Difference between revisions of "GTS meeting 5 07 18"
Jump to navigation
Jump to search
(Created page with " * HV conditioning to 210 kV completed - Ready to tun at 200 kV * Ready to activate puck with moly substrate using 5 mm mask") |
|||
Line 4: | Line 4: | ||
* Ready to activate puck with moly substrate using 5 mm mask | * Ready to activate puck with moly substrate using 5 mm mask | ||
+ | |||
+ | |||
+ | * * Latest Drawing: | ||
+ | :: [[media:haysg_JL0038343-MAGNETIZED_BEAM_LDRD_ASSY_08May2018.pdf]] |
Revision as of 08:44, 1 June 2018
- HV conditioning to 210 kV completed - Ready to tun at 200 kV
- Ready to activate puck with moly substrate using 5 mm mask
- * Latest Drawing: