;5/21/21 AIPINJ Phase I Installation and HCO Complete.
 +
 
=2020 Weeks 1 through 13 =
 
=2020 Weeks 1 through 13 =
 
<div class="mw-collapsible mw-collapsed">
 
<div class="mw-collapsible mw-collapsed">
Line 2,288: Line 2,290:
  
 
= Week 32 (May 10 - May 14) =
 
= Week 32 (May 10 - May 14) =
<div class="mw-collapsible">
+
<div class="mw-collapsible mw-collapsed">
  
 
;'''Tunnel work '''  
 
;'''Tunnel work '''  
Line 2,348: Line 2,350:
 
| '''⚡VEPCO Voltage Tests<br />9-11a'''<br />'''Hot Checkout'''
 
| '''⚡VEPCO Voltage Tests<br />9-11a'''<br />'''Hot Checkout'''
 
| '''Hot Checkout'''
 
| '''Hot Checkout'''
| ''Beam Commissioning''
+
| '''Hot Checkout''' <br> '''Service Building Clean-Up'''
 
| '''Site Phone Outages<br />8a - 5p'''
 
| '''Site Phone Outages<br />8a - 5p'''
 
|  
 
|  
Line 2,356: Line 2,358:
 
| Viewer HCO<br />Harp HCO
 
| Viewer HCO<br />Harp HCO
 
| Viewer HCO<br />Harp Cross-Connect Wiring, HCO
 
| Viewer HCO<br />Harp Cross-Connect Wiring, HCO
|  
+
| ItoV System HCO
 
|  
 
|  
 
|  
 
|  
Line 2,364: Line 2,366:
 
| V-Wien Comm Conn Remedying
 
| V-Wien Comm Conn Remedying
 
| Magnet HCO
 
| Magnet HCO
| ItoV HCO, temp FC2 unlock <br /> Magnet HCO
+
| ItoV HCO<br /> Magnet HCO
|  
+
| Wien HV Interlock<br />Testing and HV Soak
|  
+
| Wien HV Soak (+B-field?)
 
|  
 
|  
 
|  
 
|  
Line 2,374: Line 2,376:
 
| Magnet HCO
 
| Magnet HCO
 
| Magnet HCO
 
| Magnet HCO
|  
+
| Wien HV Soak<br />Magnet HCO
|  
+
| Wien HV Soak<br />Magnet HCO
 
|  
 
|  
 
|  
 
|  
Line 2,383: Line 2,385:
 
| '''Hot Checkout''' <br /> CIS Work -- <br /> * Airline->metal <br /> * IP Noise T/S
 
| '''Hot Checkout''' <br /> CIS Work -- <br /> * Airline->metal <br /> * IP Noise T/S
 
| '''⚡VEPCO Voltage Tests<br />9-11a'''<br />'''Hot Checkout'''<br />CIS Work
 
| '''⚡VEPCO Voltage Tests<br />9-11a'''<br />'''Hot Checkout'''<br />CIS Work
| '''2B Alignment'''
+
| '''2B Alignment'''<br />'''Hot Checkout'''
| ''Beam Commissioning''
+
| '''2B Alignment'''<br />'''Hot Checkout''' <br> CIS Jobs = Gun Valve T/S <br> TMG shutter T/S
| '''Site Phone Outages<br />8a - 5p'''
+
| Wien HV Soak <br> '''Site Phone Outages<br />8a - 5p'''
|  
+
| Wien HV Soak
 
|- style="background-color:#DFDCBA;"
 
|- style="background-color:#DFDCBA;"
 
| '''Tunnel'''<br /> Early <br /> Morning <br /> <9a
 
| '''Tunnel'''<br /> Early <br /> Morning <br /> <9a
Line 2,393: Line 2,395:
 
| Viewer HCO (1 ppl)<br />0I02 anti-collision testing (1 ppl) <br />ItoV/Picoam. HCO (1ppl)
 
| Viewer HCO (1 ppl)<br />0I02 anti-collision testing (1 ppl) <br />ItoV/Picoam. HCO (1ppl)
 
| 2B Alignment (2 ppl)
 
| 2B Alignment (2 ppl)
|  
+
| 2B Alignment (2 ppl) <br> 0I02 Anti-collision (1 ppl) <br> CIS Jobs (1-2ppl)
 
|  
 
|  
 
|  
 
|  
Line 2,402: Line 2,404:
 
