Difference between revisions of "2021-05-26"
Jump to navigation
Jump to search
Line 25: | Line 25: | ||
* Downstream viewer / faraday cup assembly under vacuum. RGA leak check completed. | * Downstream viewer / faraday cup assembly under vacuum. RGA leak check completed. | ||
* Last 4 5/8" bpm pulled from elevated line & installed. (One: failed insertion measurements & w/ John Musson, One: stripped tap hole). | * Last 4 5/8" bpm pulled from elevated line & installed. (One: failed insertion measurements & w/ John Musson, One: stripped tap hole). | ||
− | * Spool pieces installed on both sides of 1st cross (one last one remaining); all but ~2 feet of beam line now under vacuum and leak checked. | + | * Spool pieces installed on both sides of 1st cross (one last one remaining); all but ~2 feet of beam line now under vacuum and leak checked. |
+ | * Vacuum falling, but light bake may be required once we have completed installation. | ||
* Roof tiles off for HDIce (5/24), Dilution refrigerator craned out (5/25), and then roof tiles replaced again (5/26). | * Roof tiles off for HDIce (5/24), Dilution refrigerator craned out (5/25), and then roof tiles replaced again (5/26). | ||
− | + | ||
*Gun work progressing well: | *Gun work progressing well: | ||
Line 43: | Line 44: | ||
* Break vacuum in FC3 region | * Break vacuum in FC3 region | ||
* Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining. | * Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining. | ||
+ | * Last spool piece [4.5" flange x 24.5" long x 4 5/8" flange] under fabrication. To install: | ||
+ | *# Ion pumps OFF | ||
+ | *# Purge with GN2 from both sides, one side through pump cart, the other side through kwik flange with 1/4" compression port. | ||
+ | *# Use other pump cart from vacuum lab TL1137 (attached to the LIGO tube station) to vent from both sides, with GN2. Wait until Matt's return if desired. | ||
+ | *# One more pump down and RGA leak check | ||
+ | *# Add the thin window | ||
+ | *# Heat / bake beam line | ||
+ | *# Activate NEGs | ||
+ | *# Move ion pumps onto house power / UHV supplies. | ||
+ | |||
+ | (Note: Pump cart w/ RGA suffering intermittent leak; Matt isolated to 11 L/s pump & 4-way cross joint - 4-way cross new, so swap out 11 L/s pump if it's an issue. One is staged on shelf in cave.) | ||
+ | |||
Revision as of 09:53, 25 May 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Long Term Schedule: Gantt (Outstanding tasks)
- Supplementary Shielding Installation: Mid-June
- Beamline Commissioning / Test Plans / Shielding Verification
- 7/26/21 Start Hot Check-out
- Commission new beam line and execute experiment
- Science!!!
New items for discussion:
Short term schedule update:
This week:
- Area up to transition after solenoid under vacuum. RGA leak check completed.
- Downstream viewer / faraday cup assembly under vacuum. RGA leak check completed.
- Last 4 5/8" bpm pulled from elevated line & installed. (One: failed insertion measurements & w/ John Musson, One: stripped tap hole).
- Spool pieces installed on both sides of 1st cross (one last one remaining); all but ~2 feet of beam line now under vacuum and leak checked.
- Vacuum falling, but light bake may be required once we have completed installation.
- Roof tiles off for HDIce (5/24), Dilution refrigerator craned out (5/25), and then roof tiles replaced again (5/26).
- Gun work progressing well:
- HV chamber evaluation - plan to bake to evaporate lubricant & pump it off, install photocathode, and bake again.
- Gun rebuild schedule
- Minor SF6 leak in HV chamber identified; repair later...
Next Week:
- Mount bottle rack in Labyrinth; remove gas bottles to rack.
- Wastewater experiment line fully under vacuum (with flange in place of the thin window).
- Install target mechanism
- Build 80/20 support structure; Pb table components awaiting delivery.
- Unistrut mounting for cables - Neal will do when available
- Break vacuum in FC3 region
- Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining.
- Last spool piece [4.5" flange x 24.5" long x 4 5/8" flange] under fabrication. To install:
- Ion pumps OFF
- Purge with GN2 from both sides, one side through pump cart, the other side through kwik flange with 1/4" compression port.
- Use other pump cart from vacuum lab TL1137 (attached to the LIGO tube station) to vent from both sides, with GN2. Wait until Matt's return if desired.
- One more pump down and RGA leak check
- Add the thin window
- Heat / bake beam line
- Activate NEGs
- Move ion pumps onto house power / UHV supplies.
(Note: Pump cart w/ RGA suffering intermittent leak; Matt isolated to 11 L/s pump & 4-way cross joint - 4-way cross new, so swap out 11 L/s pump if it's an issue. One is staged on shelf in cave.)
2 weeks:
- Add Mu metal over bellows on wastewater line.
- Switch Wastewater line Vacuum HV from local supplies to house power. Make UED updates as appropriate for vacuum system.
- Pull Heliax from Spectrum analyzer/Control room >> Buncher
- 4th terminal system in Control room under assembly/rebuild
- Items from To-do list...
Engineering Other business
Reports on Open Action Items:
Action Items:
- Formal run plan (McCaughan)