* Short term schedule update:
+
Short term schedule update:
*This week:  
+
This week:  
**Component disconnects (Mostly complete)
+
*Component disconnects (Mostly complete)
*#*Diagnose Chopper slit (Complete - gear box issue; on A5 controls/STAC5 now. Thanks to Scott!)
+
*Diagnose Chopper slit (Complete - gear box issue; on A5 controls/STAC5 now. Thanks to Scott!)
*#*Post 2-d schematic on beam line to guide installation (Completed and posted)
+
*Post 2-d schematic on beam line to guide installation (Completed and posted)
*#*Install more brackets and flange supports on 80/20 (BPM locations; need measurements...) (Completed)
+
*Install more brackets and flange supports on 80/20 (BPM locations; need measurements...) (Completed)
*#*PEPPo magnet/Solenoid installed on 80/20 (Completed)
+
*PEPPo magnet/Solenoid installed on 80/20 (Completed)
*#*Gun work progressing well:
+
*Gun work progressing well:
*#*# [https://logbooks.jlab.org/entry/3876061 Schneedle replaced]
+
*# [https://logbooks.jlab.org/entry/3876061 Schneedle replaced]
*#*# [https://logbooks.jlab.org/entry/3876599 Scheedle, anode, and cathode aligned]
+
*# [https://logbooks.jlab.org/entry/3876599 Scheedle, anode, and cathode aligned]
*#*#[https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule]
+
*#[https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule]
*#*Vacuum work / Beam line assembly Fridays starting at 10:30 am for any who want to participate
+
*Vacuum work / Beam line assembly Fridays starting at 10:30 am for any who want to participate
  
*Next Week:  
+
Next Week:  
*#* Alignment today (Wed.) or Friday of big pieces (solenoid, viewer crosses, FC4)
+
* Alignment today (Wed.) or Friday of big pieces (solenoid, viewer crosses, FC4)
*#* Get area up to transition after solenoid under vacuum. Install valve/bellow/bpm.
+
* Get area up to transition after solenoid under vacuum. Install valve/bellow/bpm.
*#* Install 4 5/8" BPMs after insertion measurements completed
+
* Install 4 5/8" BPMs after insertion measurements completed
*#* Break vacuum in FC3 region
+
* Break vacuum in FC3 region
  
 
2 weeks:
 
2 weeks:
*#*Build 80/20 support structure; add mounting plates/brackets/etc. (Pb table components awaiting delivery)
+
*Build 80/20 support structure; add mounting plates/brackets/etc. (Pb table components awaiting delivery)
*#*Pull Heliax from Sprectrum analyzer/Control room >> Buncher
+
*Pull Heliax from Sprectrum analyzer/Control room >> Buncher
*#*Unistrut mounting for cables / gas bottle rack - Neal will do when available
+
*Unistrut mounting for cables / gas bottle rack - Neal will do when available
*#*4th terminal system in Control room under assembly/rebuild
+
*4th terminal system in Control room under assembly/rebuild
*#*Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining.
+
*Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining.
*#*[https://wiki.jlab.org/ciswiki/index.php/To-do_list Items from To-do list...]
+
*[https://wiki.jlab.org/ciswiki/index.php/To-do_list Items from To-do list...]
* Engineering
+
 
*#Insertion measurements in progress on 4 5/8" BPMs
+
Engineering
 +
*Insertion measurements in progress on 4 5/8" BPMs
 
* Other business
 
* Other business
  

Revision as of 12:05, 11 May 2021

Meeting Information

Connecting

To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.

  1. To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
  2. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
  3. To join via phone, use one of the following numbers and the Conference ID: 946721076.
    • Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

Agenda

Schedule

Rough timetable:

  1. CMTF tests with C75-1 (late-March - early-June).
  2. UITF beam line modification
  3. Supplementary Shielding Installation: Mid-June
  4. Beamline Commissioning / Test Plans / Shielding Verification
  5. 7/26/21 Start Hot Check-out
  6. Commission new beam line and execute experiment

Long Term Schedule (McCaughan) Strawman

New items for discussion:

Short term schedule update: This week:

  • Component disconnects (Mostly complete)
  • Diagnose Chopper slit (Complete - gear box issue; on A5 controls/STAC5 now. Thanks to Scott!)
  • Post 2-d schematic on beam line to guide installation (Completed and posted)
  • Install more brackets and flange supports on 80/20 (BPM locations; need measurements...) (Completed)
  • PEPPo magnet/Solenoid installed on 80/20 (Completed)
  • Gun work progressing well:
    1. Schneedle replaced
    2. Scheedle, anode, and cathode aligned
    3. Gun rebuild schedule
  • Vacuum work / Beam line assembly Fridays starting at 10:30 am for any who want to participate

Next Week:

  • Alignment today (Wed.) or Friday of big pieces (solenoid, viewer crosses, FC4)
  • Get area up to transition after solenoid under vacuum. Install valve/bellow/bpm.
  • Install 4 5/8" BPMs after insertion measurements completed
  • Break vacuum in FC3 region

2 weeks:

  • Build 80/20 support structure; add mounting plates/brackets/etc. (Pb table components awaiting delivery)
  • Pull Heliax from Sprectrum analyzer/Control room >> Buncher
  • Unistrut mounting for cables / gas bottle rack - Neal will do when available
  • 4th terminal system in Control room under assembly/rebuild
  • Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining.
  • Items from To-do list...

Engineering

  • Insertion measurements in progress on 4 5/8" BPMs
  • Other business

Reports on Open Action Items:

  • Action Items:
    1. Formal run plan

Back to Main Meeting Minutes Page