=== Week 6 (Oct 26 - Oct 30)  Remove old Y+NEG & Move GUn2 new location ===
+
=== Week 6 (Oct 26 - Oct 30)  Remove old Y+NEG & Move Gun2 new location ===
 
<div class="mw-collapsible">
 
<div class="mw-collapsible">
 
;Tunnel work
 
;Tunnel work
Line 372: Line 372:
 
| '''InjSB'''<br>5a - 9a || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis
 
| '''InjSB'''<br>5a - 9a || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis || Norris, Dela Cruz, Francis
 
|-
 
|-
| '''Tunnel'''<br>5a - 9a ||  || ''Gun Vacuum Work'' ||  || Gun2 Table Move <br> Y-Chamber+Gun3 Removal || ''open -- cable pulls?''
+
| '''Tunnel'''<br>5a - 9a ||  || ''Gun Vacuum Work'' ||  || Gun2 Table Move <br> Y-Chamber+Gun3 Removal ||  
 
|- style="background-color:#F0F8FF"
 
|- style="background-color:#F0F8FF"
 
| '''InjSB'''<br>9a - 12p || Francis, SSG || Francis, Windham, SSG || Francis, Windham, SSG || Dela Cruz, Norris, Francis, SSG || Francis, SSG
 
| '''InjSB'''<br>9a - 12p || Francis, SSG || Francis, Windham, SSG || Francis, Windham, SSG || Dela Cruz, Norris, Francis, SSG || Francis, SSG
Line 380: Line 380:
 
| '''InjSB'''<br>12p - 4p || SSG || Windham, SSG  || Windham, SSG || SSG ||  SSG
 
| '''InjSB'''<br>12p - 4p || SSG || Windham, SSG  || Windham, SSG || SSG ||  SSG
 
|-
 
|-
| '''Tunnel'''<br>12p - 4p || ''Gun Vacuum Work'' || ''Gun Vacuum Work'' <br> 3p:Videographer Tour || ''open'' || || S&A Point Layouts
+
| '''Tunnel'''<br>12p - 4p || ''Gun Vacuum Work'' || ''Gun Vacuum Work'' <br> 3p:Videographer Tour || || || S&A Point Layouts
 
