Difference between revisions of "2019-12-5-LeadershipReports"

From Administrative
Jump to navigation Jump to search
 
Line 155: Line 155:
 
       - Presented the update on \ Two Energy Storage Ring Cooler" in \ High Innovative Cooling " meeting at CASA on Dec 06, 2019.
 
       - Presented the update on \ Two Energy Storage Ring Cooler" in \ High Innovative Cooling " meeting at CASA on Dec 06, 2019.
 
     Next two weeks (Dec 9 - Dec 20)
 
     Next two weeks (Dec 9 - Dec 20)
       - Modi�cation of lattice to adjust the phase advance from the decelerating cavity to the accelerating cavity to be exactly 2*n*pi(Fanglei
+
       - Modifcation of lattice to adjust the phase advance from the decelerating cavity to the accelerating cavity to be exactly 2*n*pi(Fanglei
 
         mentioned that she has already done this for electron storage ring and she is going to apply the same technique for a two energy storage
 
         mentioned that she has already done this for electron storage ring and she is going to apply the same technique for a two energy storage
 
         ring.)
 
         ring.)
Line 197: Line 197:
 
'''Computational Physics - Yves Roblin'''<br>
 
'''Computational Physics - Yves Roblin'''<br>
 
Yves Roblin
 
Yves Roblin
     Previous two weeks (Oct 28 - Nov 8)
+
     Previous two weeks (Nov 25 - Dec 6)
 
       - CEBAF:
 
       - CEBAF:
           - Bteam preparation/meetings
+
           -  
          - Preparing and investigating alternate schemes for reduced linac gradients
 
          - Schedule and coordination for startup
 
 
       - JLEIC:
 
       - JLEIC:
           - FOA PI meeting at DOE
+
           -    
          - Re-scoping of FOA
 
          - Meeting with student every week
 
          - Meeting with CNU prof and JLab operations for use of drones in tunnel (AI)
 
          - Organizing committee for AI workshop   
 
 
       - OTHER
 
       - OTHER
           - Preparing lecture for SPIN2020 school. Initial gathering and writing of agenda
+
           -  
     Next two weeks (Oct 28 - Nov 8)
+
     Next two weeks (Dec 9 - Dec 20)
       - SLLP training in Chicago
+
       -  
      - Machine startup
 
  
  
Line 219: Line 212:
 
Randi Gamage
 
Randi Gamage
  
     Previous two weeks (Oct 28 - Nov 8)
+
     Previous two weeks (Nov 25 - Dec 6)
       - Next step of the orbit correction - correcting the beta function distortion
+
       -  
      - Investigating different multipole correction schemes.
+
     Next two weeks (Dec 9 - Dec 20)
      - Jlab contribution to the quarterly report
+
       -  
     Next two weeks (Nov 11 - Nov 22)
 
       - Continue to correct beta distortion
 
      - Continue different multipole correction schemes
 
 
   
 
   
  
Line 232: Line 222:
 
River Huang
 
River Huang
  
     Previous two weeks (Nov 11 - Nov 22)
+
     Previous two weeks (Nov 25 - Dec 6)
       - Transparent Spin Projet - In order to test the theoretical prediction, we introduced different cases of misalignments in RHIC lattice
+
       - Continue working on EIC project
        configuration and we obtained the spin field direction and the resonance strength by fitting the data to offset spin curves. The
 
        obtained resonance strength was consistent with the theoretical prediction. The spin field was close to horizontal as expected. We plan
 
        to report these results on IPAC2000.
 
      - CASA Beam-Beam package - In order to generate or deal with users’ own data for different phase definitions, we completed a Python code
 
        and added it into CASA Beam-Beam package. We revised BeamBeam3D (BB3D) so that BB3D can track all detail changes of a particle phase-
 
        coordinate.
 
 
     Next two weeks (Nov 25 - Dec 6)
 
     Next two weeks (Nov 25 - Dec 6)
      - Continue working on EIC project
+
      -
  
  
Line 247: Line 231:
 
Isurumali Neththikumara
 
Isurumali Neththikumara
  
     Previous two weeks (Oct 28 - Nov 8)
+
     Previous two weeks (Nov 25 - Dec 6)
       - Edited the script to output 6-D coordinates of a specific particle.
+
       -  
     Next two weeks (Nov 11 - Nov 22)
+
     Next two weeks (Dec 9 - Dec 20)
       - Calculation of Lyapunov exponent using the data obtained from BB3D simulations.
+
       -  
  
  
Line 305: Line 289:
 
Kevin Jordan
 
Kevin Jordan
  
     Previous two weeks (Oct 28 - Nov 8)
+
     Previous two weeks (Nov 25 - Dec 6)
 
       -  
 
       -  
     Next two weeks (Nov 11 - Nov 22)
+
     Next two weeks (Dec 9 - Dec 20)
 
       -  
 
       -  
  
Line 331: Line 315:
 
Michael Tiefenback
 
Michael Tiefenback
  
     Previous two weeks ()
+
     Previous two weeks (Nov 25 - Dec 6)
 
       -  
 
       -  
     Next two weeks ()
+
     Next two weeks (Dec 9 - Dec 20)
 
       -  
 
       -  
  
Line 363: Line 347:
 
Andrew Hutton
 
Andrew Hutton
 
   
 
   
     Previous two weeks (Nov 11 - Nov 22)
+
     Previous two weeks (Nov 25 - Dec 6)
      - Lost a fair amount of time due to (very) minor surgery, pre-op and post-op visits, etc.  I will survive! 
 
      - On November 12, I attended a VNECA meeting on Richmond to approve the draft annual report (I sent a copy to Stuart, Andrei and Todd). 
 
        We are moving forward on closing out the Isotope ERR items; we will have had two meetings on this as well as a lot of behind the scenes
 
        cajoling. 
 
      - I discussed with Doug Wells, our isotope collaborator at NMT, a new FOA for Isotopes which is only available to Universities.  It was
 
        agreed that NMT would take the lead on this.  I discussed this with Stuart and got his blessing to proceed.  Our part would be
 
        irradiating targets prepared at NMT, which would then be shipped offsite to VCU for separation.  Chemists from NMT would participate in
 
        the separation.  We also discussed the follow-on Isotope FOA that currently funds us; Doug will develop a short list of isotopes that we
 
        could address, and we would then discuss this list with Ethan Balkin, DOE-ONP Isotope Program Manager, to gauge the level of interest.
 
        We expect this FOA to come out in July 2020. 
 
      - I developed and presented my idea for asynchronous electron cooling for JLEIC.  I now don’t think this is the best solution, but I was
 
        pleased to generate discussion that hopefully will lead to improved understanding of the cooling process. 
 
    Next two weeks (Nov 25 - Dec 6)
 
 
       - We hope to have CW beam to the 1G dump (credit to Kevin, Steve and Joe).  I also hope to be able to submit demonstration that we have
 
       - We hope to have CW beam to the 1G dump (credit to Kevin, Steve and Joe).  I also hope to be able to submit demonstration that we have
 
         met all of the ERR items and receive beam authorization for the first 1kW isotope irradiation.   
 
         met all of the ERR items and receive beam authorization for the first 1kW isotope irradiation.   
 
       - On December 3, i (and Todd) will be on a conference call to advise the Madison Accelerator Lab.   
 
       - On December 3, i (and Todd) will be on a conference call to advise the Madison Accelerator Lab.   
       - I will continue to look at improving the JLEIC cooling.
+
       - I will continue to look at improving the JLEIC cooling.
 +
    Next two weeks (Dec 9 - Dec 20)
 +
      -

