* New plan:
 
* New plan:
# Finish emittance measurements and try a larger laser size (x3) - August 21-23
+
# Finish emittance measurements, including a larger laser size (x3) August 21-23
# Attempt 5 mA (non-magnetized, then magnetized) - August 24 - August 31
+
# Attempt 5 mA (non-magnetized, then magnetized) August 24-31
# Shutdown - September 5:
+
# Shutdown September 5:
 
## Install new YAG screen at viewer 3
 
## Install new YAG screen at viewer 3
## New harp with 20 um tungsten wire (or fix fork on existing harp?)
+
## New harp with 20 µm tungsten wire (or fix fork on existing harp?)

Revision as of 09:02, 20 August 2017

  • Emittance Measurements - Yan


  • ASTRA Simulation - Sajini:
ASTRA simulations for the new magnetic field


  • New plan:
  1. Finish emittance measurements, including a larger laser size (x3) – August 21-23
  2. Attempt 5 mA (non-magnetized, then magnetized) – August 24-31
  3. Shutdown – September 5:
    1. Install new YAG screen at viewer 3
    2. New harp with 20 µm tungsten wire (or fix fork on existing harp?)