Difference between revisions of "February 28, 2013"
Jump to navigation
Jump to search
(6 intermediate revisions by the same user not shown) | |||
Line 2: | Line 2: | ||
== 12 GeV Commissioning Discussion == | == 12 GeV Commissioning Discussion == | ||
− | [[Media:130227_Commission_Discussion.pdf]] | + | |
+ | * [http://opsweb.acc.jlab.org/TJ3/12GeV_CEBAF/ Arne's live link to the 12 GeV Commissioning Plan] | ||
+ | * Commissioning Plan => [[Media:130227_Commission_Discussion.pdf]] | ||
+ | * Injector Startup Plan => [[Media:InjectorStartup_rev1.pdf]] | ||
== Mott Experiment Slide == | == Mott Experiment Slide == | ||
[[File:Mott_layout.jpeg|200px|thumb|left|Annotated layout for group discussion.]] | [[File:Mott_layout.jpeg|200px|thumb|left|Annotated layout for group discussion.]] |
Latest revision as of 09:32, 28 February 2013
EGG Meeting - ARC 428
12 GeV Commissioning Discussion
* Arne's live link to the 12 GeV Commissioning Plan * Commissioning Plan => Media:130227_Commission_Discussion.pdf * Injector Startup Plan => Media:InjectorStartup_rev1.pdf