Latest revision as of 17:39, 14 January 2020

Dec 5 2019 Report - Nov 25 - Dec 20 Director - Todd Satogata

Todd Satogata

  Previous two weeks (Nov 25 - Dec 6)
     - ADMIN 12 GeV PRAB paper planning/writing
     - MGMT Continue annual appraisals, AWP updates
     - JLEIC planning and organization, cooling studies
     - JACOW Team meeting preparations
     - IPAC'20 SPC/3 preparations, absract submissions
     - OPS CEBAF startup support
     - ODU PHYS854 teaching (with Geoff Krafft)
     - Madison Accelerator Lab annual telecon (Dec 2)
     - HOLIDAY (Nov 28-29, Thankgiving)
     - JACOW Team Meeting (Nov 30-Dec 7, attended remotely)
  Next two weeks (Dec 9 - Dec 20)
     - ADMIN 12 GeV PRAB paper planning/writing
     - MGMT Complete annual appraisals, AWP updates
     - JLEIC planning and organization, transfer line start
     - JLEIC ICR BPM start evaluation, calculations
     - JACOW Post-Team Meeting info transfer to new Directors
     - IPAC'20 SPC/3 preparations, abstract QA/reclassification
     - OPS CEBAF ops support, Hall D procedures development
     - ODU PHYS854 final exam (with Geoff Krafft)
     - VACATION (Dec 19-20)




Alex Bogacz

  Previous two weeks (Nov 25 - Dec 6) 
     - Lectures/Homework for USPAS’20
     -	PRAB article review
     -	Thanksgiving
     -	Optimized Spr/Rec design for the LHeC ERL
     -	Invention  disclosures review
  Next two weeks (Dec 9 - Dec 20)
     - Lectures for USPAS’20
     -	PERLE magnet specs, field quality 
     -	CESR hardbend specs and drawings
     -	Vacation




Rui Li

  Previous two weeks (Nov 25 - Dec 6)
     - Coordinate presentations for the next JLEIC impedance meeting
     - Write and submitted 3 abstracts for IPAC20
     - Continue with my analysis on the spectra of uneven bunch distribution pattern
  Next two weeks (Dec 9 - Dec 20) 
     - Organize JLEIC impedance meeting on 11/11
     - Finish writing up the technote on spectra for uneven bunch fill
     - Write abstracts for IPAC 2020
     - Continue my understanding of coupled bunch instability and feedback systems
     - Organize the impedance meeting in December



Edy Nissen

   Previous two weeks (Nov 25 - Dec 6)
     - I will be on extended medical leave
   Next two weeks (Dec 9 - Dec 20)
     - I will be on extended medical leave
     - I will put a little bit of time in to update my pre-proposal for for the DOE Early Career Award.



Chris Tennant

   Previous two weeks (Nov 25 - Dec 6)
     - Thanksgiving break
     - Continue with PRAB draft
     - Found issues with tsfresh and have begun recomputing features (time consuming!) for SRF fault classifier models
     - Meeting with individuals and as group for identifying AI projects in Accelerator Division
     - SBIR Phase II coordination with RadiaSoft (meeting with J. Edelen, Kelly Webster, Deborah Dowd, budgets, letter of support, etc.)
     - Prep for LDRD Postdoc interviews
   Next two weeks (Dec 9 - Dec 20)
     - Follow-up meeting to identify AI opportunities in Accelerator Division (in preparation for DOE presentation next month)
     - Telecon about a proposal to NSF for a AI Research Institute funds
     - Meeting with CNU about mobile (robot-based) diagnostic
     - Presentation at AI Lunch Series on "Problem of the Quarter 02" solution
     -	LDRD Postdoc candidate interviews (3)





Accelerator R & D - Yuhong Zhang

Yuhong Zhang

  Previous two weeks (Nov 25 - Dec 6)
     - Thanksgiving break
  Next two weeks (Dec 9 - Dec 20)
     - 


Max Bruker

  Previous (Nov 25 - Dec 6)
     -	Preparations for IMP experiment
          - Improved dithering data analysis
          - Set up tools for Schottky spectrum analysis
  Next (Dec 9 - Dec 20)
     -	Perform IMP experiment or help remotely
     -	Vacation until end of year



