;5/21/21 AIPINJ Phase I Installation and HCO Complete.
 +
 
=2020 Weeks 1 through 13 =
 
=2020 Weeks 1 through 13 =
 
<div class="mw-collapsible mw-collapsed">
 
<div class="mw-collapsible mw-collapsed">
Line 2,438: Line 2,440:
  
 
= Week 33 (May 17 - May 21) =
 
= Week 33 (May 17 - May 21) =
<div class="mw-collapsible">
+
<div class="mw-collapsible mw-collapsed">
  
;'''Tunnel work '''
 
* '''Finish HCO''' ====> '''Beam Commissioning!'''
 
** First CEBAF beam of 2021
 
** First ~4m of Injector newly upgraded
 
  
 +
; HCO to 500keV [https://logbooks.jlab.org/entry/3877755 completed] 5/21
 +
; Beam Authorization [https://logbooks.jlab.org/entry/3877749 granted] 5/21
  
* Equipment crane-out (MechInstall)
 
  
* Viewer HCO (Norris)
+
* [http://devweb.acc.jlab.org/CSUEApps/atlis/task/22462?load=Task&task_id=22462&allComments=yes 22462 0I02 Harp Repair]
* Harp 0I02 electronics install and HCO (Dela Cruz)
+
** Wednesday: beamline component disconnects and vent, begin harp swap
* Magnet HCO (Coleman)
+
** Thursday: complete harp swap, pumpdown, leak check, verify harp operation, setup and begin overnight bake
 
+
** Friday: Bake cool by 8AM. Re-install beamline components, re-HCO components
* CIS HCO
 
** Laser alignment optimization (Zhang)
 
** 1/2 Waveplate T/S (Windham)
 
** Photocathode activation (Grames)
 
** Wien system HCO (Hernandez-Garcia, Dela Cruz)
 
** Ion pump noise investigation (Stutzman)
 
 
 
 
 
* 60Hz electrical noise snooping (Suleiman) ''evenings''
 
  
  
;'''ISB Work '''
+
* VEPCO Automatic Voltage Regulators Test, ATLis 22392  
* CIS Rack Work, IN01* (Windham)
 
* Wien System HCO, IN01B0{0,1} (Dela Cruz, Hernandez-Garcia)
 
* ItoV System Checkout, FC2 unlock (Francis) ''Mon''
 
* Magnet HCO, IN02B{10,11,26}+IN04B10 (Coleman)
 
* Viewer HCO, IN01B04+IN03B0{6,7} (Norris)
 
* Harp HCO, IN01B03+IN03B06 (Dela Cruz)
 
 
 
 
 
* VEPCO Automatic Voltage Regulators Test, ATLis 22392 ''Tuesday, 1030a - noon (if all goes well)''
 
 
** Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.  
 
** Voltage will be adjusted remotely to verify operation of automatic voltage regulators. If there is a huge problem... there could be a power outage.  
 
** Incoming power voltage variation < +/- 10%
 
** Incoming power voltage variation < +/- 10%
Line 2,490: Line 2,471:
 
|- style="background-color:#AFDCEA;"
 
|- style="background-color:#AFDCEA;"
 
| '''InjSB'''<br /> All Day
 
| '''InjSB'''<br /> All Day
| '''Service Building Clean-Up'''<br />'''Wrapping up HCO'''
+
| '''Service Building Clean-Up'''<br />'''Hot Checkout'''
|  
+
| '''Service Building Clean-Up''' <br> '''Hot Checkout'''
| ⚡VEPCO Voltage Tests<br />1030a-noon (4th attempt?)
+
| '''Service Building Clean-Up''' <br> '''Hot Checkout''' <br><s>⚡VEPCO Voltage Tests<br />1030a-noon (4th attempt?)</s>
|  
+
| '''Service Building Clean-Up''' <br> '''Hot Checkout'''
|  
+
| '''Service Building Clean-Up''' <br> '''Hot Checkout'''
 
|-
 
|-
 
| '''InjSB'''<br /> Early <br /> Morning <br /> <9a
 
| '''InjSB'''<br /> Early <br /> Morning <br /> <9a
Line 2,505: Line 2,486:
 
| '''InjSB'''<br /> Morning
 
| '''InjSB'''<br /> Morning
 
| Magnet HCO
 
| Magnet HCO
|  
+
| Magnet HCO
|  
+
| Magnet Rack HCO
|  
+
| Magnet Rack HCO
 
|  
 
|  
 
|-
 
|-
 
| '''InjSB'''<br /> Afternoon
 
| '''InjSB'''<br /> Afternoon
 
| Magnet HCO
 
| Magnet HCO
|  
+
| Magnet HCO
|  
+
| Magnet Rack HCO
|  
+
| Magnet Rack HCO
 
|  
 
|  
 
|- style="background-color:#EFDCAA;"
 
|- style="background-color:#EFDCAA;"
 