|}
 
|}
  

Revision as of 08:42, 29 October 2020

Week 1 (Sep 21 - Sep 27) High Voltage Testing w/ PSS lock-ups

Week 2 (Sep 28 - Oct 4) - Instrument, Magnet, LCW, Air, Laser disconnects

Fri 9/25 - Mon 9/28
  • CIS Gun Jobs
Wien electrode testing – 9am!!!
Gun HVPS lockout - DONE
Gun HV cable disconnect – DONE
Remove PIG – Coordinate w/ Neil for convenient time
Shukui - Laser outrigger table as-founds, remove components
Scott - Remove yellow box
Scott - Disconnect Decarad
Monday 9/28 Tasks (updated 0915 9/28)
  • Power down Wein system (Scott/Joe)
  • Power down and remove DecaRad system (Scott)
  • Return gun valve config to "normal" (Marcy)
  • Dispose of grey mineral oil tank in coordination w/ESH&Q (Carlos/Bubba)
  • PSS Kickers and associated chassis removal (SSG)
  • Laser table disassembly (Shukui/Scott)
Tuesday 9/29 Tasks (updated 0930 9/29)
  • (Done) Disconnect BPMs 2I01->0I02A (Pete) beginning 5a
  • (Done) Disconnect aperture and cup signal cables (Pete) 5a
  • Disconnect rad probes (Melvin) 8a
  • Tunnel magnet disconnects (Diggs, Delk) 10a
  • (Done) Removal of old chopper amps from rack (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • ODH Head Replacements (SSG)
  • Document existing Wein cabling and power off PS (Scott)
Wednesday 9/30 Tasks (updated 0900 9/30)
  • RF Prebuncher disconnects (Farrish) 6a
  • Vacuum Component Labeling (Greenfield, Gonzales) 430a
  • Magnet disconnects -- wire wrap-ups, junction box investigation (Coleman, Diggs, Delk) 10a
  • Tiny magnet removals (Scott, Grames) 9a
  • PSS Kicker Magnet removal (SSG) 9a
  • Sample hold cables install, InjSB (Francis)
  • Remaining PSS Interface chassis removal (SSG)
  • Harp upgrade to PC104 (Dela Cruz)
  • Moser transfers CCOC phone @1430, to reach moving forward x5089
Thursday 10/1 Tasks (updated 0830 10/1)
  • Picoammeter Removal, InjSB (Francis) 5a
  • Sample hold cables install, IN02B24 (Francis)
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • Viewer+harp hardware disconnects (Norris, Dela Cruz) 6a
  • Disconnecting water and air lines from apertures and cups (Adderley) 8a
  • Mech Install Pre-Job Walk-Thru (Grames, Wilson) 9a
Friday 10/2 Tasks (updated 0900 10/2)
  • Viewer disconnects (Norris) 6a
  • BPM Work in IN02B2* (Francis)
  • Chopper amplifier upgrade (Farrish)
  • Harp upgrade to PC104 (Dela Cruz)
  • PSS Kicker Cables tie-up (SSG)
  • Survey and Alignment control measure around gun (S&A)
  • Load suitcase with "bad" pucks (CIS)
  • Pump-down vacuum in front of tee for next week (CIS)
Tunnel Work
Time Mon 9/28 Tue 9/29 Wed 9/30 Thu 10/1 F 10/2
4a - 8a I&C; 5a: Francis: BPMs, Cups, Apertures I&C; 430a: Greenfield + Gonzales: vacuum labelling; 6a: Farrish: Prebuncher I&C; 6a: Norris: Viewer; 6a: Dela Cruz, Harps I&C: Norris: Viewer disconnects
8a - 10a CIS + SSG RadCon: rad probes SSG: Kicker magnet removal; CIS: Tiny magnet removals CIS; Adderley: Aperture+Cups Air/Water; Grames: Mech Install Walk-Thru S&A: Gun
10a - 12p CIS + SSG DC Power DC Power: Wire wrap-ups, junction box investigation S&A: Gun; SSG: Kicker cable tie-up
12p - 2p CIS + SSG DC Power DC Power: Wire wrap-ups, junction box investigation DC Power S&A: Gun
2p - 4p CIS + SSG DC Power 3p: Moser: Safety Warden checks S&A: Gun
4p - ??
Other Work Occurring When Convenient
  • Remove suitcase, Tunnel (CIS)
  • Harp upgrade, InjSB (I&C)
  • ODH Head Replacement, InjSB and Tunnel (SSG)
  • PSS Chassis Removals, InjSB (SSG)

Week 3 (Oct 5 - Oct 11) - Vacuum disconnects, girder/pedestal removal, injector survey network

Monday Oct 5
  • vacuum tests, disconnects, and pre-removal blank offs (CIS)
  • QCM->downstream Survey and Alignment
  • S&H cable work for iocinse4, InjSB (Francis)
Tuesday Oct 6
  • Survey and Alignment finishing up around 0L04 (S&A)
  • U-tube operations at 0L03 (Cryo)
  • S&H cable work for iocinse4, InjSB (Francis)
  • Stage/prepare for craning our girders (Mech Install)
  • Chopper SSA upgrade -- LCW line install, InjSB (Mech Install / RF)
Wednesday Oct 7
  • S&H cable work for iocinse4, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Wein PS Work, InjSB (Windham)
  • VIP UHV PS Work, InjSB (Windham)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
Thursday Oct 8
  • BPM work, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
Wednesday Oct 7 and Thursday Oct 8 -- Mechanical Install
  • Remove to test lab --
    • Laser outrigger table
    • 1st Wein girder and pedestals
    • 2nd Wein girder, apertures, and pedestals
    • Photocathode puck suitcase on cart
  • Remove to Brett Lewis grey oil tank
  • Penetration stone drops

Current list of Injector penetrations to be dropped: 57, 86, 108, possibly this one

Penetration drop distance e3854100:

  • 34ft from floor of InjSB to floor of Inj tunnel
  • 25ft from floor of InjSB to elevated Inj tunnel cable tray
Friday Oct 9
  • BPM Work, InjSB (Francis)
  • Chopper SSA upgrade, InjSB (Farrish)
  • Harp PC104 upgrade, InjSB (Dela Cruz)
  • Penetration stone drop -- 57, 86, 108, Tunnel (Mech Install)
    • Penetration above laser hut already opened