Fanglei Lin

  Previous two weeks (Nov 25 - Dec 6)
       - Worked on the storage ring cooler project
       - Revisited the electron top-off injection scheme for JLEIC and reported in the JLEIC RD meeting
       - Preparing the teaching material for the Spin@USPAS class
       - Attended the JLEIC weekly meeting and presented an overview of JLEIC polarization design
       - Miscellaneous: attended the Innovative HE Cooling Project Status meeting, attended the Storage Ring Cooler meeting, attended JLEIC R&D
         meeting, attended JLEIC weekly meeting, attended a meeting for the Spin@USPAS class, attended the JLEIC transient beam loading    
         meeting, attended the JLEIC IR machine detector interface assessment meeting
  Next two weeks (Nov 25 - Dec 6)
       - Evaluate the IR design for various electron energies
       - Work on the storage ring cooler project
       - Work on teaching material for the Spin@USPAS class
       - Prepare and submit abstracts to IPAC2020




Bhawin Dhital

   Previous two weeks (Oct 28 - Nov 8)
     - Working on longitudinal dynamics and stability in two energy storage ring cooler.
     - Single and many particles tracking.
     - Understanding why particles get lost after few turns. Elegant simulation shows that transverse co-ordinates keep growing drastically and
       finally particle gets lost. M. Borland suggestion : \ Try to modify the lattice so that the phase advance from the decelerating cavity 
       to the accelerating cavity is n*2*pi, while avoiding total tunes close to integer or half-integer values."
     - Presented the update on \ Two Energy Storage Ring Cooler" in \ High Innovative Cooling " meeting at CASA on Dec 06, 2019.
   Next two weeks (Dec 9 - Dec 20)
     - Modifcation of lattice to adjust the phase advance from the decelerating cavity to the accelerating cavity to be exactly 2*n*pi(Fanglei
       mentioned that she has already done this for electron storage ring and she is going to apply the same technique for a two energy storage
       ring.)
     - Single and many particles tracking using new lattice after the lattice optimization / after the adjustment of phase advance between the
       cavities.
     - Stability in two energy storage ring cooler.
     - Radiation damping study.


Vasiliy Morozov

   Previous two weeks (Nov 25 - Dec 6)
     -Attended the EIC Ion Collider Research and Development Project (11/16 - 11/30/19)
   Next two weeks (Dec 9 - Dec 20)
     -Attended the EICUG Yellow Reports - Kick-off Meeting (12/11 - 12/13/19)




Amy Sy

   Previous two weeks (Nov 25 - Dec 6):
     - Submission of abstracts for presentation at IPAC2020 on H- intrabeam stripping estimates and stripping chicane design for the JLEIC ion
       linac.
     - Work on the DTL portion of the linac in PyORBIT.
     - Discussions on longitudinal Schottky signal analysis for the upcoming bunched beam cooling experiments.
   Next two weeks (Dec 9 - Dec 20)
     - Participation in the DOE Independent Project Review of Mu2e at Fermilab.
     - Offline Schottky signal analysis as necessary for the upcoming bunched beam cooling experiments.
     - Continued work on getting the DTL portion of the ion linac working in PyORBIT.






Computational Physics - Yves Roblin
Yves Roblin

   Previous two weeks (Nov 25 - Dec 6)
     - CEBAF:
          - 
     - JLEIC:
          -     
     - OTHER
          - 
   Next two weeks (Dec 9 - Dec 20)
     - 



Randi Gamage

   Previous two weeks (Nov 25 - Dec 6)
     - 
   Next two weeks (Dec 9 - Dec 20)
     - 


River Huang

   Previous two weeks (Nov 25 - Dec 6)
     - Continue working on EIC project
   Next two weeks (Nov 25 - Dec 6)
     -


Isurumali Neththikumara

   Previous two weeks (Nov 25 - Dec 6)
     - 
   Next two weeks (Dec 9 - Dec 20)
     - 



