Line 34: | Line 34: | ||
* Document existing Wein cabling and power off PS (Scott) | * Document existing Wein cabling and power off PS (Scott) | ||
+ | ; Wednesday 9/30 Tasks (updated 1000 9/29) | ||
+ | * RF Prebuncher disconnects (Farrish) 6a | ||
+ | * Vacuum Component Labeling (Greenfield, Gonzales) 430a | ||
+ | * Magnet disconnects (Diggs, Delk) 12p | ||
+ | * | ||
− | ; Tue 9/29 – Fri 10/1 (updated | + | ; Thursday 10/1 Tasks (updated 1000 9/29) |
+ | * Picoammeter Removal, InjSB (Francis) 5a | ||
+ | * Disconnecting water and air lines from apertures and cups (Adderley) 8a | ||
+ | * | ||
+ | |||
+ | ; Tue 9/29 – Fri 10/1 (updated 1000 9/29) | ||
; <u>'''Tunnel Work'''</u> | ; <u>'''Tunnel Work'''</u> | ||
Line 42: | Line 52: | ||
! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2 | ! Time !! Mon 9/28 !! Tue 9/29 !! Wed 9/30 !! Thu 10/1 !! F 10/2 | ||
|- | |- | ||
− | | 4a - 8a || || I&C; 5a: Francis: BPMs, Cups, Apertures || I&C; 430a: Greenfield + Gonzales: vacuum labelling || I&C || I&C | + | | 4a - 8a || || I&C; 5a: Francis: BPMs, Cups, Apertures || I&C; 430a: Greenfield + Gonzales: vacuum labelling; RF: Prebuncher || I&C || I&C |
|- | |- | ||
− | | 8a - 10a || CIS + SSG || RadCon: rad probes || | + | | 8a - 10a || CIS + SSG || RadCon: rad probes || || CIS; Adderley: Aperture+Cups Air/Water || |
|- | |- | ||
| 10a - 12p || CIS + SSG || DC Power || || || | | 10a - 12p || CIS + SSG || DC Power || || || | ||
Line 55: | Line 65: | ||
|} | |} | ||
− | * Remove suitcase | + | ; <u>'''Other Work Occurring When Convenient'''</u> |
− | * | + | * Remove suitcase (CIS) |
− | + | * ODH Head Replacement (SSG) | |
− | + | * PSS Kicker Magnet removal (SSG) | |
− | * | ||
=== Week 3 (Oct 5 - Oct 11) === | === Week 3 (Oct 5 - Oct 11) === |
Revision as of 08:49, 29 September 2020
Week 1 (Sep 21 - Sep 27)
- Updated schedule media:200914_AIPINJ_Weeks_Sep_18_update.docx
- High voltage test slides media:200902_HV_Plans.pptx
- Gun and Wien tasks Media:High Voltage Work Gun2 & Wien filters.xlsx
Week 2 (Sep 28 - Oct 4)
- Fri 9/25 - Mon 9/28
- CIS Gun Jobs
- Wien electrode testing – 9am!!!
- Gun HVPS lockout - DONE
- Gun HV cable disconnect – DONE
- Remove PIG – Coordinate w/ Neil for convenient time
- Shukui - Laser outrigger table as-founds, remove components
- Scott - Remove yellow box
- Scott - Disconnect Decarad
- Monday 9/28 Tasks (updated 0915 9/28)
- Power down Wein system (Scott/Joe)
- Power down and remove DecaRad system (Scott)
- Return gun valve config to "normal" (Marcy)
- Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
- PSS Kickers and associated chassis removal (SSG)
- Laser table disassembly (Shukui/Scott)
- Tuesday 9/29 Tasks (updated 0930 9/29)
- (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
- (Done) Disconnect aperture and cup signal cables (Pete) 5a
- Disconnect rad probes (Melvin) 8a
- Tunnel magnet disconnects (Diggs, Delk) 10a
- (Done) Removal of old chopper amps from rack (Farrish)
- Harp upgrade to PC104 (Dela Cruz)
- ODH Head Replacements (SSG)
- Document existing Wein cabling and power off PS (Scott)
- Wednesday 9/30 Tasks (updated 1000 9/29)
- RF Prebuncher disconnects (Farrish) 6a
- Vacuum Component Labeling (Greenfield, Gonzales) 430a
- Magnet disconnects (Diggs, Delk) 12p
- Thursday 10/1 Tasks (updated 1000 9/29)
- Picoammeter Removal, InjSB (Francis) 5a
- Disconnecting water and air lines from apertures and cups (Adderley) 8a
- Tue 9/29 – Fri 10/1 (updated 1000 9/29)
- Tunnel Work
Time | Mon 9/28 | Tue 9/29 | Wed 9/30 | Thu 10/1 | F 10/2 |
---|---|---|---|---|---|
4a - 8a | I&C; 5a: Francis: BPMs, Cups, Apertures | I&C; 430a: Greenfield + Gonzales: vacuum labelling; RF: Prebuncher | I&C | I&C | |
8a - 10a | CIS + SSG | RadCon: rad probes | CIS; Adderley: Aperture+Cups Air/Water | ||
10a - 12p | CIS + SSG | DC Power | |||
12p - 2p | CIS + SSG | DC Power | DC Power | DC Power | |
2p - 4p | CIS + SSG | DC Power | 3p: Moser: Safety Warden checks | ||
4p - ?? |
- Other Work Occurring When Convenient
- Remove suitcase (CIS)
- ODH Head Replacement (SSG)
- PSS Kicker Magnet removal (SSG)
Week 3 (Oct 5 - Oct 11)
- Vacuum disconnects
Week 4 (Oct 12 - Oct 18)
Week 5 (Oct 19 - Oct 25)
- Injector is now in restricted access all the time
- LOTO and system disconnects
Week X
- Vacuum jobs Options for gun through y-chamber