Line 2,385: Line 2,385:
 
| '''2B Alignment'''<br />'''Hot Checkout'''
 
| '''2B Alignment'''<br />'''Hot Checkout'''
 
| '''2B Alignment'''<br />'''Hot Checkout''' <br> CIS Jobs = Gun Valve T/S <br> TMG shutter T/S
 
| '''2B Alignment'''<br />'''Hot Checkout''' <br> CIS Jobs = Gun Valve T/S <br> TMG shutter T/S
| '''Site Phone Outages<br />8a - 5p'''
+
| Wien HV Soak <br> '''Site Phone Outages<br />8a - 5p'''
|  
+
| Wien HV Soak
 
|- style="background-color:#DFDCBA;"
 
|- style="background-color:#DFDCBA;"
 
| '''Tunnel'''<br /> Early <br /> Morning <br /> <9a
 
| '''Tunnel'''<br /> Early <br /> Morning <br /> <9a
Line 2,394: Line 2,394:
 
| 2B Alignment (2 ppl)
 
| 2B Alignment (2 ppl)
 
| 2B Alignment (2 ppl) <br> 0I02 Anti-collision (1 ppl) <br> CIS Jobs (1-2ppl)
 
| 2B Alignment (2 ppl) <br> 0I02 Anti-collision (1 ppl) <br> CIS Jobs (1-2ppl)
| Wien HV Soak
+
|  
| Wien HV Soak
+
|  
 
|- style="background-color:#DFDCBA;"
 
|- style="background-color:#DFDCBA;"
 
| '''Tunnel'''<br /> Morning
 
| '''Tunnel'''<br /> Morning

Revision as of 13:05, 14 May 2021

2020 Weeks 1 through 13

Week 14 (Jan 4 - Jan 8)

Week 15 (Jan 11 - Jan 15)

Week 16 (Jan 18 - Jan 22 +weekend)

Week 17 (Jan 25 - Jan 29)

Week 18 (Feb 1 - Feb 5)

Week 19 (Feb 8 - Feb 12)

Week 20 (Feb 15 - Feb 19)

Week 21 (Feb 22 - Feb 26)

Week 22 (Mar 1- Mar 5)

Week 23 (Mar 8 - Mar 12)

Week 24 (Mar 15 - Mar 19)

Week 25 (Mar 22 - Mar 26)

Week 26 (Mar 29 - Apr 2)

Week 27 (Apr 5 - Apr 9)

Week 28 (Apr 12 - Apr 16)

Week 29 (Apr 19 - Apr 23)

Week 30 (Apr 26 - Apr 30)

Week 31 (May 3 - May 7)

Week 32 (May 10 - May 14)

Collapse
Tunnel work
  • Finish HCO ====> Beam Commissioning!
    • First CEBAF beam of 2021
    • First ~4m of Injector newly upgraded


  • Equipment crane-out (MechInstall)
  • Viewer HCO (Norris)
  • Harp 0I02 electronics install and HCO (Dela Cruz)
  • Magnet HCO (Coleman)
  • CIS HCO
    • Laser alignment optimization (Zhang)
    • 1/2 Waveplate T/S (Windham)
    • Photocathode activation (Grames)
    • Wien system HCO (Hernandez-Garcia, Dela Cruz)
    • Ion pump noise investigation (Stutzman)


  • 60Hz electrical noise snooping (Suleiman) evenings


ISB Work
  • CIS Rack Work, IN01* (Windham)
  • Wien System HCO, IN01B0{0,1} (Dela Cruz, Hernandez-Garcia)
  • ItoV System Checkout, FC2 unlock (Francis) Mon
  • Magnet HCO, IN02B{10,11,26}+IN04B10 (Coleman)
  • Viewer HCO, IN01B04+IN03B0{6,7} (Norris)
  • Harp HCO, IN01B03+IN03B06 (Dela Cruz)


  • VEPCO Automatic Voltage Regulators Test, ATLis 22392 Tuesday, 1030a - noon (if all goes well)
    • Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
    • Incoming power voltage variation < +/- 10%
    • "Be prepared for a power interruption"


Injector Tunnel and Service Building

italics = timing less certain
Location
Time
Mon 5/10 Tue 5/11 Wed 5/12 Thu 5/13 Fri 5/14 Sa
5/15
Su
5/16
InjSB
All Day
Hot Checkout Hot Checkout ⚡VEPCO Voltage Tests
9-11a

