Difference between revisions of "CIS Phase 1 work plans"
Jump to navigation
Jump to search
Line 24: | Line 24: | ||
* Laser table disassembly (Shukui/Scott) | * Laser table disassembly (Shukui/Scott) | ||
− | ; Tuesday 9/29 Tasks (updated | + | ; Tuesday 9/29 Tasks (updated 0815 9/29) |
− | * Disconnect BPMs 2I01->0I02A (Pete) beginning 5a | + | * (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a |
− | * Disconnect aperture and cup signal cables (Pete) 5a | + | * (Done) Disconnect aperture and cup signal cables (Pete) 5a |
* Disconnect rad probes (Melvin) 8a | * Disconnect rad probes (Melvin) 8a | ||
* Tunnel magnet disconnects (Diggs, Delk) 10a | * Tunnel magnet disconnects (Diggs, Delk) 10a | ||
* Removal of old chopper amps from rack (Farrish) | * Removal of old chopper amps from rack (Farrish) | ||
+ | * Harp upgrade to PC104 (Dela Cruz) | ||
* | * | ||
Revision as of 07:17, 29 September 2020
Week 1 (Sep 21 - Sep 27)
- Updated schedule media:200914_AIPINJ_Weeks_Sep_18_update.docx
- High voltage test slides media:200902_HV_Plans.pptx
- Gun and Wien tasks Media:High Voltage Work Gun2 & Wien filters.xlsx
Week 2 (Sep 28 - Oct 4)
- Fri 9/25 - Mon 9/28
- CIS Gun Jobs
- Wien electrode testing – 9am!!!
- Gun HVPS lockout - DONE
- Gun HV cable disconnect – DONE
- Remove PIG – Coordinate w/ Neil for convenient time
- Shukui - Laser outrigger table as-founds, remove components
- Scott - Remove yellow box
- Scott - Disconnect Decarad
- Monday 9/28 Tasks (updated 0915 9/28)
- Power down Wein system (Scott/Joe)
- Power down and remove DecaRad system (Scott)
- Return gun valve config to "normal" (Marcy)
- Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
- PSS Kickers and associated chassis removal (SSG)
- Laser table disassembly (Shukui/Scott)
- Tuesday 9/29 Tasks (updated 0815 9/29)
- (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
- (Done) Disconnect aperture and cup signal cables (Pete) 5a
- Disconnect rad probes (Melvin) 8a
- Tunnel magnet disconnects (Diggs, Delk) 10a
- Removal of old chopper amps from rack (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- Tue 9/29 – Fri 10/1 (updated 0915 9/28)
- Tunnel Work
Time | Mon 9/28 | Tue 9/29 | Wed 9/30 | Thu 10/1 | F 10/2 |
---|---|---|---|---|---|
4a - 8a | I&C; 5a: Francis: BPMs, Cups, Apertures | I&C; 430a: Greenfield + Gonzales: vacuum labelling | I&C | I&C | |
8a - 10a | CIS + SSG | RadCon: rad probes | RF: Prebuncher | ||
10a - 12p | CIS + SSG | DC Power | |||
12p - 2p | CIS + SSG | DC Power | DC Power | DC Power | |
2p - 4p | CIS + SSG | DC Power | 3p: Moser: Safety Warden checks | ||
4p - ?? |
- Remove suitcase
- EES-IC Disconnects 5a - 8a, Tues-Fri
- RadCon probe disconnects, 8a - 10a, Tues
- DC Power magnet disconnects, 10a - 4p Tues, 10a-noon Wed+Thur
- Prebuncher disconnects, 8a - 10a, Wed
Week 3 (Oct 5 - Oct 11)
- Vacuum disconnects
Week 4 (Oct 12 - Oct 18)
Week 5 (Oct 19 - Oct 25)
- Injector is now in restricted access all the time
- LOTO and system disconnects
Week X
- Vacuum jobs Options for gun through y-chamber