Week 4 (Oct 12 - Oct 18) Cable Pulls and Y-Chamber Girder Rebuild

  • Laser/Y-Chamber viewer for Y-chamber girder (Marcy)
  • Fiducializing Y-chamber girder (S&A)
  • Laser window under vacuum evaluations (Phil/Shukui/Caryn)
  • Documenting early InjSB racks (Scott)
  • Cable pulls through penetrations (EES)
  • Fire pipe demolition? (Facilities Contractor)
  • Wein upgrade (Carlos) --
    • Finish new Wien electrodes drawing and sign-offs
    • Vacuum chambers to machine shop for mods
    • Begin creating new screens
  • Injector Tunnel Photos from W 10/14


Monday Oct 12

Tunnel --

  • Hooking up VIPs to new 18V PS for load testing (Marcy/Scott)
  • Cable pulls through penetrations (EES)

InjSB --

  • BPM Cable Pulls through Penetration 86 (Francis)
  • Chopper SSA upgrade (Farrish)
  • Harp to PC104 upgrade (Dela Cruz)
  • Early rack documentation and space optimization (Scott)
  • PSS Upgrade work (IN02BNI, B29, B30) (SSG)


Tuesday Oct 13

Tunnel --

  • Cable pulls through penetrations (EES)
  • Resistor box evaluation (Coleman)

InjSB --

  • BPM Work, IN02B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)


Wednesday Oct 14

Tunnel --

  • Cable pulls through penetrations (EES)
  • Safety warden walk-through (Moser)

InjSB --

  • BPM Work, IN02B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • Determining rack location for Wien magnet PSs, IN02-middle (Coleman, Grames, Moser)
  • Safety warden walk-through (Moser)
  • Conduit in penetration 135 (Electricians)


Thursday Oct 15

Tunnel --

  • S&A Level surveys

InjSB --

  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
Friday Oct 16

Tunnel --

  • Cable pulls through penetrations (EES)
  • Mott cable removals (Scott/Riad, EES)

InjSB --

  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
  • IN02B26 Power Lock-Out, ~915a (DC Power)

Week 5 (Oct 19 - Oct 23) Prep for Gun to Y Vacuum Installation

Non-Tunnel Work
  • Build new Y-chamber viewer => Y-built w/test screen, Laser being built.
  • Use test screen + laser + S&A to verify position of first viewer => This week
  • Install + align + vacuum seal (2) viewers => target this week
  • Caryn will confirm but identified best ‘mushroom’ window, attach => done
  • ME provide ALL points to S&A for installation (gun table, 2I stand, Y-chamber, 2 peds for Wien, 2 peds A1/A2) => ???
  • Carlos' Wien-mania!
Tunnel Work
  • Complete remove old keV Mott cables => done
  • Complete remove old gun HV cables => done
  • Jim pulls Wien PS cables? => done
  • Does Wien HV cable pull start? => starting this week
  • Scott will finish tie back of cables on tunnel floor to cable tray => done
  • Refill 86? => no, not yet
Standing Injector Service Building Work
  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, Rack re-org, IN02B22 (DC Power)
Monday Oct 19

Tunnel --

  • Cryo u-tube pulls for 0L0{2,3,4}
Tuesday Oct 20

Tunnel --

  • Cable pulls and removals

InjSB --

  • BPM Work, IN0{2,3}B{*} (Francis)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • Harp to PC104 upgrade, IN03B07 (Dela Cruz)
  • Early rack documentation and space optimization, IN01B{02-05} (Scott)
  • PSS Upgrade, IN02{BNI, B29, B30} (SSG)
  • 20A PS Install, IN02B22, 2p - 4p (DC Power)
Wednesday Oct 21

Tunnel --

  • S&A Verify line with new control

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • M56 Hardware Removal from IN02B22, (I&C)


Thursday Oct 22

InjSB --

  • Wien Magnet PS Install, IN02B22, afternoon (DC Power)
  • Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (SSG - single person)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)


Friday Oct 23

Tunnel --

  • Vacuum work clean room craned in 6a - 8a (Mech Install)
  • Clean room setup and prepping (Marcy)
  • Gun interlock checks in preparation of removal of old HV Interlock Chassis in IN01B02 (Windham, Grames)
  • Laser room work (Shukui)

