tag&Try issues with Laser Safety personnel. 
     - Reviewed Class 3R laser status int he LERF and disabled several unused lasers.
     - Reviewed Isotope program and run plans with Operations Staff
     - Prepared AWPs for Cooling FOA project and Isotope production program.
   Next two weeks (Oct 28 - Nov 8)
     - Certify User Lab 4 in the LERF
     - Submit papers for ERL workshop
     - Assist in run to the 1G dump with CW beam.
     - Work on punch list items for the Isotope ERR
     - Get kicker coils for RF merge test completed
     - Prepare slides for and the attend the NP Accelerator R&D PI Exchange meeting in Gaithersburg MD. 




Andrew Hutton

   Previous two weeks (Sept 30 - Oct 11)
     - I spent most of my time organizing a response to the Isotope ERR. In addition;, I prepared my talk for AMICI and helped Yuhong with his talk on IBS.    
   Next two weeks (Oct 14 - Oct 25)
     - Attended the AMICI meeting in Saclay and gave my closing report from the Industrial Advisory Board, of which I am the Chairman.  
     - Now I am on vacation until the middle of next week.  I will be at the LHeC/PERLE at the end of next week.