Line 25: | Line 25: | ||
*Move all but one of the rad monitors down the beamline. | *Move all but one of the rad monitors down the beamline. | ||
*With SCAM over-ride do the RF calibration. Keep valve closed. | *With SCAM over-ride do the RF calibration. Keep valve closed. | ||
+ | *Swap dry nitrogen for air on the vortex chiller input to back of hot deck. |
Latest revision as of 08:46, 5 December 2019
Status:
- Remote Bias supply working
- Corrector magnets installed
To Do:
- Get OSP signed by Kevin Banks
- Survey of gun again (at some point)
- RF Reflected power fiber link pair repair.
- Viewer repair - Chris Norris
- Replace anode picoampmeter - Fixed & working, comm problem.
- PSS Certification of GTS: Wednesday Dec 18, 8:30 to 12:00.
Update 12/5/19
- OSP signed.
Electrons made!! WOOHOO - Cut off voltage v. gun V plot.
- TOSP or ATLIS for DC bias supply and RF on. "Work control document". Ask Harry
- Move all but one of the rad monitors down the beamline.
- With SCAM over-ride do the RF calibration. Keep valve closed.
- Swap dry nitrogen for air on the vortex chiller input to back of hot deck.