Difference between revisions of "GTS meeting 3 07 17"

From Ciswikidb
Jump to navigation Jump to search
 
Line 1: Line 1:
  
* Measured QE ~ 3.5% with -100 V Gun bias. Was about 0.4% with -1 kV bias. This is to be compared to QE ~ 3.9% measured in Prep Chamber with -280 V bias before moving the photocathode to Gun.
+
* Measured QE ~ 3.5% with -100 V Gun bias. Was about 0.4% with -1 kV bias. This is to be compared to QE ~ 3.9% in Prep Chamber with -280 V bias before moving the photocathode to Gun.
  
 
* Gun vacuum improved when opening the gate valve to beamline
 
* Gun vacuum improved when opening the gate valve to beamline

Latest revision as of 11:55, 7 March 2017

  • Measured QE ~ 3.5% with -100 V Gun bias. Was about 0.4% with -1 kV bias. This is to be compared to QE ~ 3.9% in Prep Chamber with -280 V bias before moving the photocathode to Gun.
  • Gun vacuum improved when opening the gate valve to beamline
  • Beam to F-Cup
  • Plan to complete the second part of beamline in two weeks. We will have one-week down in about 2 weeks to install the second DP can, solenoid, ion precipitator and the BNNT diagnostic station.