| '''Tunnel'''<br /> All Day
 
| '''Tunnel'''<br /> All Day
 
| '''Wrapping up HCO'''<br />Wien HV Soak
 
| '''Wrapping up HCO'''<br />Wien HV Soak
| PSS Certs<br />Beam Commissioning
+
| '''Wrapping up HCO'''<br />Wien HV Soak<br />Beam Commissioning
| '''Beam Commissioning'''<br />⚡VEPCO Voltage Tests<br />1030a-noon (4th attempt?)
+
| '''0I02 Harp Repair''' <br /><s>⚡VEPCO Voltage Tests<br />1030a-noon (4th attempt?)</s>
| '''Beam Commissioning'''
+
| '''Wrapping up Magnet HCO'''
| '''Beam Commissioning'''
+
| 0I02-"region" Reconnects <br> ''Beam Commissioning?''
 
|- style="background-color:#DFDCBA;"
 
|- style="background-color:#DFDCBA;"
 
| '''Tunnel'''<br /> Early <br /> Morning <br /> <9a
 
| '''Tunnel'''<br /> Early <br /> Morning <br /> <9a
 
| 0I02 anti-collision (1 ppl)<br />
 
| 0I02 anti-collision (1 ppl)<br />
 
|  
 
|  
 +
| Turbopump hook-up at 0I06 (1ppl)
 
|  
 
|  
|  
+
| 0I02-"region" reconnects <br> Wien Resistor LCW Fittings
|
 
 
|- style="background-color:#DFDCBA;"
 
|- style="background-color:#DFDCBA;"
 
| '''Tunnel'''<br /> Morning
 
| '''Tunnel'''<br /> Morning
 
| Magnet HCO (2-5ppl)
 
| Magnet HCO (2-5ppl)
| 11a: HCO Committee tour (3ppl)
+
| Magnet HCO <br> 11a: HCO Committee tour (3ppl)
| 830-9a: Cryo tour (3ppl)
+
| 830-9a: Cryo tour (3ppl) <br> 0I02 Harp Repair (3ppl) <br> Laser mirror work
|  
+
| 0I02 NEG Activation <br> Bake Takedown (2ppl) <br> Magnet HCO (2-5ppl) <br> Wien resistor cooling <br>
|  
+
| 0I02-"region" Reconnects -- <br> Magnets <br> YAG, A2, BPM, Harp <br> PSS Kicker <br> <br> Wien resistor cooling
 
|- style="background-color:#DFDCBA;"
 
|- style="background-color:#DFDCBA;"
 
| '''Tunnel'''<br /> Afternoon
 
| '''Tunnel'''<br /> Afternoon
 
| ''Laser hut work?''<br />Magnet HCO (2-5ppl)<br />Evening: 60Hz snooping
 
| ''Laser hut work?''<br />Magnet HCO (2-5ppl)<br />Evening: 60Hz snooping
| Lock-up: PSS Certs<br />''Beam Commissioning''
 
|
 
|
 
 
|  
 
|  
 +
| 0I02 Harp Repair (3ppl)
 +
| Magnet HCO (2-5ppl) <br> Wien resistor cooling <br>
 +
| '''12p Lock-up: M0 PSS Certs''' <br> Beam Auth <br> Transitioning to Beam Ops
 
|}
 
|}
  
 
Tunnel Personnel Loading Limits: '''Injector''', upstream of plastic curtain, '''total=8 -> 4 upstream of laser hut, 4 downstream of laser hut'''
 
Tunnel Personnel Loading Limits: '''Injector''', upstream of plastic curtain, '''total=8 -> 4 upstream of laser hut, 4 downstream of laser hut'''
 +
 +
[[File:InjSB Week30 1.png|1000px]]
  
 
</div>
 
</div>

Latest revision as of 16:19, 23 May 2021

5/21/21 AIPINJ Phase I Installation and HCO Complete.

2020 Weeks 1 through 13

Week 14 (Jan 4 - Jan 8)

Week 15 (Jan 11 - Jan 15)

Week 16 (Jan 18 - Jan 22 +weekend)

Week 17 (Jan 25 - Jan 29)

Week 18 (Feb 1 - Feb 5)

Week 19 (Feb 8 - Feb 12)

Week 20 (Feb 15 - Feb 19)

Week 21 (Feb 22 - Feb 26)

Week 22 (Mar 1- Mar 5)

Week 23 (Mar 8 - Mar 12)

Week 24 (Mar 15 - Mar 19)

Week 25 (Mar 22 - Mar 26)

Week 26 (Mar 29 - Apr 2)

Week 27 (Apr 5 - Apr 9)

Week 28 (Apr 12 - Apr 16)

Week 29 (Apr 19 - Apr 23)

Week 30 (Apr 26 - Apr 30)

Week 31 (May 3 - May 7)

Week 32 (May 10 - May 14)

Week 33 (May 17 - May 21)

Penetration Work

Fire System Work