Difference between revisions of "GTS meeting 2 11 19"

From Ciswikidb
Jump to navigation Jump to search
 
(5 intermediate revisions by the same user not shown)
Line 1: Line 1:
 +
= '''Preliminary Drawings of T-Gun and 3D Views''' =
 +
:: [[media:haysg_JL0067948-MAGNETIZED_BEAM_THERMIONIC_GUN_ASSY_12Feb2019.pdf]]
 +
:: [[media:JL0067948_12Feb2019_VIEW1.JPG]]
 +
:: [[media:JL0067948_12Feb2019_VIEW2.JPG]]
 +
:: [[media:JL0067948_12Feb2019_VIEW3.JPG]]
 +
:: [[media:JL0067948_12Feb2019_VIEW4.JPG]]
 +
 +
 +
= '''New Ion Precipitator''' =
 +
:: [[media:6CF_Ion_Precipitator1.pdf]]
 +
 +
 +
= '''Beamline Survey''' =
 +
:: [[media:DT_F1907_T-Gun_Beamline_07Feb2019.pdf]]
 +
 +
 
= '''List of completed beamline hardware modifications''' =
 
= '''List of completed beamline hardware modifications''' =
# Replace YAG screen on Viewer 1  
+
# Replaced YAG screen on Viewer 1  
# Replace Slit on Viewer 2 with holes assembly  
+
# Replaced Slit on Viewer 2 with holes assembly  
# Replace two ion collectors with new ones  
+
# Replaced two ion collectors with new ones  
# Replace Harp fork (Tony)
+
# Replaced Harp fork (Tony)
# Remove modified DP can  
+
# Removed modified DP can  
# Remove Faraday Cup  
+
# Removed Faraday Cup  
# Remove bellow upstream of dump  
+
# Removed bellow upstream of dump  
# Remove LDR Harp arm and replace with ion-pump
+
# Removed LDR Harp arm and replace with ion-pump
# Rotate Viewer 3 to vertical  
+
# Rotated Viewer 3 to vertical  
# Install TE011 Cavity
+
# Installed TE011 Cavity
# Install Deflecting Cavity  
+
# Installed Deflecting Cavity  
# Install new 5th solenoid
+
# Installed new 5th solenoid
# Move DP can 1 to end of beamline  
+
# Moved DP can 1 to end of beamline  
 
# All bellows at least 2.5 inch diameter
 
# All bellows at least 2.5 inch diameter
 
# Both gate valves are 2.5 inch-bore
 
# Both gate valves are 2.5 inch-bore
 
# S&A on Thursday February 7, 2019
 
# S&A on Thursday February 7, 2019
 +
  
 
= '''List of hardware support''' =
 
= '''List of hardware support''' =

Latest revision as of 10:52, 11 March 2019

Preliminary Drawings of T-Gun and 3D Views

media:haysg_JL0067948-MAGNETIZED_BEAM_THERMIONIC_GUN_ASSY_12Feb2019.pdf
media:JL0067948_12Feb2019_VIEW1.JPG
media:JL0067948_12Feb2019_VIEW2.JPG
media:JL0067948_12Feb2019_VIEW3.JPG
media:JL0067948_12Feb2019_VIEW4.JPG


New Ion Precipitator

media:6CF_Ion_Precipitator1.pdf


Beamline Survey

media:DT_F1907_T-Gun_Beamline_07Feb2019.pdf


List of completed beamline hardware modifications

  1. Replaced YAG screen on Viewer 1
  2. Replaced Slit on Viewer 2 with holes assembly
  3. Replaced two ion collectors with new ones
  4. Replaced Harp fork (Tony)
  5. Removed modified DP can
  6. Removed Faraday Cup
  7. Removed bellow upstream of dump
  8. Removed LDR Harp arm and replace with ion-pump
  9. Rotated Viewer 3 to vertical
  10. Installed TE011 Cavity
  11. Installed Deflecting Cavity
  12. Installed new 5th solenoid
  13. Moved DP can 1 to end of beamline
  14. All bellows at least 2.5 inch diameter
  15. Both gate valves are 2.5 inch-bore
  16. S&A on Thursday February 7, 2019


List of hardware support

  1. Install Deflecting Cavity power supply, MO and other parts
  2. Install TE011 Cavity readout cable and electronics


List of software and controls changes

  1. Re-program SCAM to allow for 1 Hz and 50 ns macro-pulses
  2. Add 5th solenoid to magnet screen


Re-install gain-switched laser (seed and pre-amp) in GTS