Difference between revisions of "GTS meeting 10 16 17"
Jump to navigation
Jump to search
Line 7: | Line 7: | ||
# Replace bad ion pump | # Replace bad ion pump | ||
# Activate new photocathode (new puck) with full active area | # Activate new photocathode (new puck) with full active area | ||
+ | |||
+ | |||
+ | * Map RadiaBeam steerer and measure the electrical characteristics (e.g., time constant) | ||
Revision as of 08:18, 16 October 2017
- Shutdown Plan:
- Install new YAG screen at viewer 3
- Fix existing harp and install 20 µm tungsten wire
- Add a new CEBAF-style harp with 10 µm tungsten wire (i.e, GTS will have two harps)
- Replace leaky vent valve
- Replace bad ion pump
- Activate new photocathode (new puck) with full active area
- Map RadiaBeam steerer and measure the electrical characteristics (e.g., time constant)
- Next Shutdown – January 2018:
- Install TE011 cavity
- High current runs: [1]