Line 33: | Line 33: | ||
; Tue 9/29 – Fri 10/1 (updated 0915 9/28) | ; Tue 9/29 – Fri 10/1 (updated 0915 9/28) | ||
; <u>'''Tunnel Work'''</u> | ; <u>'''Tunnel Work'''</u> | ||
+ | |||
+ | {| class="wikitable" | ||
+ | |- | ||
+ | ! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2 | ||
+ | |- | ||
+ | | 4a - 8a || || I&C; 5a: Francis: BPMs, Cups, Apertures || I&C; 430a: Greenfield + Gonzales: vacuum labelling || I&C || I&C | ||
+ | |- | ||
+ | | 8a - 10a || CIS + SSG || RadCon: rad probes || RF: Prebuncher || || | ||
+ | |- | ||
+ | | 10a - 12p || CIS + SSG || DC Power || || || | ||
+ | |- | ||
+ | | 12p - 2p || CIS + SSG || DC Power || DC Power || DC Power || | ||
+ | |- | ||
+ | | 2p - 4p || CIS + SSG || DC Power || 3p: Moser: Safety Warden checks || || | ||
+ | |- | ||
+ | | 4p - ?? || || || || || | ||
+ | |} | ||
+ | |||
* Remove suitcase | * Remove suitcase | ||
* EES-IC Disconnects 5a - 8a, Tues-Fri | * EES-IC Disconnects 5a - 8a, Tues-Fri |
Revision as of 14:02, 28 September 2020
Week 1 (Sep 21 - Sep 27)
- Updated schedule media:200914_AIPINJ_Weeks_Sep_18_update.docx
- High voltage test slides media:200902_HV_Plans.pptx
- Gun and Wien tasks Media:High Voltage Work Gun2 & Wien filters.xlsx
Week 2 (Sep 28 - Oct 4)
- Fri 9/25 - Mon 9/28
- CIS Gun Jobs
- Wien electrode testing – 9am!!!
- Gun HVPS lockout - DONE
- Gun HV cable disconnect – DONE
- Remove PIG – Coordinate w/ Neil for convenient time
- Shukui - Laser outrigger table as-founds, remove components
- Scott - Remove yellow box
- Scott - Disconnect Decarad
- Monday 9/28 Tasks (updated 0915 9/28)
- Power down Wein system (Scott/Joe)
- Power down and remove DecaRad system (Scott)
- Return gun valve config to "normal" (Marcy)
- Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
- PSS Kickers and associated chassis removal (SSG)
- Laser table disassembly (Shukui/Scott)
- Tuesday 9/29 Tasks (updated 1230 9/28)
- Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
- Disconnect aperture and cup signal cables (Pete) 5a
- Disconnect rad probes (Melvin) 8a
- Tunnel magnet disconnects (Diggs, Delk) 10a
- Tue 9/29 – Fri 10/1 (updated 0915 9/28)
- Tunnel Work
Time | Mon 9/28 | Tue 9/29 | Wed 9/30 | Thu 10/1 | F 10/2 |
---|---|---|---|---|---|
4a - 8a | I&C; 5a: Francis: BPMs, Cups, Apertures | I&C; 430a: Greenfield + Gonzales: vacuum labelling | I&C | I&C | |
8a - 10a | CIS + SSG | RadCon: rad probes | RF: Prebuncher | ||
10a - 12p | CIS + SSG | DC Power | |||
12p - 2p | CIS + SSG | DC Power | DC Power | DC Power | |
2p - 4p | CIS + SSG | DC Power | 3p: Moser: Safety Warden checks | ||
4p - ?? |
- Remove suitcase
- EES-IC Disconnects 5a - 8a, Tues-Fri
- RadCon probe disconnects, 8a - 10a, Tues
- DC Power magnet disconnects, 10a - 4p Tues, 10a-noon Wed+Thur
- Prebuncher disconnects, 8a - 10a, Wed
Week 3 (Oct 5 - Oct 11)
- Vacuum disconnects
Week 4 (Oct 12 - Oct 18)
Week 5 (Oct 19 - Oct 25)
- Injector is now in restricted access all the time
- LOTO and system disconnects
Week X
- Vacuum jobs Options for gun through y-chamber