Difference between revisions of "2021-02-24"
Jump to navigation
Jump to search
Line 26: | Line 26: | ||
* HDIce run2b update (Matt) | * HDIce run2b update (Matt) | ||
* Optics Characterization: Results of deflection study (Yan) | * Optics Characterization: Results of deflection study (Yan) | ||
− | * Engineering Reports | + | * Engineering Reports: BPM Characterization[https://wiki.jlab.org/ciswiki/images/9/99/UITF_stripline_BPM_study_John_Musson_2_17_21.pdf](Musson), Yao/Bunchlength Test[https://wiki.jlab.org/ciswiki/index.php/Reza%27s_thoughts_on_bunchlength_measurement_at_UITF](Kazimi), others... |
* Engineering plan for change request (Mike) | * Engineering plan for change request (Mike) | ||
* Other business | * Other business |
Revision as of 12:49, 23 February 2021
Meeting Information
The meeting will be on
Connecting
To connect to the meeting, please do the following:Wednesday February 10, 2020 at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Rough timetable:
- HDIce run2b ~(March 1-13)
- CMTF tests with C75-1 (late-March - early-June). More refined CMTF schedule / testing duration?
- UITF beamline Modification in parallel to install new beamline
- Supplementary Shielding Installation: Early/Mid-June
- Beamline Commissioning / Test Plans / Shielding Verification: Late June / Early July
- First commissioning of water irradiation beamline in ~July/August
Short term plan[2]
New items for discussion:
- ERR Results (Mike)
- HDIce run2b update (Matt)
- Optics Characterization: Results of deflection study (Yan)
- Engineering Reports: BPM Characterization[3](Musson), Yao/Bunchlength Test[4](Kazimi), others...
- Engineering plan for change request (Mike)
- Other business