(Created page with "= '''List of beamline hardware modifications''' = # Replace YAG screen on Viewer 1 - '''''Done''''' # Replace Slit on Viewer 2 with holes assembly - '''''Done''''' # Replace t...") |
|||
(One intermediate revision by the same user not shown) | |||
Line 2: | Line 2: | ||
# Replace YAG screen on Viewer 1 - '''''Done''''' | # Replace YAG screen on Viewer 1 - '''''Done''''' | ||
# Replace Slit on Viewer 2 with holes assembly - '''''Done''''' | # Replace Slit on Viewer 2 with holes assembly - '''''Done''''' | ||
− | # Replace two ion collectors with new ones | + | # Replace two ion collectors with new ones - '''''Done''''' |
# Replace Harp fork (Tony) | # Replace Harp fork (Tony) | ||
# Remove modified DP can - '''''Done''''' | # Remove modified DP can - '''''Done''''' | ||
Line 15: | Line 15: | ||
# All bellows at least 2.5 inch diameter - '''''Done''''' | # All bellows at least 2.5 inch diameter - '''''Done''''' | ||
# Both gate valves are 2.5 inch-bore and will remain on beamline - '''''Done''''' | # Both gate valves are 2.5 inch-bore and will remain on beamline - '''''Done''''' | ||
− | # S&A on | + | # S&A on Thursday February 7, 2019 |
= '''List of hardware support''' = | = '''List of hardware support''' = |
Latest revision as of 12:28, 6 February 2019
List of beamline hardware modifications
- Replace YAG screen on Viewer 1 - Done
- Replace Slit on Viewer 2 with holes assembly - Done
- Replace two ion collectors with new ones - Done
- Replace Harp fork (Tony)
- Remove modified DP can - Done
- Remove Faraday Cup - Done
- Remove bellow upstream of dump - Done
- Remove LDR Harp arm and replace with ion-pump
- Rotate Viewer 3 to vertical - Done
- Install TE011 Cavity
- Install Deflecting Cavity - Done
- Install new 5th solenoid
- Move DP can 1 to end of beamline - Done
- All bellows at least 2.5 inch diameter - Done
- Both gate valves are 2.5 inch-bore and will remain on beamline - Done
- S&A on Thursday February 7, 2019
List of hardware support
- Install Deflecting Cavity power supply, MO and other parts
- Install TE011 Cavity readout cable and electronics
List of software and controls changes
- Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses
- Add 5th solenoid to magnet screen
Remove gain-switched laser (seed and pre-amp) from GTS to LERF
Install Brock's Magnetometer Cavity
Modification to HV and Preparation chambers
- Upgrade anode HV bias feed-through to 5 kV
- Remove anode and clean melted spot
- Fix Transverse Manipulator
- Fix Sb boat
- Clean Sb pellets off chamber