1- RTP cell installation in 2019 Winter SAD
 
1- RTP cell installation in 2019 Winter SAD
 +
- optics spares (crystals/mounts)
 +
- HV system (2 units w/o pots)
 +
- cable from DAC to HV system
 +
- screen and equations app for DAC
 +
- UVa parts ready (cell + HVPS + dragon boards)
 +
- laser box top hat
 +
- schedule (RTP install, beam checkout, back out)
 +
- RTP monitoring plan during Spring run
 +
- 2019 CEBAF schedule
 +
- What else?
  
  

Revision as of 15:14, 4 December 2018

We will meet in TEDF 2559 Thursday December 6 at 4:00 pm EST.

For those calling in we'll use the Blue Jeans [1] audio conference system.

Phone number: 1-888-240-2560
Meeting ID: 3528502673#
Meeting URL: http://bluejeans.com/3528502673


Agenda:

1- RTP cell installation in 2019 Winter SAD - optics spares (crystals/mounts) - HV system (2 units w/o pots) - cable from DAC to HV system - screen and equations app for DAC - UVa parts ready (cell + HVPS + dragon boards) - laser box top hat - schedule (RTP install, beam checkout, back out) - RTP monitoring plan during Spring run - 2019 CEBAF schedule - What else?


2- New RTP EDM screen:

  1. HV controls
  2. ON/OFF