Line 20: | Line 20: | ||
;SAD/AIPINJ | ;SAD/AIPINJ | ||
− | * Preliminary layout complete | + | * Preliminary layout rev. 4 complete [[media:SONGSHEET AUGUST 21 dm comments.pdf]] |
* ME folders on M: contain complete drawings | * ME folders on M: contain complete drawings | ||
;Budgets | ;Budgets | ||
* Marcy - many thanks for RSR vacuum estimates | * Marcy - many thanks for RSR vacuum estimates |
Revision as of 14:37, 25 August 2020
- News
- CEBAF
- Any news from on-call?
- C goes to 1-pass for few days next week (Aug 31 - Sep 3) then returns
- LERF
- Andrei approved work at LERF to support the radio-isotope run
- Steve Benson's LERF punchlist media:200825_LERF_punchlist.docx
- Kevin's schedule media:200817_WAG.docx
- UITF
- Lock-up Thu/Fri for SRF Booster testing
- Matt is planning for Run 1 to begin on Mon Aug 31
- Safety
- Cat 2 PPE gear ordered for Joe, Bubba, Carlos, Marcy, Riad => pick-up on Thursday (otherwise 2 week delivery time)
- Cat 2 PPE size chart media:200825_CAT2PPE.jpg
- SAD/AIPINJ
- Preliminary layout rev. 4 complete media:SONGSHEET AUGUST 21 dm comments.pdf
- ME folders on M: contain complete drawings
- Budgets
- Marcy - many thanks for RSR vacuum estimates