InjSB --

  • Early rack documentation and space optimization, IN01B{00-05}, 9a - 4p (Windham)
  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • 20A PS Install, IN02B22 (DC Power)


Inj Service Building Work

InjSB Racks.png

Time Wed 10/21 Thu 10/22 Fri 10/23
5a - 9a Dela Cruz, Norris, Francis Dela Cruz, Norris, Francis Dela Cruz, Norris, Francis
9a - 12p Francis, SSG, Windham Francis, SSG Francis, SSG, Windham
12p - 4p DC Power, SSG, Windham, Francis DC Power, SSG, Windham, Francis DC Power, SSG, Windham, Francis


Week 6 (Oct 26 - Oct 30) Remove old Y+NEG & Move Gun2 new location

Tunnel work
  • Remove NEG filter from HV chamber done
  • Setup mobile cleanroom over HV chamber done
  • Vent Gun3 chamber to test Gun3 valve done
  • Vent Gun2 chamber to test Gun2 valve done
  • Remove 2I NEG beam line, remove NEG pedestal (temporarily) Wed / Thur
  • Replace 10” flange + SHV connector + blank off + pump down done
  • Prep Gun3 & Y-chamber for Install to remove done
  • Wrap up UHV ion pump power supply power tests done
  • INSTALL lift and move gun table off feet, & move Gun3 & Y-chamber back to TL-1137 Wed / Thur
  • S&A may start setting/checking points (gun feet, 2I ped, Y ped, Wien ped, A1/A2 ped) Fri
Non-Tunnel Work
  • Finish Y-chamber : add viewers, add laser vacuum window, add NEG towers, add gun valve
  • Wien-mania! (high level schedule)
-Wien magnetic field mapping next couple weeks
-Bubba assembles the fixtures done


Thur Oct 29

Tunnel --

  • Gun2 move, 5a - 8a (Mech Install)
  • Removal of Gun3 and Y-chamber to Test Lab, 5a - 8a (Mech Install)
  • Wien HV and control cable pulls, 9a - 1p (Dela Cruz)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 1p (Dela Cruz)
  • Viewer work, IN03B07, 6a - 1p (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)

Other possible work....

  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
  • LLRF air temperature control system removal from IN01B13? (Plawski?)
  • Trim Card Checks, IN02B{10+11+26} + IN04B10, (Diggs, Richardson)


TOMORROW, Friday, All Hallows' Eve Eve Mask -- join the fun by wearing masks to the 0830 toolbox meeting.


Injector Tunnel and Service Building Work

Location
Time
Mon 10/26 Tue 10/27 Wed 10/28 Thu 10/29 Fri 10/30
InjSB
5a - 9a
Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis Norris, Dela Cruz, Francis
Tunnel
5a - 9a
Gun Vacuum Work Gun2 Table Move
Y-Chamber+Gun3 Removal
InjSB
9a - 12p
Francis, SSG Francis, Windham, SSG Francis, Windham, SSG Dela Cruz, Norris, Francis, SSG Francis, SSG
Tunnel
9a - 12p
Gun Vacuum Work Gun Vacuum Work 9a CIS+MechInstall Walk-Thru
open
Wien Cable Pulls Cryo 0L02 L-tube pull
S&A Point Layouts
InjSB
12p - 4p
SSG Windham, SSG Windham, SSG SSG SSG
Tunnel
12p - 4p
Gun Vacuum Work Gun Vacuum Work
3p:Videographer Tour
S&A Point Layouts

InjSB Week6.png


Mon Oct 26

Tunnel --

  • Gun vacuum work, 9a - 4p (CIS)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • LLRF air temperature control system removal from IN01B13? (Plawski?)
Tues Oct 27

Tunnel --

  • Gun vacuum work, 9a - 3p (CIS)
  • Videographer Tour, 3p+ (K. Carter + two videographers)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
  • CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • LLRF air temperature control system removal from IN01B13? (Plawski?)
Wed Oct 28

Tunnel --

  • Opportunity for cable pulls --
    • Wien HV and control cables
    • Removal of old Cat5 viewer cables
    • New viewer cables
    • Neutron detector cablesNorris (possibly) removing old Cat5 cable
  • CIS + MechInstall Walk-Through of Gun Table Move, Removal of Gun3 stub and Y-chamber, 9a