| 830-9a: Cryo tour (3ppl)<br />Viewer HCO (1 ppl)<br />0I02 anti-collision testing (1 ppl)<br />ItoV/Picoam. HCO (1ppl)<br />CIS Work (1-2ppl)
 
| 830-9a: Cryo tour (3ppl)<br />Viewer HCO (1 ppl)<br />0I02 anti-collision testing (1 ppl)<br />ItoV/Picoam. HCO (1ppl)<br />CIS Work (1-2ppl)
 
| 2B Alignment (2 ppl)
 
| 2B Alignment (2 ppl)
| ''PSS Kicker Cert?''
+
| 2B Alignment (2ppl) <br> 0I02 Anti-collision (1 ppl) <br> CIS Jobs (1-2ppl) <br> Laser Hut Work <br> FML HVAC Reconfig (2 ppl)?
|  
+
| 60 Hz Snooping (1ppl)
 
|  
 
|  
 
|- style="background-color:#DFDCBA;"
 
|- style="background-color:#DFDCBA;"
Line 2,410: Line 2,412:
 
| Laser hut work<br />Magnet HCO (2-4ppl) <br /> ''Photocathode activation (1 ppl)''
 
| Laser hut work<br />Magnet HCO (2-4ppl) <br /> ''Photocathode activation (1 ppl)''
 
| Laser hut work<br />Magnet HCO (2-4ppl)<br />'''4p Lock-Up''': PSS Certs -> BP
 
| Laser hut work<br />Magnet HCO (2-4ppl)<br />'''4p Lock-Up''': PSS Certs -> BP
| Laser hut work<br />Magnet HCO (2-4ppl)
+
| Laser hut work<br />Magnet HCO (2-4ppl)<br />'''4p Lock-Up''': PSS Certs -> BP
|  
+
| Laser hut work<br />Magnet HCO (2-4ppl) <br> QE Scan? (2 ppl)
|  
+
| 60 Hz Snooping (1ppl)
 
|  
 
|  
 
|}
 
|}
Line 2,434: Line 2,436:
 
