Line 2,399: Line 2,399:
 
|- style="background-color:#DFDCBA;"
 
|- style="background-color:#DFDCBA;"
 
| style="vertical-align:middle;" | '''Tunnel'''<br /> Morning
 
| style="vertical-align:middle;" | '''Tunnel'''<br /> Morning
| style="vertical-align:middle;" | Viewer HCO (1 ppl)<br />Wien System HCO (1-2ppl)<br />Ion pump noise (1 ppl)<br />1/2 waveplate T/S
+
| style="vertical-align:middle;" | Viewer HCO (1 ppl)<br />0I02 Harp Electronics (1 ppl)<br />Ion pump noise (1 ppl)<br />1/2 waveplate T/S
| Viewer HCO (1 ppl)<br />0I02 Harp Electronics (1 ppl)<br />Ion pump noise (1ppl)<br />1/2 waveplate T/S
+
| Viewer HCO (1 ppl)<br />Harp HCO (1 ppl)<br />Ion pump noise (1ppl)<br />1/2 waveplate T/S
 
| style="vertical-align:middle;" | 830-9a: Cryo tour (3ppl) <br>''2B Alignment''
 
| style="vertical-align:middle;" | 830-9a: Cryo tour (3ppl) <br>''2B Alignment''
 
| style="vertical-align:middle;" |  
 
| style="vertical-align:middle;" |  

Revision as of 20:02, 7 May 2021

2020 Weeks 1 through 13

Week 14 (Jan 4 - Jan 8)

Week 15 (Jan 11 - Jan 15)

Week 16 (Jan 18 - Jan 22 +weekend)

Week 17 (Jan 25 - Jan 29)

Week 18 (Feb 1 - Feb 5)

Week 19 (Feb 8 - Feb 12)

Week 20 (Feb 15 - Feb 19)

Week 21 (Feb 22 - Feb 26)

Week 22 (Mar 1- Mar 5)

Week 23 (Mar 8 - Mar 12)

Week 24 (Mar 15 - Mar 19)

Week 25 (Mar 22 - Mar 26)

Week 26 (Mar 29 - Apr 2)

Week 27 (Apr 5 - Apr 9)

Week 28 (Apr 12 - Apr 16)

Week 29 (Apr 19 - Apr 23)

Week 30 (Apr 26 - Apr 30)

Week 31 (May 3 - May 7)

Collapse
Tunnel work
  • System re-connects and HCO (EES, CIS, Ops)


  • A1-region bake takedown (Stutzman, Bullard) Mon
  • VBV2I01A Solenoid Air Leak T/S (Windham) Mon
  • Laser hut work (Zhang)
  • Photocathode shuffle (Grames)
    • Remove bulk GaAs
    • Load in SSL cathodes
    • Activate cathode
  • Ion pump checkout (Stutzman)
    • Set operational voltages
    • Hi-pot FE'ing pumps
    • Configure system for EPICS


  • Main airline leaky valve swap (pics) (MechInstall) Thurs
  • Viewer reconnects and HCO (Norris)
  • Harp reconnects and HCO (Dela Cruz)
  • Magnet Connections and HCO (Coleman)
    • Layout terminal blocks
    • Magnet lead reinforcement
    • Magnet wiring
    • Install MDR1I02 (CIS, Grames)
  • Warm RF HCO (Wissman, Farrish)
    • Chopper turn-on, conditioning
    • Buncher turn-on, conditioning
    • Capture turn-on, conditioning
    • Prebuncher readback calibrations, GDR operation (Plawski)
  • 60Hz electrical noise snooping (Suleiman) Sat
  • Helicity magnet HCO (Suleiman) Sat
ISB Work
  • System re-connects / associated rack work
  • CIS Rack Work, IN01* (Windham)
  • Magnet Cabling, IN02B{10,11,22,26}, IN04B10 (DC Power, Coleman)
  • Wien HV System, IN01B0{0,1} (Dela Cruz)
  • Penetration 78 (IN02B18) and 86 (IN02B23) Stone Top-Off (MechInstall) Tues early AM
  • VEPCO Automatic Voltage Regulators Test, ATLis 22392 Friday
    • Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
    • Incoming power voltage variation < +/- 10%
    • "Be prepared for a power interruption"

