Difference between revisions of "AIPINJ - Layouts"

From Ciswikidb
Jump to navigation Jump to search
Line 1: Line 1:
 
== Injector quick reference drawing ==
 
== Injector quick reference drawing ==
 +
* Updated (Feb '21) Inj Quick Reference, Rev17beta, Draft 2 [[media:12GeV injector quick reference rev17 DRAFT-2.pdf]]
 
* Pre-Upgrade (April 2020) injector quick reference : [[media:12GeV_injector_quick_reference_rev16.pdf]]
 
* Pre-Upgrade (April 2020) injector quick reference : [[media:12GeV_injector_quick_reference_rev16.pdf]]
* Updated (Feb '21) Inj Quick Reference, Rev17beta, Draft 2 [[media:12GeV injector quick reference rev17 DRAFT-2.pdf]]
 
  
 
==Phase 1 - Songsheet ==
 
==Phase 1 - Songsheet ==
 +
* Feb 23, 2021 - Preliminary songsheet update [[media:210223_ACC0002845-0001, INJECTOR, REV C.pdf]]
 +
* Correct order of MBH2I01AH/V and MBH2I01H/V, put the one with the "A" second
 +
* Correct order of VIP0I03 and MED0I03
 
* Feb 18, 2021 - Preliminary songsheet update [[media:210218_ACC0002845-0001, INJECTOR, REV C.pdf]]
 
* Feb 18, 2021 - Preliminary songsheet update [[media:210218_ACC0002845-0001, INJECTOR, REV C.pdf]]
 
:VIP2I01A => VIP2I00A  
 
:VIP2I01A => VIP2I00A  

Revision as of 13:51, 24 February 2021

Injector quick reference drawing

Phase 1 - Songsheet

VIP2I01A => VIP2I00A
VIP2I01B => VIP2I00B
VIP2I01C => VIP2I00C
VIP2I01 => VIP2I00
ILL2I01DCANO => ILL2I00DCANO
VGP0I01 => VGP0I01A

Phase 1 - CED Layout Info

Phase 1 - Gun to Chopper Layouts

-sequence just before the gun valve goes like this if possible: bellows + bpm/corr + valve.
-remove the pink rectangular placeholders for quadrupoles
-sequence after Vertical Wien: viewer/cross + bpm/corr + bellows, then pipe that solenoids are attached
-restore gap between the FG solenoids as exists in tunnel today
-sequence after Horizonal Wien: viewer/cross + prebuncher + bpm/corr, then bellows
-if moving valve/DP can upstream a little helps w/layout that's OK, keep subsequent solenoid located as shown

Phase 2 - Booster Layouts

Note: At the November 12, 2019 Modeling meeting [1], we decided to move the buncher to the midpoint position (between the centerline of the choppers and the centerline of the 2-cell in the booster). The buncher position in the July 2019 layout drawings is not the midpoint position; the buncher is shifted closer to the choppers in the July 2019 layout drawings.

-QCM was .32" further downstream. so all those interfaces moved.
-distance between chopper cavities was 59.32", so distance from center of choppers to downstream face of chopper #2 increased from 29.65" to 29.66".
-buncher, IFY0I06, MB00I06, A3, YAO cavity, A4 all moved slightly downstream.
-YAO cavity was .37" longer than the design drawing.

Overall Phase 1 & 2 AIPINJ Layouts

Note: At the November 12, 2019 Modeling meeting [2], we decided to move the buncher to the midpoint position (between the centerline of the choppers and the centerline of the 2-cell in the booster). The buncher position in the July 2019 layout drawings is not the midpoint position; the buncher is shifted closer to the choppers in the July 2019 layout drawings.