Dennis Turner

   Previous two weeks (Nov 25 - Dec 6)
     - Attended Accelerator AI projects meeting.
     - Addressed High Level Apps OPS-PRs generated during ops
         - eDT
         - DogCalc
         - QTSnyder
         - ArcSteer
     - Discussed with Tief a new RF cresting method using SLMs.
         - AIPINJ
             - Reconciled elegant deck with Alicia's GPT model.
     - 12GeV PRAB
         - Revised Optics Tuning section.
         - Completed first draft of Pathlength section.
     - Continued QTSnyder upgrade.
     - Attended BTeam, Injector Upgrade Modeling, AI Lunch meetings.
     - Took a few sick days for doctor appointments and such.
   Next two weeks (Dec 6 - Dec 20)
     - Provide Optics On-Call support through the end of the run.
     - Begin working with Tief on new cresting method with SLM.
     - Finish QTSnyder upgrade and write ATLis for testing.
     - Continue work on Injector upgrade elegant deck.
     - Continue work on assigned sections of the 12GeV PRAB paper.
     - Attend BTeam, Injector Upgrade, AI lunch, 12GeV PRAB meetings.
     - Continue exploring ML with Keras and TensorFlow, particularly for use at CEBAF.



He Zhang

   Previous two weeks (Nov 25 - Dec 6)     
     - Vacation most of the time.   
     - Submitted an abstract to IPAC’20 
   Next two weeks (Dec 9 - Dec 20) 
     - Finish refactor electron cooling rate calculation. Revisit the particle model and the turn-by-turn model. Make sure they work well. 
       Based on the turn-by-turn model, work on the simulations of sweeping effect and cooling with shifted electron beam for better cooling 
       on the edge of the ion beam.  




Diagnostic Development - Kevin Jordan

Kevin Jordan

   Previous two weeks (Nov 25 - Dec 6)
     - 
   Next two weeks (Dec 9 - Dec 20)
     - 



Joe Gubeli

   Previous two weeks (Nov 11 - Nov 22)
     - Isotope Experiment – Prepare for a two day run to the 1G dump. Worked with I&C to fix problems with viewers. Created a test setup for 
       the LERF Cameras. These cameras can now be set correctly (gain, black level, sharpness and gamma) as well as verified to work on the 
       Beamenizer.
     - Halo monitor – Run delayed a week.
     - HPWS – Printed a pneumatic cylinder holder for the air balancer. It and the cylinder was installed and tested.
   Next two weeks (Nov 11 - Nov 22)
     - Isotope Experiment – Help with the two day run to the 1G dump.
     - Halo monitor – Conduct the Halo Monitor experiment in the LERF.
     - DPIT – Discuss the future of the LERF Video system



Michael Tiefenback

   Previous two weeks (Nov 25 - Dec 6)
     - 
   Next two weeks (Dec 9 - Dec 20)
     - 



CASA Fellows
LERF - Steve Benson

   Previous two weeks (Nov 25 - Dec 6)
     - Assisted in run to the 1G dump with CW beam. Unfortunately we could not run beam.
     -	Reviewed SBIR
     - Reviewed IPAC 2020 abstracts
     -	Looked over new Phase II SBIRs
     - Met with diagnostics team to derive a plan for replacing the beam-a-nizer frame grabber at the LERF
     -	Met with the magnet group and came up with a strategy for the kicker coils for RF merge test
     -	Continued gathering documents for the ERR punch list
     -	Planned for another run to the 1G dump
   Next two weeks (Dec 9 - Dec 20)
     - Assist with the run to the 1G dump
     -	Certify User Lab 4 in the LERF
     -	Host Michael Famiano for Acc. seminar (with Joe Grames)
     -	Move excess equipment out of the LERF



Andrew Hutton

   Previous two weeks (Nov 25 - Dec 6)
     - We hope to have CW beam to the 1G dump (credit to Kevin, Steve and Joe).  I also hope to be able to submit demonstration that we have
       met all of the ERR items and receive beam authorization for the first 1kW isotope irradiation.  
     - On December 3, i (and Todd) will be on a conference call to advise the Madison Accelerator Lab.  
     - I will continue to look at improving the JLEIC cooling.  
   Next two weeks (Dec 9 - Dec 20)
     -