Hot Checkout
Hot Checkout Hot Checkout
Service Building Clean-Up
Site Phone Outages
8a - 5p
InjSB
Early
Morning
<9a
Viewer HCO
ItoV/Picoam. HCO
Viewer HCO
Harp HCO
Viewer HCO
Harp Cross-Connect Wiring, HCO
ItoV System HCO
InjSB
Morning
V-Wien Comm Conn Remedying Magnet HCO ItoV HCO
Magnet HCO
Wien HV Interlock
Testing and HV Soak
Wien HV Soak (+B-field?)
InjSB
Afternoon
Magnet HCO Magnet HCO Magnet HCO Wien HV Soak
Magnet HCO
Wien HV Soak
Magnet HCO
Tunnel
All Day
Hot Checkout Hot Checkout
CIS Work --
* Airline->metal
* IP Noise T/S
⚡VEPCO Voltage Tests
9-11a

Hot Checkout
CIS Work
2B Alignment
Hot Checkout
2B Alignment
Hot Checkout
CIS Jobs = Gun Valve T/S
TMG shutter T/S
Wien HV Soak
Site Phone Outages
8a - 5p
Wien HV Soak
Tunnel
Early
Morning
<9a
Equipment crane-out (1-2 ppl)
Viewer HCO (1 ppl)
0I02 harp electronics (1ppl)
Photocathode activation (1ppl)
Viewer HCO (1ppl)
Harp HCO (1ppl)
Viewer HCO (1 ppl)
0I02 anti-collision testing (1 ppl)
ItoV/Picoam. HCO (1ppl)
2B Alignment (2 ppl) 2B Alignment (2 ppl)
0I02 Anti-collision (1 ppl)
CIS Jobs (1-2ppl)
Tunnel
Morning
Viewer HCO (1 ppl)
Wien interlock (1-2ppl)
Ion pump noise (1 ppl)
1/2 waveplate T/S
Viewer HCO (1 ppl)
Harp HCO (1 ppl)
CIS Work (1-2ppl)
1/2 waveplate T/S
830-9a: Cryo tour (3ppl)
Viewer HCO (1 ppl)
0I02 anti-collision testing (1 ppl)
ItoV/Picoam. HCO (1ppl)
CIS Work (1-2ppl)
2B Alignment (2 ppl) 2B Alignment (2ppl)
0I02 Anti-collision (1 ppl)
CIS Jobs (1-2ppl)
Laser Hut Work
FML HVAC Reconfig (2 ppl)?
60 Hz Snooping
Tunnel
Afternoon
Laser hut work
Magnet HCO (2-4ppl)
Laser hut work
Magnet HCO (2-4ppl)
Photocathode activation (1 ppl)
Laser hut work
Magnet HCO (2-4ppl)
4p Lock-Up: PSS Certs -> BP
Laser hut work
Magnet HCO (2-4ppl)
4p Lock-Up: PSS Certs -> BP
Laser hut work
Magnet HCO (2-4ppl)
QE Scan? (2 ppl)
60 Hz Snooping

Tunnel Personnel Loading Limits: Injector, upstream of plastic curtain, total=8 -> 4 upstream of laser hut, 4 downstream of laser hut


InjSB Week30 1.png


Points of Contact by system --

  • BPM = Francis
  • Valve Controls = Ketchum
  • ItoV, Picoammeters, Gun FSD Interlocks = Francis
  • Viewers = Norris
  • Harps = Dela Cruz
  • Wien = Dela Cruz
  • Magnet / DC Power = Coleman
  • Warm RF -- prebuncher, buncher, chopper, capture = Wissman
  • 2B Alignment = S&A, Gould
  • PSS = Kowal


Week 33 (May 17 - May 21)

Collapse
Tunnel work
  • Finish HCO ====> Beam Commissioning!
    • First CEBAF beam of 2021
    • First ~4m of Injector newly upgraded


  • Equipment crane-out (MechInstall)
  • Viewer HCO (Norris)
  • Harp 0I02 electronics install and HCO (Dela Cruz)
  • Magnet HCO (Coleman)
  • CIS HCO
    • Laser alignment optimization (Zhang)
    • 1/2 Waveplate T/S (Windham)
    • Photocathode activation (Grames)
    • Wien system HCO (Hernandez-Garcia, Dela Cruz)
    • Ion pump noise investigation (Stutzman)