Injector Tunnel and Service Building

Location
Time
Mon 5/3 Tue 5/4 Wed 5/5 Thu 5/6 Fri 5/7 Sa 5/8 Su 5/9
InjSB
All Day
Systems HCO
CIS Rack Work
Systems HCO
CIS Rack Work
Systems HCO
CIS Rack Work
Systems HCO
CIS Rack Work
⚡VEPCO Voltage Tests
Systems HCO
CIS Rack Work
InjSB
Early
Morning
<9a
Associated Rack Work Chopper/Buncher HCO Chopper/Buncher HCO Buncher/Chopper HCO Viewer/harp HCO
InjSB
Morning
Chopper/Buncher HCO
Prebuncher Rdbk Cals
Chopper/Buncher HCO
Wien Sys Walkthru
Pene 78 & 86 Top-Off
Chopper/Buncher HCO
Wien HV Cable Chkout
Buncher/Chopper HCO Chopper Vac Intlk Testing
9-11a: Wien HV Calibrations
VBV0I02 UHV Interlocks
Magnet HCO Magnet HCO
InjSB
Afternoon
Chopper/Buncher HCO
Prebuncher Rdbk Cals
Magnet re-connects, HCO
Chopper/Buncher HCO
Magnet re-connects, HCO
Chopper/Buncher HCO
Magnet re-connects, HCO
Magnet re-connects, HCO
4p: Capture HCO, Conditioning
Magnet re-connects, HCO
VBV0I02 UHV Interlocks
Magnet HCO Magnet HCO
Tunnel
All Day
CIS Reconnects
A1-region Bake Takedown
CIS Vacuum Work
Ion pump checkout
VIP0I01/1A HiPot
Device/line labeling
Other CIS Jobs
PCup, A1, A2 LCW
PCup, A1 Current Pigtails
Photocathode shuffle
CIS Laser Hut Work:
*Laser checks
*1/2 waveplate T/S
System Reconnects & HCO
⚡VEPCO Voltage Tests
System Reconnects & HCO
Tunnel
Early
Morning
<9a
Viewers (1 ppl) (away from A1)
A1-region bake takedown
Viewers (1 ppl)
Wien Interlock Cables (1 ppl)
CIS Jobs (1-2 ppl)
Viewers (1 ppl)
Harp / Wien (1 ppl)
BPM (1 ppl)
Buncher, Capture hook-ups (1 ppl)
7a: Main Airline Valve Swap (2ppl)
Harp / Wien (1ppl)
Waterflow Interlocks /
ItoV System HCO (1 ppl)
* Craning in cage/suitcase
for equipment removal (1-2ppl)
* Viewers (1 ppl)
* Harp (1ppl)
Tunnel
Morning
Viewers (1 ppl) (away from A1)

A1-region Leak Checks
Viewers (1 ppl)
11-1130a: Wien Sys Walkthru (2 ppl)
CIS Vac Work (1-2 ppl)
Viewers (1 ppl)
9a-noon: Wien HV Cable Chkout (2ppl)
BPM (1 ppl)
A1, A2, PCup LCW (1 ppl)
Wien HV T/S (1-2 ppl)
Waterflow Interlocks /
ItoV System HCO (1 ppl)
Ion pump T/S (1ppl)
MDR1I02 Cabling (1ppl)
1/2 waveplate T/S
Viewers (1 ppl)
9a: Wien HV Cals (1-2 ppl)
10a: IPM1I02 Connect/HCO (1-2ppl)
NEG Terminations (1ppl)
1/2 waveplate T/S
Magnet Resistances, Inductances, Mapping (1-2ppl) Magnet Resistances, Inductances, Mapping (1-2ppl)
Tunnel
Afternoon
A1-region reattachments --
air/water lines, pickups,
control boxes/solenoids
Magnet (2-4 ppl)
Magnet (3 ppl)
Swings (4p): Lock-up, 0L02 HPA PSS Cert
After: PSS Kicker Install
Magnet (2-4 ppl)
Laser hut work
4p: Lock-up for Capture HCO
Magnet (2-4 ppl)
Laser hut work
4p: PSS Kicker install (1-2ppl)
Magnet Resistances, Inductances, Mapping (1-2ppl)
60Hz Snooping (1ppl)
Helicity Mag HCO (1ppl)
Magnet Resistances, Inductances, Mapping (1-2ppl)

Tunnel Personnel Loading Limits: Injector, upstream of plastic curtain, total=8 -> 4 upstream of laser hut, 4 downstream of laser hut