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
  • CIS Rack Work, IN01B{00-05} 9a - 4p (Windham)
  • 20A Wien Magnet PS Install, IN02B22 (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11}, (Farrish)
  • LLRF air temperature control system removal from IN01B13? (Plawski?)
  • Trim Card Checks, IN02B{10+11+26} + IN04B10, (Diggs, Richardson)
Thur Oct 29

Tunnel --

  • Gun2 move, 5a - 8a (Mech Install)
  • Removal of Gun3 and Y-chamber to Test Lab, 5a - 8a (Mech Install)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23} 5a - 1p (Francis)
Fri Oct 30

Tunnel --

  • Laying out new pedestal points? (S&A)

InjSB --

  • PSS Upgrade, IN02B{NI, 29, 30} 9a - 4p (Beizer)
  • Wien controls work, IN01B03, 6a - 9a (Dela Cruz)
  • Viewer work, IN03B07, 6a - 9a (Norris)
  • BPM Work, IN03B{05-08, 23}, 5a - 1p (Francis)

Week 7 (Nov 2 - Nov 6) Point Layout and Anchor Installs

Tunnel work

  • INSTALL sets new foot pads, new anchor bolts if needed
  • INSTALL lift and move gun table to new foot pads
  • INSTALL move new y-chamber from TL-1137 to injector, and vice versa
  • S&A and CIS install and align Y-chamber + NEG tube + Gun table (CL cathode/anode)
  • Pump down and leak check
  • Check laser align/retro : back fill N2 + test retro from GaAs + test alignment to viewer
  • Iterate as needed
  • End week with laser + Y + Gun + NEG aligned (pre-bake)
  • Prep for new suitcase (i.e. prep work to safe photocathodes during eventual gun bake)

InjSB Work --

  • PSS Upgrade, IN02B{NI, 29, 30} (Beizer)
  • Wien controls work, IN01B03 (Dela Cruz)
  • Viewer work, IN03B07 (Norris)
  • BPM Work, IN03B{05-08, 23} (Francis)
  • CIS Rack Work, IN01B{00-05} (Windham)
  • 20A Wien Magnet PS Install (Coleman)
  • Chopper SSA upgrade, back of IN01B{03-11} (Farrish)
  • LLRF air temperature control system removal from IN01B13 (Plawski?)


Injector Tunnel and Service Building Work

Location
Time
Mon 11/2 Tue 11/3
Election Day 🇺🇸
Wed 11/4 Thu 11/5 Fri 11/6
InjSB
5a - 9a
BPM, Viewer, Wien Work BPM, Viewer, Wien Work BPM, Viewer, Wien Work BPM, Viewer, Wien Work BPM, Viewer, Wien Work
Tunnel
5a - 9a
M MechInstall? W R F
InjSB
9a - 12p
PSS Upgrade
BPM Work
PSS Upgrade
BPM Work
PSS Upgrade
BPM Work
PSS Upgrade
BPM Work
PSS Upgrade
BPM Work
Tunnel
9a - 12p
S&A Setting and Checking Points T W R F
InjSB
12p - 4p
PSS Upgrade
PSS Upgrade
PSS Upgrade
PSS Upgrade
PSS Upgrade
Tunnel
12p - 4p
S&A Setting and Checking Points T W R F

InjSB Week6.png


Penetration Work

InjSB Penetrations that are open (click for pictures): above laser hut, 58, 86, 108, 135

  • 34ft from floor of InjSB to floor of Inj tunnel
  • 25ft from floor of InjSB to elevated Inj tunnel cable tray


Penetration Cable Pulls/Removals --

  • Tony pulling new Wien E-field HV cables
  • Norris removing old Cat5 viewer cables
  • Norris pulling new viewer cables
  • Riad/Scott removing old Mott HV cables
  • Coleman pulling new Wien B-field magnet cables
  • Cole pulling new neutron detector cables (above 0L03)
  • Scott pulling motor control cables for A1++

InjSB Racks.png

Fire System Work

Description of Task: Replacement of tunnel sprinkler piping, fire alarm control panels in B85 & B98, replacement of detection devices.