Difference between revisions of "GTS meeting 10 07 19"

From Ciswikidb
Jump to navigation Jump to search
 
(One intermediate revision by the same user not shown)
Line 3: Line 3:
 
== (1) Status ==
 
== (1) Status ==
  
* Gun assembled with ceramic and blank flange only. Pumping.
+
* Gun assembled with ceramic and blank flange only. Pumping. 4e-8 over 3 days (potential leak)
 
* RF cage complete
 
* RF cage complete
* Back plate modified and hot deck attached in 'run set-up'
+
* Back plate modified and hot deck attached in 'run set-up' (new bar placement an issue - might want to recess the bar)
 
* Electrode assembled and snow cleaned ready for installation
 
* Electrode assembled and snow cleaned ready for installation
* GTS clean
+
* GTS cleaner
  
 
== (2) Plans ==
 
== (2) Plans ==
Line 13: Line 13:
 
* Run up Xelera spellman connected to gun to 135kV
 
* Run up Xelera spellman connected to gun to 135kV
 
* If corona test good... break vacuum and install electrodes
 
* If corona test good... break vacuum and install electrodes
 +
* Leak check, Quick HV test, then bake, Kr processing as necessary
  
 
To Fix List (to get GTS running):
 
To Fix List (to get GTS running):
Line 27: Line 28:
 
* Cathode solenoid - power supply
 
* Cathode solenoid - power supply
  
== (4) T-Gun Upgrades ==
+
== (3) T-Gun Upgrades ==
  
 
To Fix/Modify:
 
To Fix/Modify:
Line 35: Line 36:
 
* Need RF fiber from Karl for reflected power
 
* Need RF fiber from Karl for reflected power
  
== (5) Housekeeping==
+
== (4) Housekeeping==
  
 
* Remove JLab spellman
 
* Remove JLab spellman
 
* Sort out the air and nitrogen lines.
 
* Sort out the air and nitrogen lines.

Latest revision as of 10:10, 7 October 2019

Limit voltage to 135kV

(1) Status

  • Gun assembled with ceramic and blank flange only. Pumping. 4e-8 over 3 days (potential leak)
  • RF cage complete
  • Back plate modified and hot deck attached in 'run set-up' (new bar placement an issue - might want to recess the bar)
  • Electrode assembled and snow cleaned ready for installation
  • GTS cleaner

(2) Plans

  • PSS cert
  • Run up Xelera spellman connected to gun to 135kV
  • If corona test good... break vacuum and install electrodes
  • Leak check, Quick HV test, then bake, Kr processing as necessary

To Fix List (to get GTS running):

  • Glassman PSS Chassis (Service request to Omar - Carlos)
  • LCW Chassis (Coleman today or tomorrow)
  • Spellman (needs further investigation)
  • Picoammeter x2? (Pete Francis in hand - sent for fix)
  • Viewers insertion boxes bad

To Check:

  • Magnets (IOC check)
  • Cathode solenoid - power supply

(3) T-Gun Upgrades

To Fix/Modify:

  • DC bias supply - set point fix (John Musson)
  • Software issues (Karl to contact Spellman again)
  • Install new fiber link & check (CW setting - Mark emailed company)
  • Need RF fiber from Karl for reflected power

(4) Housekeeping

  • Remove JLab spellman
  • Sort out the air and nitrogen lines.