Difference between revisions of "GTS meeting 9 30 19"

From Ciswikidb
Jump to navigation Jump to search
(Created page with "== (1) Get GTS back to operational == To Fix List (to get GTS running): * Glassman PSS Chassis (Service request to Omar - Carlos) * LCW Chassis (Sarin/ Mike Todd - follow up...")
 
 
(3 intermediate revisions by the same user not shown)
Line 4: Line 4:
  
 
* Glassman PSS Chassis (Service request to Omar - Carlos)
 
* Glassman PSS Chassis (Service request to Omar - Carlos)
* LCW Chassis (Sarin/ Mike Todd - follow up)
+
* LCW Chassis (Sarin- Fay follow up)
* Turbo (Replacement part for display - Bubba/Fay)
+
* Spellman (should arrive today)
* Spellman (Augistine/ Riad)
 
 
* Picoammeter x2? (Pete Francis in hand - sent for fix)
 
* Picoammeter x2? (Pete Francis in hand - sent for fix)
 +
* Viewers insertion boxes bad
  
 
To Check:
 
To Check:
* Viewers (Operation - and cameras) (Viewer software - contact Brian Freeman)(??IOC reset?? Tony Delacruz)
+
 
 
* Magnets (IOC check)
 
* Magnets (IOC check)
* Harp (electronics)
+
* Cathode solenoid - power supply
 +
 
 +
Good
 +
* Harp (fuse replaced)
 
* Cavities (electronics)
 
* Cavities (electronics)
* Cathode solenoid - power supply
+
* Turbo (fixed itself)
  
 
== (2) T-Gun Upgrades ==
 
== (2) T-Gun Upgrades ==
Line 31: Line 34:
 
* DC bias supply - set point fix (John Musson)
 
* DC bias supply - set point fix (John Musson)
 
* RF Cage (Mark/Fay)
 
* RF Cage (Mark/Fay)
* Back plate to allow increased cooling (open the hole)
+
* Back plate to allow increased cooling (open the hole - Fay talk to Vince)
* Move Xelera spellman to the GTS vault
+
* Software issues (Karl to contact Spellman again)
* Software issues (contact Spellman again)
+
* Install new fiber link & check (CW setting - Mark emailed company)
* Install new fiber link & check
+
* Need RF fiber from Karl for reflected power
  
 
== (3) ==
 
== (3) ==
Line 41: Line 44:
 
* Remove JLab spellman
 
* Remove JLab spellman
 
* Sort out the air and nitrogen lines.
 
* Sort out the air and nitrogen lines.
* Buy a shop vac (ask Bubba)
+
* Vacuum clean!

Latest revision as of 10:21, 30 September 2019

(1) Get GTS back to operational

To Fix List (to get GTS running):

  • Glassman PSS Chassis (Service request to Omar - Carlos)
  • LCW Chassis (Sarin- Fay follow up)
  • Spellman (should arrive today)
  • Picoammeter x2? (Pete Francis in hand - sent for fix)
  • Viewers insertion boxes bad

To Check:

  • Magnets (IOC check)
  • Cathode solenoid - power supply

Good

  • Harp (fuse replaced)
  • Cavities (electronics)
  • Turbo (fixed itself)

(2) T-Gun Upgrades

Need a safe gun - no devastating trips. Limit voltage to 135kV

RF cage - Features:

  • HV attaches through the back as designed.
  • G10 plate to support the HV cable
  • Nitrogen flow, also through G10 plate aimed at the back of the hot deck
  • Nitrogen flow, though the top of the cage, aimed at ceramic
  • Dimensions need to be longer than the table to keep E fields on the hot deck lower than 3MV/m (air breakdown)

To Fix/Modify:

  • DC bias supply - set point fix (John Musson)
  • RF Cage (Mark/Fay)
  • Back plate to allow increased cooling (open the hole - Fay talk to Vince)
  • Software issues (Karl to contact Spellman again)
  • Install new fiber link & check (CW setting - Mark emailed company)
  • Need RF fiber from Karl for reflected power

(3)

Housekeeping:

  • Remove RXX cables from GTS
  • Remove JLab spellman
  • Sort out the air and nitrogen lines.
  • Vacuum clean!