Difference between revisions of "AIPINJ - Layouts"

From Ciswikidb
Jump to navigation Jump to search
Line 1: Line 1:
 
==Phase 1 - Songsheet ==
 
==Phase 1 - Songsheet ==
 
* Feb 18, 2021 - Preliminary songsheet update [[media:210218_ACC0002845-0001, INJECTOR, REV C.pdf]]
 
* Feb 18, 2021 - Preliminary songsheet update [[media:210218_ACC0002845-0001, INJECTOR, REV C.pdf]]
    Please add a date besides the word PRELIMINARY, a sort of version control until final
+
:VIP2I01A => VIP2I00A  
    Change “2I01” to “2I00” on the following
+
:VIP2I01B => VIP2I00B  
        VIP2I01A => VIP2I00A  
+
:VIP2I01C => VIP2I00C  
        VIP2I01B => VIP2I00B  
+
:VIP2I01 => VIP2I00  
        VIP2I01C => VIP2I00C  
+
:ILL2I01DCANO => ILL2I00DCANO  
        VIP2I01 => VIP2I00  
+
:VGP0I01 => VGP0I01A  
        ILL2I01DCANO => ILL2I00DCANO  
 
    Change VGP0I01 to VGP0I01A due to the cross it is on.
 
    Would be clearer if MBH2I01H and V are listed in column after MFX2I01
 
    MFA1D00 is unpowered and located between VBV1D00 and MAD1D00H.  Helpful to show (anywhere) and list as *MFA1D00* denoting unpowered
 
    VIP1D00 should be on its own line between ITV1D00 and IDL1D00
 
 
* Feb 1, 2021 - Preliminary songsheet release [[media:210201_PRELIMINARY_ACC0002845-0001, INJECTOR, REV C .pdf]]
 
* Feb 1, 2021 - Preliminary songsheet release [[media:210201_PRELIMINARY_ACC0002845-0001, INJECTOR, REV C .pdf]]
  

Revision as of 19:40, 18 February 2021

Phase 1 - Songsheet

VIP2I01A => VIP2I00A
VIP2I01B => VIP2I00B
VIP2I01C => VIP2I00C
VIP2I01 => VIP2I00
ILL2I01DCANO => ILL2I00DCANO
VGP0I01 => VGP0I01A

Phase 1 - CED Layout Info

Phase 1 - Gun to Chopper Layouts

-sequence just before the gun valve goes like this if possible: bellows + bpm/corr + valve.
-remove the pink rectangular placeholders for quadrupoles
-sequence after Vertical Wien: viewer/cross + bpm/corr + bellows, then pipe that solenoids are attached
-restore gap between the FG solenoids as exists in tunnel today
-sequence after Horizonal Wien: viewer/cross + prebuncher + bpm/corr, then bellows
-if moving valve/DP can upstream a little helps w/layout that's OK, keep subsequent solenoid located as shown

Phase 2 - Booster Layouts

Note: At the November 12, 2019 Modeling meeting [1], we decided to move the buncher to the midpoint position (between the centerline of the choppers and the centerline of the 2-cell in the booster). The buncher position in the July 2019 layout drawings is not the midpoint position; the buncher is shifted closer to the choppers in the July 2019 layout drawings.

-QCM was .32" further downstream. so all those interfaces moved.
-distance between chopper cavities was 59.32", so distance from center of choppers to downstream face of chopper #2 increased from 29.65" to 29.66".
-buncher, IFY0I06, MB00I06, A3, YAO cavity, A4 all moved slightly downstream.
-YAO cavity was .37" longer than the design drawing.

Overall Phase 1 & 2 AIPINJ Layouts

Note: At the November 12, 2019 Modeling meeting [2], we decided to move the buncher to the midpoint position (between the centerline of the choppers and the centerline of the 2-cell in the booster). The buncher position in the July 2019 layout drawings is not the midpoint position; the buncher is shifted closer to the choppers in the July 2019 layout drawings.

Injector quick reference drawing