# Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses | # Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses | ||
# Add 5th solenoid to magnet screen | # Add 5th solenoid to magnet screen | ||
+ | |||
+ | |||
+ | * Modification to HV and Preparation chambers: | ||
+ | # Upgrade anode HV bias feed-through with 5 kV | ||
+ | # Remove anode and clean melted spot | ||
+ | # Fix Transverse Manipulator | ||
+ | # Fix Sb boat | ||
+ | # Clean chamber of Sb balls |
Revision as of 12:51, 7 January 2019
- List of beamline hardware modifications:
- Replace YAG screen on Viewer 1
- Replace Slit on Viewer 2 with holes assembly
- Replace two ion collectors with new ones
- Replace Harp fork (Tony)
- Remove modified DP can
- Remove Faraday Cup
- Remove bellow upstream of dump
- Install TE011 Cavity
- Install Deflecting Cavity
- Install new 5th solenoid
- Move DP can 1 to end of beamline
- All bellows at least 2.5 inch diameter
- Both gate valves are 2.5 inch-bore and will remain on beamline
- Remove gain-switched laser from GTS to LERF
- List of software and controls changes:
- Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses
- Add 5th solenoid to magnet screen
- Modification to HV and Preparation chambers:
- Upgrade anode HV bias feed-through with 5 kV
- Remove anode and clean melted spot
- Fix Transverse Manipulator
- Fix Sb boat
- Clean chamber of Sb balls