* PSS = Kowal
 
* PSS = Kowal
  
 +
 +
</div>
 +
 +
= Week 33 (May 17 - May 21) =
 +
<div class="mw-collapsible mw-collapsed">
 +
 +
 +
; HCO to 500keV [https://logbooks.jlab.org/entry/3877755 completed] 5/21
 +
; Beam Authorization [https://logbooks.jlab.org/entry/3877749 granted] 5/21
 +
 +
 +
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22462?load=Task&task_id=22462&allComments=yes 22462 0I02 Harp Repair]
 +
** Wednesday: beamline component disconnects and vent, begin harp swap
 +
** Thursday: complete harp swap, pumpdown, leak check, verify harp operation, setup and begin overnight bake
 +
** Friday: Bake cool by 8AM. Re-install beamline components, re-HCO components
 +
 +
 +
* VEPCO Automatic Voltage Regulators Test, ATLis 22392
 +
** Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.
 +
** Incoming power voltage variation < +/- 10%
 +
** "Be prepared for a power interruption"
 +
 +
 +
<u>'''Injector Tunnel and Service Building'''</u>
 +
 +
{| class="wikitable" style="text-align:center; vertical-align:middle; background-color:#BFDCDA;"
 +
|- style="font-weight:bold; background-color:#CFDCCA;"
 +
! style="background-color:#CFDCCA" | '''Location'''<br />Time
 +
! style="background-color:#CFDCCA" | Mon 5/17
 +
! style="background-color:#CFDCCA" | Tue 5/18
 +
! style="background-color:#CFDCCA" | Wed 5/19
 +
! style="background-color:#CFDCCA" | Thu 5/20
 +
! style="background-color:#CFDCCA" | Fri 5/21
 +
|- style="background-color:#AFDCEA;"
 +
| '''InjSB'''<br /> All Day
 +
| '''Service Building Clean-Up'''<br />'''Hot Checkout'''
 +
| '''Service Building Clean-Up''' <br> '''Hot Checkout'''
 +
| '''Service Building Clean-Up''' <br> '''Hot Checkout''' <br><s>⚡VEPCO Voltage Tests<br />1030a-noon (4th attempt?)</s>
 +
| '''Service Building Clean-Up''' <br> '''Hot Checkout'''
 +
| '''Service Building Clean-Up''' <br> '''Hot Checkout'''
 +
|-
 +
| '''InjSB'''<br /> Early <br /> Morning <br /> <9a
 +
|
 +
|
 +
|
 +
|
 +
|
 +
|-
 +
| '''InjSB'''<br /> Morning
 +
| Magnet HCO
 +
| Magnet HCO
 +
| Magnet Rack HCO
 +
| Magnet Rack HCO
 +
|
 +
|-
 +
| '''InjSB'''<br /> Afternoon
 +
| Magnet HCO
 +
| Magnet HCO
 +
| Magnet Rack HCO
 +
| Magnet Rack HCO
 +
|
 +
|- style="background-color:#EFDCAA;"
 +
| '''Tunnel'''<br /> All Day
 +
| '''Wrapping up HCO'''<br />Wien HV Soak
 +
| '''Wrapping up HCO'''<br />Wien HV Soak<br />Beam Commissioning
 +
| '''0I02 Harp Repair''' <br /><s>⚡VEPCO Voltage Tests<br />1030a-noon (4th attempt?)</s>
 +
| '''Wrapping up Magnet HCO'''
 +
| 0I02-"region" Reconnects <br> ''Beam Commissioning?''
 +
|- style="background-color:#DFDCBA;"
 +
| '''Tunnel'''<br /> Early <br /> Morning <br /> <9a
 +
| 0I02 anti-collision (1 ppl)<br />
 +
|
 +
| Turbopump hook-up at 0I06 (1ppl)
 +
|
 +
| 0I02-"region" reconnects <br> Wien Resistor LCW Fittings
 +
|- style="background-color:#DFDCBA;"
 +
| '''Tunnel'''<br /> Morning
 +
| Magnet HCO (2-5ppl)
 +
| Magnet HCO <br> 11a: HCO Committee tour (3ppl)
 +
| 830-9a: Cryo tour (3ppl) <br> 0I02 Harp Repair (3ppl) <br> Laser mirror work
 +
| 0I02 NEG Activation <br> Bake Takedown (2ppl) <br> Magnet HCO (2-5ppl) <br> Wien resistor cooling <br>
 +
| 0I02-"region" Reconnects -- <br> Magnets <br> YAG, A2, BPM, Harp <br> PSS Kicker <br> <br> Wien resistor cooling
 +
|- style="background-color:#DFDCBA;"
 +
| '''Tunnel'''<br /> Afternoon
 +
| ''Laser hut work?''<br />Magnet HCO (2-5ppl)<br />Evening: 60Hz snooping
 +
|
 +
| 0I02 Harp Repair (3ppl)
 +
| Magnet HCO (2-5ppl) <br> Wien resistor cooling <br>
 +
| '''12p Lock-up: M0 PSS Certs''' <br> Beam Auth <br> Transitioning to Beam Ops
 +
|}
 +
 +
Tunnel Personnel Loading Limits: '''Injector''', upstream of plastic curtain, '''total=8 -> 4 upstream of laser hut, 4 downstream of laser hut'''
 +
 +
[[File:InjSB Week30 1.png|1000px]]
  
 
</div>
 
</div>

Latest revision as of 16:19, 23 May 2021

5/21/21 AIPINJ Phase I Installation and HCO Complete.

2020 Weeks 1 through 13

Week 14 (Jan 4 - Jan 8)

Week 15 (Jan 11 - Jan 15)

Week 16 (Jan 18 - Jan 22 +weekend)

Week 17 (Jan 25 - Jan 29)

Week 18 (Feb 1 - Feb 5)

Week 19 (Feb 8 - Feb 12)

Week 20 (Feb 15 - Feb 19)

Week 21 (Feb 22 - Feb 26)

Week 22 (Mar 1- Mar 5)

Week 23 (Mar 8 - Mar 12)

Week 24 (Mar 15 - Mar 19)

Week 25 (Mar 22 - Mar 26)

Week 26 (Mar 29 - Apr 2)

Week 27 (Apr 5 - Apr 9)

Week 28 (Apr 12 - Apr 16)

Week 29 (Apr 19 - Apr 23)

Week 30 (Apr 26 - Apr 30)

Week 31 (May 3 - May 7)

Week 32 (May 10 - May 14)

Week 33 (May 17 - May 21)

Penetration Work

Fire System Work