Difference between revisions of "March 12, 2020 - ME/INJ/CIS"
Jump to navigation
Jump to search
Line 12: | Line 12: | ||
* Laser vacuum window? | * Laser vacuum window? | ||
: Caryn started evaluating | : Caryn started evaluating | ||
− | : | + | : Show layout of laser room, outrigger box, laser table |
+ | : Shukui, tight, how to fit optics, inside laser room? | ||
* 2I spools? | * 2I spools? | ||
: ME will order, need in time to a) weld capture solenoid, b) NEG coat | : ME will order, need in time to a) weld capture solenoid, b) NEG coat | ||
Line 18: | Line 19: | ||
: Design done, feedthroughs ordered, waiting on req to MDC | : Design done, feedthroughs ordered, waiting on req to MDC | ||
* Solenoid fixtures? | * Solenoid fixtures? | ||
+ | * What is p/n for the 25S IP? | ||
;Magnets | ;Magnets | ||
Line 46: | Line 48: | ||
* Omar, do you have BPM channel? | * Omar, do you have BPM channel? | ||
: Yes! | : Yes! | ||
+ | * Remove hall probe | ||
;Modelers | ;Modelers | ||
Line 62: | Line 65: | ||
;Commissioning | ;Commissioning | ||
* Plan for May gun work? | * Plan for May gun work? | ||
+ | * BPM job | ||
+ | :Receive can/feedthroughs | ||
+ | :Clean | ||
+ | :Degas | ||
+ | :Coat | ||
+ | :Check feedthroughs, assemble feedthroughs | ||
+ | :Leak check cans | ||
+ | :electrical measurement | ||
+ | :serialize | ||
+ | :report K's and center |
Revision as of 06:12, 11 March 2020
- Mechanical
- What is the bellows type count, how may 3" and 3.5"?
- Chris, do you have all as-founds you need?
- Use C channel everywhere and move pedestals ok?
- Anthony says yes, do it
- Carlos, send Shaun Wien feedthrough p/n
- SS or Al brackets?
- Use Al, now all 7-3/4" girder to beam line, girder holes whereever imagine support
- NEG chambers
- Detail Y- 10" flange, NEG's here
- Flip DP for IP beam left, modify for new NEG's?
- Laser vacuum window?
- Caryn started evaluating
- Show layout of laser room, outrigger box, laser table
- Shukui, tight, how to fit optics, inside laser room?
- 2I spools?
- ME will order, need in time to a) weld capture solenoid, b) NEG coat
- New BPM's
- Design done, feedthroughs ordered, waiting on req to MDC
- Solenoid fixtures?
- What is p/n for the 25S IP?
- Magnets
- Dipole
- Emerson backed out, Milhous quoting round/square, Lakshimi working on Jay's AT design
- Soleonids
- Joe M. what is status?
- Quads
- Have 3 QW, Mike testing 2 spare QW quads (capture on welded cross)
- Correctors
- Joe G make tally
- Wien
- Technicoil getting ready to wind
- PSS Kicker
- Met w/ Jerry, Lakshimi working on upgraded kicker to move 200 keV beam 1cm @ 30 cm w < 200 mA (March 9 layout)
- Orders
- Bellows - waiting on final count
- Right angle valves - we have 5 or 6, should be ok?
- Gun 10" flange - signed req for (2)
- BPM feedthroughs - ordered
- BPM cans - waiting on req to MDC
- Controls
- Chris, what cameras will you use, will they fit?
- Mark/Dave, do you have a plan for 2500W solid state chopper amps?
- Mark/Dave, do you have a plan for Brock prebuncher cavity/amp?
- Omar, do you have BPM channel?
- Yes!
- Remove hall probe
- Modelers
- Is the March 9th layout ok?
- Is the harp location OK for solenoid scans?
- Should a viewer remain at the harp location, should this be a YAG?
- Where else should YAG's go?
- Can a YAG go at the laser screen, I don't think so?
- Is the beam envelope OK for ways we run spin rotators?
- What are the currents and/or B's for the solenoids and quads?
- What are the power levels for existing or Brock prebuncher cavities, for 130 or 200 keV locations?
- Is distance from MFG1I04A to upstream corrector far enough? or move MFG1I04A downstream, how far?
- Jay is running cases
- Is the corrector/bpm downstream A1 useful?
- Commissioning
- Plan for May gun work?
- BPM job
- Receive can/feedthroughs
- Clean
- Degas
- Coat
- Check feedthroughs, assemble feedthroughs
- Leak check cans
- electrical measurement
- serialize
- report K's and center