Difference between revisions of "March 12, 2020 - ME/INJ/CIS"
Jump to navigation
Jump to search
Line 28: | Line 28: | ||
;Magnets | ;Magnets | ||
− | * | + | * Dipole |
+ | Emerson Tesla (people making solenoids) backed out, Milhous quoting round/square, Lakshimi working on Jay's AT design | ||
* Soleonids => Joe M. what is status? | * Soleonids => Joe M. what is status? | ||
First article complete ~April 20th: After you receive, can you mount to the fixture plate, do your QC checks, field map it?....then ASAP, a 2.5" spool goes through, flanges get welded on, cleaned, then Phil needs 100 hours to NEG coat the spool, then 4 weeks later on May 18th it goes into CEBAF, | First article complete ~April 20th: After you receive, can you mount to the fixture plate, do your QC checks, field map it?....then ASAP, a 2.5" spool goes through, flanges get welded on, cleaned, then Phil needs 100 hours to NEG coat the spool, then 4 weeks later on May 18th it goes into CEBAF, | ||
− | + | * Quads | |
− | * Quads | + | Have 3 QW, Mike testing 2 spare QW quads (capture on welded cross) |
− | * Correctors | + | * Correctors |
− | * Wien | + | Joe G tally |
− | * PSS Kicker | + | * Wien |
+ | Technicoil working on winding fixture | ||
+ | * PSS Kicker | ||
+ | Met w/ Jerry, Lakshimi working on upgraded kicker to move 200 keV beam 1cm @ 30 cm w < 200 mA (March 9 layout) | ||
;High Voltage | ;High Voltage |
Revision as of 07:43, 11 March 2020
- Mechanical
- What is the bellows type count, how may 3" and 3.5"?
- Chris, do you have all as-founds you need?
- Use C channel everywhere and move pedestals ok?
- Anthony says yes, do it
- Carlos, send Shaun Wien feedthrough p/n
- SS or Al brackets?
- Use Al, now all 7-3/4" girder to beam line, girder holes whereever imagine support
- NEG chambers
- Detail Y- 10" flange, NEG's here
- Flip DP for IP beam left, modify for new NEG's?
- Laser vacuum window?
- Caryn started evaluating
- Show layout of laser room, outrigger box, laser table
- Shukui, tight, how to fit optics, inside laser room?
- 2I spools?
- ME will order, need in time to a) weld capture solenoid, b) NEG coat
- New BPM's
- Design done, feedthroughs ordered, waiting on req to MDC
- Solenoid fixtures?
- What is p/n for the 25S IP?
- Viewer top-hats
- What is position when retracted for Y/Laser vs. crosses?
- How many spares, do we need more or different?
- Layout
- Dennis can convert Elegant to S&A coordinates
- Joe, map all the elements in an Excel file, punchlist CED & modifications
- Magnets
- Dipole
Emerson Tesla (people making solenoids) backed out, Milhous quoting round/square, Lakshimi working on Jay's AT design
- Soleonids => Joe M. what is status?
First article complete ~April 20th: After you receive, can you mount to the fixture plate, do your QC checks, field map it?....then ASAP, a 2.5" spool goes through, flanges get welded on, cleaned, then Phil needs 100 hours to NEG coat the spool, then 4 weeks later on May 18th it goes into CEBAF,
- Quads
Have 3 QW, Mike testing 2 spare QW quads (capture on welded cross)
- Correctors
Joe G tally
- Wien
Technicoil working on winding fixture
- PSS Kicker
Met w/ Jerry, Lakshimi working on upgraded kicker to move 200 keV beam 1cm @ 30 cm w < 200 mA (March 9 layout)
- High Voltage
- status of SS shed? (flange degased, ceramic welded, electrode cut, electrode polish, electrode mounted, fiducialize)
- status of Wien high voltage?
- Orders
- Bellows - waiting on final count
- Right angle valves - we have 5 or 6, should be ok?
- Gun 10" flange - signed req for (2)
- Order 10 kV feedthroughs
- BPM feedthroughs - ordered
- BPM cans - waiting on req to MDC
- Controls
- Chris, what cameras will you use, will they fit?
- Mark/Dave, do you have a plan for 2500W solid state chopper amps?
- Mark/Dave, do you have a plan for Brock prebuncher cavity/amp?
- Omar, do you have BPM channel?
- Yes!
- Remove hall probe
- Wien HV controls
- status of prototype test at UITF?
- layout in ISB racks?
- drops/penetrations?
- controls screens?
- Wien PS
- layout in ISB racks?
- drops?
- Modelers
- Is the March 9th layout ok?
- Is the harp location OK for solenoid scans?
- Should a viewer remain at the harp location, should this be a YAG?
- Where else should YAG's go?
- Can a YAG go at the laser screen, I don't think so?
- Is the beam envelope OK for ways we run spin rotators?
- What are the currents and/or B's for the solenoids and quads?
- What are the power levels for existing or Brock prebuncher cavities, for 130 or 200 keV locations?
- Is distance from MFG1I04A to upstream corrector far enough? or move MFG1I04A downstream, how far?
- Jay is running cases
- Is the corrector/bpm downstream A1 useful?
- Commissioning
- Plan for May gun work?
- BPM job
- Receive can/feedthroughs
- Clean
- Degas
- Coat
- Check feedthroughs, assemble feedthroughs
- Leak check cans
- electrical measurement
- serialize
- report K's and center