  • 60Hz electrical noise snooping (Suleiman) evenings


ISB Work
  • CIS Rack Work, IN01* (Windham)
  • Wien System HCO, IN01B0{0,1} (Dela Cruz, Hernandez-Garcia)
  • ItoV System Checkout, FC2 unlock (Francis) Mon
  • Magnet HCO, IN02B{10,11,26}+IN04B10 (Coleman)
  • Viewer HCO, IN01B04+IN03B0{6,7} (Norris)
  • Harp HCO, IN01B03+IN03B06 (Dela Cruz)


  • VEPCO Automatic Voltage Regulators Test, ATLis 22392 Tuesday, 1030a - noon (if all goes well)
    • Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
    • Incoming power voltage variation < +/- 10%
    • "Be prepared for a power interruption"


Injector Tunnel and Service Building

Location
Time
Mon 5/17 Tue 5/18 Wed 5/19 Thu 5/20 Fri 5/21 Sa
5/22
Su
5/23
InjSB
All Day
Hot Checkout Hot Checkout ⚡VEPCO Voltage Tests
9-11a

Hot Checkout
Hot Checkout Hot Checkout
Service Building Clean-Up
Site Phone Outages
8a - 5p
InjSB
Early
Morning
<9a
Viewer HCO
ItoV/Picoam. HCO
Viewer HCO
Harp HCO
Viewer HCO
Harp Cross-Connect Wiring, HCO
ItoV System HCO
InjSB
Morning
V-Wien Comm Conn Remedying Magnet HCO ItoV HCO
Magnet HCO
Wien HV Interlock
Testing and HV Soak
Wien HV Soak (+B-field?)
InjSB
Afternoon
Magnet HCO Magnet HCO Magnet HCO Wien HV Soak
Magnet HCO
Wien HV Soak (+B-field?)
Magnet HCO
Tunnel
All Day
Hot Checkout Hot Checkout
CIS Work --
* Airline->metal
* IP Noise T/S
⚡VEPCO Voltage Tests
9-11a

Hot Checkout
CIS Work
2B Alignment
Hot Checkout
2B Alignment
Hot Checkout
CIS Jobs = Gun Valve T/S
TMG shutter T/S
Site Phone Outages
8a - 5p
Tunnel
Early
Morning
<9a
Equipment crane-out (1-2 ppl)
Viewer HCO (1 ppl)
0I02 harp electronics (1ppl)
Photocathode activation (1ppl)
Viewer HCO (1ppl)
Harp HCO (1ppl)
Viewer HCO (1 ppl)
0I02 anti-collision testing (1 ppl)
ItoV/Picoam. HCO (1ppl)
2B Alignment (2 ppl) 2B Alignment (2 ppl)
0I02 Anti-collision (1 ppl)
CIS Jobs (1-2ppl)
Tunnel
Morning
Viewer HCO (1 ppl)
Wien interlock (1-2ppl)
Ion pump noise (1 ppl)
1/2 waveplate T/S
Viewer HCO (1 ppl)
Harp HCO (1 ppl)
CIS Work (1-2ppl)
1/2 waveplate T/S
830-9a: Cryo tour (3ppl)
Viewer HCO (1 ppl)
0I02 anti-collision testing (1 ppl)
ItoV/Picoam. HCO (1ppl)
CIS Work (1-2ppl)
2B Alignment (2 ppl) 2B Alignment (2ppl)
0I02 Anti-collision (1 ppl)
CIS Jobs (1-2ppl)
Laser Hut Work
FML HVAC Reconfig (2 ppl)?
Tunnel
Afternoon
Laser hut work
Magnet HCO (2-4ppl)
Laser hut work
Magnet HCO (2-4ppl)
Photocathode activation (1 ppl)
Laser hut work
Magnet HCO (2-4ppl)
4p Lock-Up: PSS Certs -> BP
Laser hut work
Magnet HCO (2-4ppl)
4p Lock-Up: PSS Certs -> BP
Laser hut work
Magnet HCO (2-4ppl)
QE Scan? (2 ppl)

Tunnel Personnel Loading Limits: Injector, upstream of plastic curtain, total=8 -> 4 upstream of laser hut, 4 downstream of laser hut

Penetration Work

Fire System Work