(Created page with "== Meeting Information == ==== Connecting ==== To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST. # To join via a Web Browser, go to the pag...") |
|||
Line 22: | Line 22: | ||
<u>Short term schedule update:</u><br> | <u>Short term schedule update:</u><br> | ||
<u>This week:</u> | <u>This week:</u> | ||
− | + | * Area up to transition after solenoid under vacuum. Ready for RGA leak check. | |
− | + | * Downstream viewer / faraday cup assembly under vacuum. Ready for RGA leak check. | |
− | * Area up to transition after solenoid under vacuum | + | * Second 4 5/8" BPM stolen from elevated line for installation. |
− | * | + | * Roof tiles off for HDIce (5/24), Dilution refrigerator craned out (5/25), and then roof tiles replaced again (5/26). |
− | * | + | * Spool pieces / nipples being fabricated |
*Gun work progressing well: | *Gun work progressing well: | ||
− | *# | + | *# HV chamber evaluation - plan to bake to evaporate lubricant & pump it off, install photocathode, and bake again. |
− | |||
*# [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule] | *# [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule] | ||
*# Minor SF6 leak in HV chamber identified; repair later... | *# Minor SF6 leak in HV chamber identified; repair later... | ||
Line 36: | Line 35: | ||
<u>Next Week:</u> | <u>Next Week:</u> | ||
− | |||
− | |||
* Mount bottle rack in Labyrinth; remove gas bottles to rack. | * Mount bottle rack in Labyrinth; remove gas bottles to rack. | ||
+ | * Wastewater experiment line fully under vacuum (with flange in place of the thin window). | ||
+ | * Install target mechanism | ||
+ | * Build 80/20 support structure; Pb table components awaiting delivery. | ||
+ | * Unistrut mounting for cables - Neal will do when available | ||
+ | * Break vacuum in FC3 region | ||
+ | * Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining. | ||
<u>2 weeks:</u> | <u>2 weeks:</u> | ||
− | |||
− | |||
− | |||
*Pull Heliax from Spectrum analyzer/Control room >> Buncher | *Pull Heliax from Spectrum analyzer/Control room >> Buncher | ||
− | |||
*4th terminal system in Control room under assembly/rebuild | *4th terminal system in Control room under assembly/rebuild | ||
− | |||
− | |||
− | |||
*[https://wiki.jlab.org/ciswiki/index.php/To-do_list Items from To-do list...] | *[https://wiki.jlab.org/ciswiki/index.php/To-do_list Items from To-do list...] | ||
<u>Engineering</u> | <u>Engineering</u> | ||
− | |||
− | |||
− | |||
Other business | Other business | ||
Revision as of 08:52, 20 May 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Long Term Schedule: Gantt (Outstanding tasks)
- Supplementary Shielding Installation: Mid-June
- Beamline Commissioning / Test Plans / Shielding Verification
- 7/26/21 Start Hot Check-out
- Commission new beam line and execute experiment
- Science!!!
New items for discussion:
Short term schedule update:
This week:
- Area up to transition after solenoid under vacuum. Ready for RGA leak check.
- Downstream viewer / faraday cup assembly under vacuum. Ready for RGA leak check.
- Second 4 5/8" BPM stolen from elevated line for installation.
- Roof tiles off for HDIce (5/24), Dilution refrigerator craned out (5/25), and then roof tiles replaced again (5/26).
- Spool pieces / nipples being fabricated
- Gun work progressing well:
- HV chamber evaluation - plan to bake to evaporate lubricant & pump it off, install photocathode, and bake again.
- Gun rebuild schedule
- Minor SF6 leak in HV chamber identified; repair later...
Next Week:
- Mount bottle rack in Labyrinth; remove gas bottles to rack.
- Wastewater experiment line fully under vacuum (with flange in place of the thin window).
- Install target mechanism
- Build 80/20 support structure; Pb table components awaiting delivery.
- Unistrut mounting for cables - Neal will do when available
- Break vacuum in FC3 region
- Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining.
2 weeks:
- Pull Heliax from Spectrum analyzer/Control room >> Buncher
- 4th terminal system in Control room under assembly/rebuild
- Items from To-do list...
Engineering Other business
Reports on Open Action Items:
Action Items:
- Formal run plan (McCaughan)