==Jobs Leading to HCO & Commissioning == | ==Jobs Leading to HCO & Commissioning == | ||
− | + | ; 15 deg dipole (Scott) | |
− | ; 15 deg dipole ( | ||
* Install on beam line after bake out, then align, do we use shims? | * Install on beam line after bake out, then align, do we use shims? | ||
* Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test | * Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test | ||
Line 8: | Line 7: | ||
* Update drawings, document | * Update drawings, document | ||
− | ; Laser jobs | + | ; Laser jobs (Shukui/Scott) |
* Complete outrigger box, install, test with laser room shutter, update LSOP | * Complete outrigger box, install, test with laser room shutter, update LSOP | ||
* Flush chiller, decide on PM schedule, fill | * Flush chiller, decide on PM schedule, fill | ||
Line 15: | Line 14: | ||
* Update drawings, document | * Update drawings, document | ||
− | ; Gun HVPS jobs | + | ; Gun HVPS jobs (Carlos/Bubba/Scott) |
− | ; Wien HVPS | + | ; Wien HVPS (Carlos) |
* (done) Add placards to ISB racks | * (done) Add placards to ISB racks | ||
* Install HV Switcher chassis at ISB, complete cabling between rack components | * Install HV Switcher chassis at ISB, complete cabling between rack components | ||
Line 24: | Line 23: | ||
* Update drawings, document | * Update drawings, document | ||
− | ; Ion Pump Power Supplies | + | ; Ion Pump Power Supplies (Scott, Marcy) |
* (done) Finalize IP names for songsheet | * (done) Finalize IP names for songsheet | ||
* Complete mapping between all IP and power supplies (gun to choppers) | * Complete mapping between all IP and power supplies (gun to choppers) | ||
Line 32: | Line 31: | ||
* Update drawings, document | * Update drawings, document | ||
− | ; Valves | + | ; Vacuum (Marcy, Phil) |
+ | * Bake gun and beam line | ||
+ | * Activate NEG's | ||
+ | * Hi-pot any FE-er pumps | ||
+ | * Set voltage for all pumps | ||
+ | |||
+ | ; Valves (Scott) | ||
* Work with I&C and software, controls for (3) valves (note - confirm valve type different) | * Work with I&C and software, controls for (3) valves (note - confirm valve type different) | ||
* Build, install, test (3) shut-override boxes for valves | * Build, install, test (3) shut-override boxes for valves | ||
Line 39: | Line 44: | ||
* Update drawings, document | * Update drawings, document | ||
− | ; Air, GN2, LCW | + | ; Air, GN2, LCW (Phil, Bubba) |
* Move GN2 near gun lower, hook for air lines, caps for poly hose | * Move GN2 near gun lower, hook for air lines, caps for poly hose | ||
* Add 2nd GN2 near girder, hook for air lines, caps for poly hose | * Add 2nd GN2 near girder, hook for air lines, caps for poly hose | ||
Line 45: | Line 50: | ||
* (done) Re-install LCW manifold | * (done) Re-install LCW manifold | ||
− | ; Crash inhibit | + | ; Crash inhibit (Scott) |
* Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices) | * Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices) | ||
* Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on) | * Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on) | ||
− | ; Apertures & PCup | + | ; Apertures & PCup (Phil, Scott) |
* Scribe new aperture stops, bag, store in tunnel, throw away ALL old stops | * Scribe new aperture stops, bag, store in tunnel, throw away ALL old stops | ||
* Install shoulder bolt on A1, test | * Install shoulder bolt on A1, test | ||
Line 55: | Line 60: | ||
* Reconnect LCW, I&C check flow meters clear interlock | * Reconnect LCW, I&C check flow meters clear interlock | ||
− | ; Electrician jobs | + | ; Electrician jobs (Scott) |
* Relocate floor outlets | * Relocate floor outlets | ||
* Bond girders (Shaun has holes drilled on girders already for this) | * Bond girders (Shaun has holes drilled on girders already for this) | ||
* Install cable tray | * Install cable tray | ||
− | ; Decarad | + | ; Decarad (Carlos, Scott) |
+ | * Tally # of heads for gun (Carlos) and beam line (Alicia) | ||
+ | * |
Revision as of 09:44, 10 February 2021
Jobs Leading to HCO & Commissioning
- 15 deg dipole (Scott)
- Install on beam line after bake out, then align, do we use shims?
- Current sensor for HV interlock installed and tested, ready for DC power, to set limits, fault test
- Current sensor for FSD installed and tested, calibrated for FSD card, ready for DC power, to set limits, fault test
- Update drawings, document
- Laser jobs (Shukui/Scott)
- Complete outrigger box, install, test with laser room shutter, update LSOP
- Flush chiller, decide on PM schedule, fill
- Re-install Hall B amp in permanent location
- Complete macropulse chassis upgrade (replace 18 VDC + booster with 24 VDC, add protection diode to shutters), test all beam modes
- Update drawings, document
- Gun HVPS jobs (Carlos/Bubba/Scott)
- Wien HVPS (Carlos)
- (done) Add placards to ISB racks
- Install HV Switcher chassis at ISB, complete cabling between rack components
- Drop/pull HV cables from HV switcher outputs to Wiens
- Update drawings, document
- Ion Pump Power Supplies (Scott, Marcy)
- (done) Finalize IP names for songsheet
- Complete mapping between all IP and power supplies (gun to choppers)
- Complete UHV power supply upgrade, remove temp PS, spare PS on shelf (identify cabinet area for spares)
- Work with software to reprogram UHV PS EPICS names, can we have unique identifier from old names?
- Re-install (2) HV patch boxes, update box labels, pull HV drop cables to patch boxes, updated labels
- Update drawings, document
- Vacuum (Marcy, Phil)
- Bake gun and beam line
- Activate NEG's
- Hi-pot any FE-er pumps
- Set voltage for all pumps
- Valves (Scott)
- Work with I&C and software, controls for (3) valves (note - confirm valve type different)
- Build, install, test (3) shut-override boxes for valves
- UHV vacuum fault (series, yes?) shuts all three gate valves, test
- Gun2 valve open required for HV enable; method to jumper/bypass for HV conditioning (i.e. valve closed, but HV enable OK)
- Update drawings, document
- Air, GN2, LCW (Phil, Bubba)
- Move GN2 near gun lower, hook for air lines, caps for poly hose
- Add 2nd GN2 near girder, hook for air lines, caps for poly hose
- Fabricate, install air manifold w/ cutoff for (8) viewers, (2) valves, (2) spares
- (done) Re-install LCW manifold
- Crash inhibit (Scott)
- Install, test crash inhibit for pcup and viewer (note - fail safe test, i.e. do NOT hook up air to BOTH devices)
- Install, test crash inhibit for harp and viewer (note - does this exist, would speak to I&C early on)
- Apertures & PCup (Phil, Scott)
- Scribe new aperture stops, bag, store in tunnel, throw away ALL old stops
- Install shoulder bolt on A1, test
- Attach current monitoring w/ inline I&C protection boxes
- Reconnect LCW, I&C check flow meters clear interlock
- Electrician jobs (Scott)
- Relocate floor outlets
- Bond girders (Shaun has holes drilled on girders already for this)
- Install cable tray
- Decarad (Carlos, Scott)
- Tally # of heads for gun (Carlos) and beam line (Alicia)