Difference between revisions of "Document-Controlled Procedures and Assessments for UITF"

From Ciswikidb
Jump to navigation Jump to search
Line 3: Line 3:
 
these procedures are managed via document control with links to individual procedures as shown, but note documents can also be found using the search tool at this link: https://mis.jlab.org/mis/apps/mis_forms/search_operational_safety_procedure_forms.cfm
 
these procedures are managed via document control with links to individual procedures as shown, but note documents can also be found using the search tool at this link: https://mis.jlab.org/mis/apps/mis_forms/search_operational_safety_procedure_forms.cfm
  
HDIce target loading procedure OSP and THA  
+
Transferring(loading/removing)targets to/from the HDice IBC in cave-2 of the UITF, valid through 3/11/2023: https://mis.jlab.org/mis/apps/mis_forms/operational_safety_procedure_form.cfm?entry_id=94834  
  
HDIce Dump Magnet OSP and THA 
+
HDIce Dump Magnet  
  
UITF Cave2 ceiling roof tile removal OSP and THA
+
UITF Cave2 ceiling roof tile removal  
  
Cool and Operate HDice IBC and its superconducting magnets in cave2 of UITF ENP-18-80380-OSP [[File:Cool and Operate HDice IBC and its superconducting magnets in cave2 of UITF ENP-18-80380-OSP.pdf]]
+
Cool and Operate HDice IBC and its superconducting magnets in cave2 of UITF, valid through 10/27/2021: https://mis.jlab.org/mis/apps/mis_forms/operational_safety_procedure_form.cfm?entry_id=80380
  
UITF 748.5 MHz Buncher Cavity Operation at the Upgraded Injector Test Facility OSP and THA
+
UITF 748.5 MHz Buncher Cavity Operation at the Upgraded Injector Test Facility  
  
UITF Commissioning the QCM with RF, no beam acceleration, OSP and THA
+
UITF Commissioning the QCM with RF, no beam acceleration
  
UITF keV Beam Operations OSP and THA
+
UITF keV Beam Operations  
 
 
UITF sweep procedure, updated 1/3/2020, Document Number:SSG-PR-03-101,Rev. 20.0 [[File: UITF sweep procedure_SSG-PR-03-101_Rev. 20.0_January 3, 2020.pdf]]
 
  
 
UITF TOSP_high voltage conditioning a new photogun with 225kV Spellman supply
 
UITF TOSP_high voltage conditioning a new photogun with 225kV Spellman supply
Line 25: Line 23:
  
 
'''[[Other official documents managed via document-control, e.g., official assessments]]'''
 
'''[[Other official documents managed via document-control, e.g., official assessments]]'''
 +
 +
UITF sweep procedure, updated 1/3/2020, Document Number:SSG-PR-03-101,Rev. 20.0 [[File: UITF sweep procedure_SSG-PR-03-101_Rev. 20.0_January 3, 2020.pdf]]
  
 
Shielding Design Package from Vashek, approved by SCMB:  https://jlabdoc.jlab.org/docushare/dsweb/Get/Document-200615/JLAB-TN-18-020.pdf, [[media:UITF shielding package by Vashek Vylet.pdf]],  Photos of trench foam and lead shielding [[media:UITF trench shielding with photos.xls]]
 
Shielding Design Package from Vashek, approved by SCMB:  https://jlabdoc.jlab.org/docushare/dsweb/Get/Document-200615/JLAB-TN-18-020.pdf, [[media:UITF shielding package by Vashek Vylet.pdf]],  Photos of trench foam and lead shielding [[media:UITF trench shielding with photos.xls]]

Revision as of 11:31, 4 March 2020

OSPs, TOSPs and LOSPs for UITF

these procedures are managed via document control with links to individual procedures as shown, but note documents can also be found using the search tool at this link: https://mis.jlab.org/mis/apps/mis_forms/search_operational_safety_procedure_forms.cfm

Transferring(loading/removing)targets to/from the HDice IBC in cave-2 of the UITF, valid through 3/11/2023: https://mis.jlab.org/mis/apps/mis_forms/operational_safety_procedure_form.cfm?entry_id=94834

HDIce Dump Magnet

UITF Cave2 ceiling roof tile removal

Cool and Operate HDice IBC and its superconducting magnets in cave2 of UITF, valid through 10/27/2021: https://mis.jlab.org/mis/apps/mis_forms/operational_safety_procedure_form.cfm?entry_id=80380

UITF 748.5 MHz Buncher Cavity Operation at the Upgraded Injector Test Facility

UITF Commissioning the QCM with RF, no beam acceleration

UITF keV Beam Operations

UITF TOSP_high voltage conditioning a new photogun with 225kV Spellman supply

UITF Laser OSP


Other official documents managed via document-control, e.g., official assessments

UITF sweep procedure, updated 1/3/2020, Document Number:SSG-PR-03-101,Rev. 20.0 File:UITF sweep procedure SSG-PR-03-101 Rev. 20.0 January 3, 2020.pdf

Shielding Design Package from Vashek, approved by SCMB: https://jlabdoc.jlab.org/docushare/dsweb/Get/Document-200615/JLAB-TN-18-020.pdf, media:UITF shielding package by Vashek Vylet.pdf, Photos of trench foam and lead shielding media:UITF trench shielding with photos.xls

UITF SF6 tank pressure vessel assessment PS-ACC-17-001 can be found in DOCUSHARE at https://jlabdoc.jlab.org/docushare/dsweb/View/Collection-38867 (Note, the pressure vessel assessment for a similar SF6 tank used at CEBAF can be found at https://jlabdoc.jlab.org/docushare/dsweb/View/Collection-38417)

UITF QCM Vacuum Vessel assessment: File:QCM Vacuum Vessel Assessment by Gary Cheng.docx

UITF Final Approved ODH Assessment: File:UITF ODH Assessment.pdf and available at https://misportal.jlab.org/railsForms/oxygen_deficiency_reviews/74180/edit

UITF Industrial Hygiene Assessment for SF6 exposure: File:UITF SF6 assessment.pdf