Difference between revisions of "Aug 26, 2020"
Jump to navigation
Jump to search
Line 21: | Line 21: | ||
;SAD/AIPINJ | ;SAD/AIPINJ | ||
* Preliminary layout rev. 4 complete [[media:SONGSHEET AUGUST 21 dm comments.pdf]] | * Preliminary layout rev. 4 complete [[media:SONGSHEET AUGUST 21 dm comments.pdf]] | ||
− | * ME folders on M: contain complete drawings | + | * ME folders on M: contain complete drawings => will copy these occasionally to AIPINJ share folder |
;Budgets | ;Budgets | ||
* Marcy - many thanks for RSR vacuum estimates | * Marcy - many thanks for RSR vacuum estimates |
Revision as of 14:39, 25 August 2020
- News
- CEBAF
- Any news from on-call?
- C goes to 1-pass for few days next week (Aug 31 - Sep 3) then returns
- LERF
- Andrei approved work at LERF to support the radio-isotope run
- Steve Benson's LERF punchlist media:200825_LERF_punchlist.docx
- Kevin's schedule media:200817_WAG.docx
- UITF
- Lock-up Thu/Fri for SRF Booster testing
- Matt is planning for Run 1 to begin on Mon Aug 31
- Safety
- Cat 2 PPE gear ordered for Joe, Bubba, Carlos, Marcy, Riad => pick-up on Thursday (otherwise 2 week delivery time)
- Cat 2 PPE size chart media:200825_CAT2PPE.jpg
- SAD/AIPINJ
- Preliminary layout rev. 4 complete media:SONGSHEET AUGUST 21 dm comments.pdf
- ME folders on M: contain complete drawings => will copy these occasionally to AIPINJ share folder
- Budgets
- Marcy - many thanks for RSR vacuum estimates