Difference between revisions of "2/26/21 - Bi-weekly meeting"
Jump to navigation
Jump to search
(Created page with "; To-Do list from 2/12/21 # Joe - distance flange to beam center CEBAF vs UITF # Joe - copper ladder drawings if available, cooling spec, what would have to change to get it...") |
|||
(5 intermediate revisions by one other user not shown) | |||
Line 1: | Line 1: | ||
; To-Do list from 2/12/21 | ; To-Do list from 2/12/21 | ||
− | + | * Joe - distance flange to beam center CEBAF vs UITF | |
− | + | ** Done | |
− | + | ||
− | + | * Joe - copper ladder drawings if available, cooling spec, what would have to change to get it installed in CEBAF or UITF | |
− | + | ** Done | |
− | + | ||
− | + | * Marcy - select gold targets | |
− | + | ||
− | + | * Jim - poly diamond sandwich design sketches (how mount to single crystal, metal) | |
− | + | ||
+ | * Joe/Marcy - get existing tunnel camera framed with central beam pixel on old ladder and not moved before June install | ||
+ | ** Yes, we would do this later | ||
+ | |||
+ | * Marcy - any tech note on thickness, statistics, target and beam scans? | ||
+ | |||
+ | * Riad - send Euclid the tech notes on asymmetry as function of data rate? | ||
+ | |||
+ | * Joe - check if all gold, diamond, and phosphor can be round (no square ladder mounts needed) | ||
+ | ** Yes, any target in holder with 2 holes to rectangular ladder (or make new ladder) | ||
+ | |||
+ | * Andrei/Dave - could send Euclid the Hall A diamond data, also work w/Andrei on thermal after Euclid provides the ladder design (can do limiting case of all-radiative early) | ||
+ | |||
+ | * Biweekly with core (Eric, Andrei, Joe) and add others as needed, 30 minutes at 3pm Fri Eastern time | ||
+ | ** Yes, 2/26 |
Latest revision as of 15:04, 26 February 2021
- To-Do list from 2/12/21
- Joe - distance flange to beam center CEBAF vs UITF
- Done
- Joe - copper ladder drawings if available, cooling spec, what would have to change to get it installed in CEBAF or UITF
- Done
- Marcy - select gold targets
- Jim - poly diamond sandwich design sketches (how mount to single crystal, metal)
- Joe/Marcy - get existing tunnel camera framed with central beam pixel on old ladder and not moved before June install
- Yes, we would do this later
- Marcy - any tech note on thickness, statistics, target and beam scans?
- Riad - send Euclid the tech notes on asymmetry as function of data rate?
- Joe - check if all gold, diamond, and phosphor can be round (no square ladder mounts needed)
- Yes, any target in holder with 2 holes to rectangular ladder (or make new ladder)
- Andrei/Dave - could send Euclid the Hall A diamond data, also work w/Andrei on thermal after Euclid provides the ladder design (can do limiting case of all-radiative early)
- Biweekly with core (Eric, Andrei, Joe) and add others as needed, 30 minutes at 3pm Fri Eastern time
- Yes, 2/26