Difference between revisions of "2021-05-26"
Jump to navigation
Jump to search
(→Agenda) |
|||
Line 45: | Line 45: | ||
<u>2 weeks:</u> | <u>2 weeks:</u> | ||
+ | *Add Mu metal over bellows on wastewater line. | ||
+ | *Switch Wastewater line Vacuum HV from local supplies to house power. Make UED updates as appropriate for vacuum system. | ||
*Pull Heliax from Spectrum analyzer/Control room >> Buncher | *Pull Heliax from Spectrum analyzer/Control room >> Buncher | ||
*4th terminal system in Control room under assembly/rebuild | *4th terminal system in Control room under assembly/rebuild |
Revision as of 08:55, 20 May 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Long Term Schedule: Gantt (Outstanding tasks)
- Supplementary Shielding Installation: Mid-June
- Beamline Commissioning / Test Plans / Shielding Verification
- 7/26/21 Start Hot Check-out
- Commission new beam line and execute experiment
- Science!!!
New items for discussion:
Short term schedule update:
This week:
- Area up to transition after solenoid under vacuum. Ready for RGA leak check.
- Downstream viewer / faraday cup assembly under vacuum. Ready for RGA leak check.
- Second 4 5/8" BPM stolen from elevated line for installation.
- Roof tiles off for HDIce (5/24), Dilution refrigerator craned out (5/25), and then roof tiles replaced again (5/26).
- Spool pieces / nipples being fabricated
- Gun work progressing well:
- HV chamber evaluation - plan to bake to evaporate lubricant & pump it off, install photocathode, and bake again.
- Gun rebuild schedule
- Minor SF6 leak in HV chamber identified; repair later...
Next Week:
- Mount bottle rack in Labyrinth; remove gas bottles to rack.
- Wastewater experiment line fully under vacuum (with flange in place of the thin window).
- Install target mechanism
- Build 80/20 support structure; Pb table components awaiting delivery.
- Unistrut mounting for cables - Neal will do when available
- Break vacuum in FC3 region
- Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining.
2 weeks:
- Add Mu metal over bellows on wastewater line.
- Switch Wastewater line Vacuum HV from local supplies to house power. Make UED updates as appropriate for vacuum system.
- Pull Heliax from Spectrum analyzer/Control room >> Buncher
- 4th terminal system in Control room under assembly/rebuild
- Items from To-do list...
Engineering Other business
Reports on Open Action Items:
Action Items:
- Formal run plan (McCaughan)