InjSB Week30 1.png

Points of Contact by system --

  • BPM = Francis
  • Valve Controls = Ketchum
  • ItoV, Picoammeters, Gun FSD Interlocks = Francis
  • Viewers = Norris
  • Harps = Dela Cruz
  • Wien = Dela Cruz
  • Magnet / DC Power = Coleman
  • Warm RF -- prebuncher, buncher, chopper, capture = Wissman
  • 2B Alignment = S&A, Gould
  • PSS = Kowal


Week 32 (May 10 - May 14)

Collapse
Tunnel work
  • Finish HCO ====> Beam Commissioning!
    • First CEBAF beam of 2021
    • First ~4m of Injector newly upgraded


  • Equipment crane-out (MechInstall)
  • Viewer HCO (Norris)
  • Harp 0I02 electronics install and HCO (Dela Cruz)
  • Magnet HCO (Coleman)
  • CIS HCO
    • Laser alignment optimization (Zhang)
    • 1/2 Waveplate T/S (Windham)
    • Photocathode activation (Grames)
    • Wien system HCO (Hernandez-Garcia, Dela Cruz)
    • Ion pump noise investigation (Stutzman)


  • 60Hz electrical noise snooping (Suleiman) evenings


ISB Work
  • CIS Rack Work, IN01* (Windham)
  • Wien System HCO, IN01B0{0,1} (Dela Cruz, Hernandez-Garcia)
  • ItoV System Checkout, FC2 unlock (Francis) Mon
  • Magnet HCO, IN02B{10,11,26}+IN04B10 (Coleman)
  • Viewer HCO, IN01B04+IN03B0{6,7} (Norris)
  • Harp HCO, IN01B03+IN03B06 (Dela Cruz)


  • VEPCO Automatic Voltage Regulators Test, ATLis 22392 Tuesday, 1030a - noon (if all goes well)
    • Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
    • Incoming power voltage variation < +/- 10%
    • "Be prepared for a power interruption"


Injector Tunnel and Service Building

italics = timing less certain
Location
Time
Mon 5/10 Tue 5/11 Wed 5/12 Thu 5/13 Fri 5/14 Sa
5/15
Su
5/16
InjSB
All Day
Hot Checkout ⚡VEPCO Voltage Tests
1030-noon

Hot Checkout
finish? HCO HCO
or/and
Beam Commissioning
Beam Commissioning
InjSB
Early
Morning
<9a
Viewer HCO
ItoV/Picoam. HCO
Viewer HCO
Harp HCO
Viewer HCO
Harp HCO
InjSB
Morning
ItoV HCO, temp FC2 unlock Magnet HCO Magnet HCO
InjSB
Afternoon
Magnet HCO Magnet HCO Magnet HCO
Tunnel
All Day
Hot Checkout ⚡VEPCO Voltage Tests
1030-noon

Hot Checkout
2B Alignment
or
finish? HCO
2B Alignment
or
Beam Commissioning
Beam Commissioning
Tunnel
Early
Morning
<9a
Equipment crane-out (1-2 ppl)
Viewer HCO (1 ppl)
0I02 harp electronics (1ppl)
ItoV/Picoam. HCO (1ppl)
Viewer HCO (1ppl)
Harp HCO (1ppl)
Diagnostics HCO
Tunnel
Morning
Viewer HCO (1 ppl)
0I02 Harp Electronics (1 ppl)
Ion pump noise (1 ppl)
1/2 waveplate T/S
Viewer HCO (1 ppl)
Harp HCO (1 ppl)
Ion pump noise (1ppl)
1/2 waveplate T/S
830-9a: Cryo tour (3ppl)
2B Alignment
PSS Kicker Cert
Tunnel
Afternoon
Laser hut work
Magnet HCO (2-4ppl)
Laser hut work
Magnet HCO (2-4ppl)
4p: PSS Certs
2B Alignment
4p: PSS Certs

Tunnel Personnel Loading Limits: Injector, upstream of plastic curtain, total=8 -> 4 upstream of laser hut, 4 downstream of laser hut


InjSB Week30 1.png


Points of Contact by system --

  • BPM = Francis
  • Valve Controls = Ketchum
  • ItoV, Picoammeters, Gun FSD Interlocks = Francis
  • Viewers = Norris
  • Harps = Dela Cruz
  • Wien = Dela Cruz
  • Magnet / DC Power = Coleman
  • Warm RF -- prebuncher, buncher, chopper, capture = Wissman
  • 2B Alignment = S&A, Gould
  • PSS = Kowal


Penetration Work

Fire System Work