Difference between revisions of "CIS Phase 1 work plans"

From Ciswikidb
Jump to navigation Jump to search
Line 17: Line 17:
  
 
; Tue – Fri
 
; Tue – Fri
*System disconnects
+
* Daniel will coordinate system disconnects (Magnets, Diagnostics, PSS, RF)
: Magnets
+
* Remove suitcase
: Diagnostics
 
: PSS
 
: RF
 
*Remove suitcase
 
  
 
=== Week 3 (Oct 5 - Oct 11) ===
 
=== Week 3 (Oct 5 - Oct 11) ===

Revision as of 07:53, 25 September 2020

Week 1 (Sep 21 - Sep 27)

Week 2 (Sep 28 - Oct 4)

Fri - Mon
  • CIS Gun Jobs
Wien electrode testing – 9am!!!
Gun HVPS lockout - DONE
Gun HV cable disconnect – DONE
Remove PIG – Coordinate w/ Neil for convenient time
Shukui - Laser outrigger table as-founds, remove components
Scott - Remove yellow box
Scott - Disconnect Decarad
Tue – Fri
  • Daniel will coordinate system disconnects (Magnets, Diagnostics, PSS, RF)
  • Remove suitcase

Week 3 (Oct 5 - Oct 11)

Week 4 (Oct 12 - Oct 18)

Week 5 (Oct 19 - Oct 25)

  • Injector is now in restricted access all the time
  • LOTO and system disconnects

Week X