Difference between revisions of "UITF Official Documents"
Jump to navigation
Jump to search
Line 5: | Line 5: | ||
UITF Accelerator Safety Envelope (ASE), submitted to DOE Site Office 10/8/2019 for approval, [[media:UITF ASE rev0.pdf]], [[media:ASE approval letter from Site Office.pdf]] | UITF Accelerator Safety Envelope (ASE), submitted to DOE Site Office 10/8/2019 for approval, [[media:UITF ASE rev0.pdf]], [[media:ASE approval letter from Site Office.pdf]] | ||
− | UITF Commissioning Plan [[media:UITF Commissioning | + | UITF Commissioning Plan approved 11_18_2019 [[media:UITF Commissioning Plan_approved.pdf]] |
Revision as of 10:42, 18 November 2019
Link to Thomas Jefferson National Accelerator Facility Final Safety Assessment Document, FSAD ver 8a: https://www.jlab.org/eshq/ProgramDocs
UITF Accelerator Operations Directive (UOD), UTF-AD-01-001, Revision 1, July 19, 2019 http://opsntsrv.acc.jlab.org/ops_docs/online_document_files/MCC_online_files/UITF_Operations_Directives.pdf
UITF Accelerator Safety Envelope (ASE), submitted to DOE Site Office 10/8/2019 for approval, media:UITF ASE rev0.pdf, media:ASE approval letter from Site Office.pdf
UITF Commissioning Plan approved 11_18_2019 media:UITF Commissioning Plan_approved.pdf