<u>This week:</u> | <u>This week:</u> | ||
* Elevated beam line terminated in pump and RGA leak checked | * Elevated beam line terminated in pump and RGA leak checked | ||
− | * Experimental beam line under vacuum, RGA leak check required | + | * Experimental beam line under vacuum with thin window attached, RGA leak check required. |
* Vacuum pumping down well, but light bake may be required once we have completed installation. | * Vacuum pumping down well, but light bake may be required once we have completed installation. | ||
+ | * STAC5 controller for chopper configured, installed, and tested. | ||
+ | * FC3 region [https://logbooks.jlab.org/entry/3879455 vented, purged], and [https://logbooks.jlab.org/entry/3879558 mostly reconfigured]. | ||
+ | * Go ahead given by division management for FML to procure concrete shielding using funds from LDRD and UITF (10K+30kprocurement+30K AIP/Labor reapportionment) | ||
<u>Still to do:</u> | <u>Still to do:</u> | ||
+ | * Finish FC3 region vacuum work. | ||
* Install target mechanism | * Install target mechanism | ||
* Add Mu metal over bellows on wastewater line. | * Add Mu metal over bellows on wastewater line. | ||
+ | * EES may start cabling downstream section & making UED updates. | ||
*Gun work progressing well: | *Gun work progressing well: | ||
*# HV chamber evaluation - plan to bake to evaporate lubricant & pump it off, install photocathode, and bake again. | *# HV chamber evaluation - plan to bake to evaporate lubricant & pump it off, install photocathode, and bake again. | ||
− | *# Sb source laser aperture added in depo chamber; aligned to laser path. | + | *# First [https://logbooks.jlab.org/entry/3879424 bake] [https://logbooks.jlab.org/entry/3879430 went] [https://logbooks.jlab.org/entry/3879440 well], despite an unexpected power outage. |
+ | *# Test lab procedures updated to contact UITF and Polarized source group in event of power outages in the future. | ||
+ | *# Sb source laser aperture added in depo chamber; [https://logbooks.jlab.org/entry/3878165 aligned to laser path]. | ||
+ | *# [https://logbooks.jlab.org/entry/3878166 Mask alignment examined] | ||
+ | *# [https://logbooks.jlab.org/entry/3878908 Pucks prepared for next run] | ||
*# [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule] | *# [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule] | ||
*# Minor SF6 leak in HV chamber identified; repair later... | *# Minor SF6 leak in HV chamber identified; repair later... | ||
Line 38: | Line 47: | ||
<u>Next Week:</u> | <u>Next Week:</u> | ||
− | * Build 80/20 support structure; Pb table components awaiting delivery. | + | * Build 80/20 support structure; Pb table components awaiting delivery. (status update?) |
− | |||
− | |||
− | |||
* Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining. | * Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining. | ||
+ | * Mount bottle rack in Labyrinth; remove gas bottles to rack. | ||
+ | * Unistrut mounting for cables - Neal will do when available | ||
+ | |||
<u>2 weeks:</u> | <u>2 weeks:</u> | ||
− | |||
− | |||
*Pull Heliax from Spectrum analyzer/Control room >> Buncher | *Pull Heliax from Spectrum analyzer/Control room >> Buncher | ||
*4th terminal system in Control room under assembly/rebuild | *4th terminal system in Control room under assembly/rebuild |
Latest revision as of 17:07, 8 June 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Long Term Schedule: Gantt (Outstanding tasks)
- Supplementary Shielding Installation: Mid-June
- Beamline Commissioning / Test Plans / Shielding Verification
- 7/26/21 Start Hot Check-out
- Commission new beam line and execute experiment
- Science!!!
New items for discussion:
Short term schedule update:
This week:
- Elevated beam line terminated in pump and RGA leak checked
- Experimental beam line under vacuum with thin window attached, RGA leak check required.
- Vacuum pumping down well, but light bake may be required once we have completed installation.
- STAC5 controller for chopper configured, installed, and tested.
- FC3 region vented, purged, and mostly reconfigured.
- Go ahead given by division management for FML to procure concrete shielding using funds from LDRD and UITF (10K+30kprocurement+30K AIP/Labor reapportionment)
Still to do:
- Finish FC3 region vacuum work.
- Install target mechanism
- Add Mu metal over bellows on wastewater line.
- EES may start cabling downstream section & making UED updates.
- Gun work progressing well:
- HV chamber evaluation - plan to bake to evaporate lubricant & pump it off, install photocathode, and bake again.
- First bake went well, despite an unexpected power outage.
- Test lab procedures updated to contact UITF and Polarized source group in event of power outages in the future.
- Sb source laser aperture added in depo chamber; aligned to laser path.
- Mask alignment examined
- Pucks prepared for next run
- Gun rebuild schedule
- Minor SF6 leak in HV chamber identified; repair later...
Next Week:
- Build 80/20 support structure; Pb table components awaiting delivery. (status update?)
- Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining.
- Mount bottle rack in Labyrinth; remove gas bottles to rack.
- Unistrut mounting for cables - Neal will do when available
2 weeks:
- Pull Heliax from Spectrum analyzer/Control room >> Buncher
- 4th terminal system in Control room under assembly/rebuild
- Items from To-do list...
Engineering Other business
Reports on Open Action Items:
Action Items:
- Formal run plan (McCaughan)