Difference between revisions of "CIS Phase 1 work plans"

From Ciswikidb
Jump to navigation Jump to search
Line 199: Line 199:
 
=== Week 5 (Oct 19 - Oct 23) ===
 
=== Week 5 (Oct 19 - Oct 23) ===
 
* Fire pipe demolition? (Facilities Contractor)
 
* Fire pipe demolition? (Facilities Contractor)
* Wein upgrade (Carlos)
+
* Wien upgrade (Carlos)
 
* New Y-Chamber assembly
 
* New Y-Chamber assembly
  

Revision as of 16:10, 15 October 2020

Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups

Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects

Fri 9/25 - Mon 9/28
  • CIS Gun Jobs
Wien electrode testing – 9am!!!
Gun HVPS lockout - DONE
Gun HV cable disconnect – DONE
Remove PIG – Coordinate w/ Neil for convenient time
Shukui - Laser outrigger table as-founds, remove components
Scott - Remove yellow box
Scott - Disconnect Decarad
Monday 9/28 Tasks (updated 0915 9/28)
  • Power down Wein system (Scott/Joe)
  • Power down and remove DecaRad system (Scott)
  • Return gun valve config to "normal" (Marcy)
  • Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
  • PSS Kickers and associated chassis removal (SSG)
  • Laser table disassembly (Shukui/Scott)
Tuesday 9/29 Tasks (updated 0930 9/29)
  • (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
  • (Done) Disconnect aperture and cup signal cables (Pete) 5a
  • Disconnect rad probes (Melvin) 8a
  • Tunnel magnet disconnects (Diggs, Delk) 10a
  • (Done) Removal of old chopper amps from rack (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • ODH Head Replacements (SSG)
  • Document existing Wein cabling and power off PS (Scott)
Wednesday 9/30 Tasks (updated 0900 9/30)
  • RF Prebuncher disconnects (Farrish) 6a
  • Vacuum Component Labeling (Greenfield, Gonzales) 430a
  • Magnet disconnects -- wire wrap-ups, junction box investigation (Coleman, Diggs, Delk) 10a
  • Tiny magnet removals (Scott, Grames) 9a
  • PSS Kicker Magnet removal (SSG) 9a
  • Sample hold cables install, InjSB (Francis)
  • Remaining PSS Interface chassis removal (SSG)
  • Harp upgrade to PC104 (Dela Cruz)
  • Moser transfers CCOC phone @1430, to reach moving forward x5089
Thursday 10/1 Tasks (updated 0830 10/1)
  • Picoammeter Removal, InjSB (Francis) 5a
  • Sample hold cables install, IN02B24 (Francis)
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
  • Disconnecting water and air lines from apertures and cups (Adderley) 8a
  • Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a
Friday 10/2 Tasks (updated 0900 10/2)
  • Viewer disconnects (Norris) 6a
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • PSS Kicker Cables tie-up (SSG)
  • Survey and Alignment control measure around gun (S&A)
  • Load suitcase with "bad" pucks (CIS)
  • Pump-down vacuum in front of tee for next week (CIS)
Tue 9/29 – Fri 10/1 Table

Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network

Monday Oct 5
  • vacuum tests, disconnects, and pre-removal blank offs (CIS)
  • QCM->downstream Survey and Alignment
  • S&H cable work for iocinse4, InjSB (Francis)
Tuesday Oct 6
  • Survey and Alignment finishing up around 0L04 (S&A)
  • U-tube operations at 0L03 (Cryo)
  • S&H cable work for iocinse4, InjSB (Francis)
  • Stage/prepare for craning our girders (Mech Install)
  • Chopper SSA upgrade -- LCW line install, InjSB (Mech Install / RF)
Wednesday Oct 7
  • S&H cable work for iocinse4, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Wein PS Work, InjSB (Windham)
  • VIP UHV PS Work, InjSB (Windham)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
Thursday Oct 8
  • BPM work, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
Wednesday Oct 7 and Thursday Oct 8 -- Mechanical Install
  • Remove to test lab --
    • Laser outrigger table
    • 1st Wein girder and pedestals
    • 2nd Wein girder, apertures, and pedestals
    • Photocathode puck suitcase on cart
  • Remove to Brett Lewis grey oil tank
  • Penetration stone drops

Current list of Injector penetrations to be dropped: 57, 86, 108, possibly this one

Penetration drop distance e3854100:

  • 34ft from floor of InjSB to floor of Inj tunnel
  • 25ft from floor of InjSB to elevated Inj tunnel cable tray
Friday Oct 9
  • BPM Work, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
  • Penetration stone drop -- 57, 86, 108, Tunnel (Mech Install)
    • Penetration above laser hut already opened

Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild

  • Laser/Y-Chamber viewer for Y-chamber girder (Marcy)
  • Fiducializing Y-chamber girder (S&A)
  • Laser window under vacuum evaluations (Phil/Shukui/Caryn)
  • Documenting early InjSB racks (Scott)
  • Cable pulls through penetrations (EES)
  • Fire pipe demolition? (Facilities Contractor)
  • Wein upgrade (Carlos) --
    • Finish new Wien electrodes drawing and sign-offs
    • Vacuum chambers to machine shop for mods
    • Begin creating new screens
  • Injector Tunnel Photos from W 10/14


Monday Oct 12

Tunnel --

  • Hooking up VIPs to new 18V PS for load testing (Marcy/Scott)
  • Cable pulls through penetrations (EES)

InjSB --

  • BPM Cable Pulls through Penetration 86 (Francis)
  • Chopper SSA upgrade (Farrish)
  • Harp to PC104 upgrade (Dela Cruz)
  • Early rack documentation and space optimization (Scott)
  • PSS Upgrade work (IN02BNI, B29, B30) (SSG)


Tuesday Oct 13

Tunnel --

  • Cable pulls through penetrations (EES)
  • Resistor box evaluation (Coleman)

InjSB --

  • BPM Work, IN02B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)


Wednesday Oct 14

Tunnel --

  • Cable pulls through penetrations (EES)
  • Safety warden walk-through (Moser)

InjSB --

  • BPM Work, IN02B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • Determining rack location for Wien magnet PSs, IN02-middle (Coleman, Grames, Moser)
  • Safety warden walk-through (Moser)
  • Conduit in penetration 135 (Electricians)


Thursday Oct 15

Tunnel --

  • S&A Level surveys

InjSB --

  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)


Friday Oct 16

Tunnel --

  • Cable pulls through penetrations (EES)
  • Mott cable removals (Scott/Riad, EES)

InjSB --

  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
  • IN02B26 Power Lock-Out, ~915a (DC Power)

Week 5 (Oct 19 - Oct 23)

  • Fire pipe demolition? (Facilities Contractor)
  • Wien upgrade (Carlos)
  • New Y-Chamber assembly
Standing Injector Service Building Work
  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)


Monday Oct 19

Tunnel --

  • Cryo u-tube pulls for 0L0{2,3,4}
Tuesday Oct 20

Tunnel --

  • S&A Verify line with new control

Penetration Work

InjSB Penetrations that are open (click for pictures): above laser hut, 58, 86, 108, 135

  • 34ft from floor of InjSB to floor of Inj tunnel
  • 25ft from floor of InjSB to elevated Inj tunnel cable tray

Penetration Cable Pulls/Removals --

  • Tony pulling new Wien HV cables
  • Norris (possibly) removing old Cat5 cable
  • Norris pulling new viewer cables
  • Riad/Scott removing old Mott HV cables
  • Coleman pulling new Wien magnet cables
  • Cole pulling new neutron detector cables (above 0L03)
  • Scott pulling motor control cables for A1++


InjSB Racks.png