Difference between revisions of "January 27, 2020 - Resource Meeting"
Jump to navigation
Jump to search
(Created page with "== Many good things happening, down the beam line... == ==ATLIS Tasks== * [http://devweb.acc.jlab.org/CSUEApps/uitflist/task/1273 Testing Wien HV Controls at UITF] ==Quic...") |
|||
Line 1: | Line 1: | ||
+ | == Announcements == | ||
+ | * Schedule | ||
+ | :: Run (now - May 6) | ||
+ | :: Phase 1 (May 6 - end of 2020) | ||
+ | :: Run (Jan 2021 - Sep 13 2021) | ||
+ | :: Phase 2 (Sep 13 - end of 2021) | ||
+ | |||
+ | * Mailing list => aipinj@jlab.org | ||
+ | |||
== Many good things happening, down the beam line... == | == Many good things happening, down the beam line... == | ||
Revision as of 12:29, 23 January 2020
Announcements
- Schedule
- Run (now - May 6)
- Phase 1 (May 6 - end of 2020)
- Run (Jan 2021 - Sep 13 2021)
- Phase 2 (Sep 13 - end of 2021)
- Mailing list => aipinj@jlab.org