Line 2,440: Line 2,440:
 
<div class="mw-collapsible">
 
<div class="mw-collapsible">
  
 
+
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22462?load=Task&task_id=22462&allComments=yes 22462 0I02 Harp Repair]
;'''ISB Work '''
+
** Wednesday: beamline component disconnects and vent, begin harp swap
* CIS Rack Work, IN01* (Windham)
+
** Thursday: complete harp swap, pumpdown, leak check, verify harp operation, setup and begin overnight bake
* Wien System HCO, IN01B0{0,1} (Dela Cruz, Hernandez-Garcia)
+
** Friday: Bake cool by 8AM. Re-install beamline components, re-HCO components
* ItoV System Checkout, FC2 unlock (Francis) ''Mon''
 
* Magnet HCO, IN02B{10,11,26}+IN04B10 (Coleman)
 
* Viewer HCO, IN01B04+IN03B0{6,7} (Norris)
 
* Harp HCO, IN01B03+IN03B06 (Dela Cruz)
 
  
  
Line 2,491: Line 2,487:
 
| Magnet HCO
 
| Magnet HCO
 
| Magnet HCO
 
| Magnet HCO
| Magnet HCO
+
| Magnet Rack HCO
 
|  
 
|  
 
|  
 
|  
Line 2,505: Line 2,501:
 
| 0I02 anti-collision (1 ppl)<br />
 
| 0I02 anti-collision (1 ppl)<br />
 
|  
 
|  
| Turbopump hook-up (1ppl)
+
| Turbopump hook-up at 0I06 (1ppl)
 
|  
 
|  
 
|  
 
|  
Line 2,514: Line 2,510:
 
| 830-9a: Cryo tour (3ppl) <br> 0I02 Harp Repair (3ppl) <br> ''H-wien Resistor Add (1ppl)'' <br> Laser mirror work  
 
| 830-9a: Cryo tour (3ppl) <br> 0I02 Harp Repair (3ppl) <br> ''H-wien Resistor Add (1ppl)'' <br> Laser mirror work  
 
| 0I02 Harp repair (3ppl)  
 
| 0I02 Harp repair (3ppl)  
| 0I02-"region" Reconnects -- <br> Magnets <br> YAG, A2, BPM <br> A2 LCW, valve controls <br> PSS Kicker
+
| 0I02-"region" Reconnects -- <br> Magnets <br> YAG, A2, BPM <br> A2 LCW, valve controls, ion pumps <br> PSS Kicker
 
|- style="background-color:#DFDCBA;"
 
|- style="background-color:#DFDCBA;"
 
| '''Tunnel'''<br /> Afternoon
 
| '''Tunnel'''<br /> Afternoon
 
| ''Laser hut work?''<br />Magnet HCO (2-5ppl)<br />Evening: 60Hz snooping
 
| ''Laser hut work?''<br />Magnet HCO (2-5ppl)<br />Evening: 60Hz snooping
 
| 1p: Lock-up: PSS Certs<br />''Beam Commissioning''
 
| 1p: Lock-up: PSS Certs<br />''Beam Commissioning''
| 0I02 Harp Repair <br> ''3p?'' Lock-up: PSS Certs
+
| 0I02 Harp Repair (3ppl) <br> ''3p?'' Lock-up: PSS Certs
| 0I02 Harp Repair
+
| 0I02 Harp Repair (3ppl)
 
| Finish reconnects <br> Beam Auth <br> ''Beam Commissioning''
 
| Finish reconnects <br> Beam Auth <br> ''Beam Commissioning''
 
|}
 
|}

Revision as of 20:58, 18 May 2021

2020 Weeks 1 through 13

Week 14 (Jan 4 - Jan 8)

Week 15 (Jan 11 - Jan 15)

Week 16 (Jan 18 - Jan 22 +weekend)

Week 17 (Jan 25 - Jan 29)

Week 18 (Feb 1 - Feb 5)

Week 19 (Feb 8 - Feb 12)

Week 20 (Feb 15 - Feb 19)

Week 21 (Feb 22 - Feb 26)

Week 22 (Mar 1- Mar 5)

Week 23 (Mar 8 - Mar 12)

Week 24 (Mar 15 - Mar 19)

Week 25 (Mar 22 - Mar 26)

Week 26 (Mar 29 - Apr 2)

Week 27 (Apr 5 - Apr 9)

Week 28 (Apr 12 - Apr 16)

Week 29 (Apr 19 - Apr 23)

Week 30 (Apr 26 - Apr 30)

Week 31 (May 3 - May 7)

Week 32 (May 10 - May 14)

Week 33 (May 17 - May 21)

Collapse
  • 22462 0I02 Harp Repair
    • Wednesday: beamline component disconnects and vent, begin harp swap
    • Thursday: complete harp swap, pumpdown, leak check, verify harp operation, setup and begin overnight bake
    • Friday: Bake cool by 8AM. Re-install beamline components, re-HCO components


  • VEPCO Automatic Voltage Regulators Test, ATLis 22392
    • Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
    • Incoming power voltage variation < +/- 10%
    • "Be prepared for a power interruption"


Injector Tunnel and Service Building

Location
Time
Mon 5/17 Tue 5/18 Wed 5/19 Thu 5/20 Fri 5/21
InjSB
All Day
Service Building Clean-Up
Wrapping up HCO
⚡VEPCO Voltage Tests
1030a-noon (4th attempt?)
InjSB
Early
Morning
<9a
InjSB
Morning
Magnet HCO Magnet HCO Magnet Rack HCO
InjSB
Afternoon
Magnet HCO Magnet HCO Magnet Rack HCO
Tunnel
All Day
Wrapping up HCO
Wien HV Soak
Wrapping up HCO
Wien HV Soak
Beam Commissioning
0I02 Harp Repair
⚡VEPCO Voltage Tests
1030a-noon (4th attempt?)
0I02 Harp Repair 0I02 Reconnects
Beam Commissioning?
Tunnel
Early
Morning
<9a
0I02 anti-collision (1 ppl)
Turbopump hook-up at 0I06 (1ppl)
Tunnel
Morning
Magnet HCO (2-5ppl) Magnet HCO
11a: HCO Committee tour (3ppl)
830-9a: Cryo tour (3ppl)
0I02 Harp Repair (3ppl)
H-wien Resistor Add (1ppl)
Laser mirror work
0I02 Harp repair (3ppl) 0I02-"region" Reconnects --
Magnets
YAG, A2, BPM
A2 LCW, valve controls, ion pumps
PSS Kicker
Tunnel
Afternoon
Laser hut work?
Magnet HCO (2-5ppl)
Evening: 60Hz snooping
1p: Lock-up: PSS Certs
Beam Commissioning
0I02 Harp Repair (3ppl)
3p? Lock-up: PSS Certs
0I02 Harp Repair (3ppl) Finish reconnects
Beam Auth
Beam Commissioning

Tunnel Personnel Loading Limits: Injector, upstream of plastic curtain, total=8 -> 4 upstream of laser hut, 4 downstream of laser hut

InjSB Week30 1.png

Penetration Work

Fire System Work