Difference between revisions of "2021-06-16"
Jump to navigation
Jump to search
Line 22: | Line 22: | ||
<u>Short term schedule update:</u><br> | <u>Short term schedule update:</u><br> | ||
<u>This week:</u> | <u>This week:</u> | ||
− | * | + | * Vacuum work and leak checks finished excluding thin window install. |
− | |||
− | |||
− | |||
− | |||
* Go ahead given by division management for FML to procure concrete shielding using funds from LDRD and UITF (10K+30kprocurement+30K AIP/Labor reapportionment) | * Go ahead given by division management for FML to procure concrete shielding using funds from LDRD and UITF (10K+30kprocurement+30K AIP/Labor reapportionment) | ||
<u>Still to do:</u> | <u>Still to do:</u> | ||
− | * | + | * Beam line survey today |
+ | * This window assembly update. | ||
* Install target mechanism | * Install target mechanism | ||
* Add Mu metal over bellows on wastewater line. | * Add Mu metal over bellows on wastewater line. | ||
− | * | + | * Build 80/20 support structure; Pb table components awaiting delivery. (status update?) |
+ | * Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining. | ||
+ | * Mount bottle rack in Labyrinth; remove gas bottles to rack. | ||
+ | * Unistrut mounting for cables - Neal will do when available | ||
+ | |||
*Gun work progressing well: | *Gun work progressing well: | ||
*# HV chamber evaluation - plan to bake to evaporate lubricant & pump it off, install photocathode, and bake again. | *# HV chamber evaluation - plan to bake to evaporate lubricant & pump it off, install photocathode, and bake again. | ||
− | |||
− | |||
− | |||
− | |||
*# [https://logbooks.jlab.org/entry/3878908 Pucks prepared for next run] | *# [https://logbooks.jlab.org/entry/3878908 Pucks prepared for next run] | ||
*# [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule] | *# [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild schedule] | ||
*# Minor SF6 leak in HV chamber identified; repair later... | *# Minor SF6 leak in HV chamber identified; repair later... | ||
− | |||
<u>Next Week:</u> | <u>Next Week:</u> | ||
− | * | + | * EES may start cabling downstream section & making UED updates. |
− | |||
− | |||
− | |||
Revision as of 21:58, 15 June 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/946721076.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 946721076.
- To join via phone, use one of the following numbers and the Conference ID: 946721076.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Long Term Schedule: Gantt (Outstanding tasks)
- Supplementary Shielding Installation: ???
- Beamline Commissioning / Test Plans / Shielding Verification
- 7/26/21 Start Hot Check-out
- Commission new beam line and execute experiment
- Science!!!
New items for discussion:
Short term schedule update:
This week:
- Vacuum work and leak checks finished excluding thin window install.
- Go ahead given by division management for FML to procure concrete shielding using funds from LDRD and UITF (10K+30kprocurement+30K AIP/Labor reapportionment)
Still to do:
- Beam line survey today
- This window assembly update.
- Install target mechanism
- Add Mu metal over bellows on wastewater line.
- Build 80/20 support structure; Pb table components awaiting delivery. (status update?)
- Ready to install Al base plates for FC3 region rework as well as solenoid stand. FC3 plate awaiting machining.
- Mount bottle rack in Labyrinth; remove gas bottles to rack.
- Unistrut mounting for cables - Neal will do when available
- Gun work progressing well:
- HV chamber evaluation - plan to bake to evaporate lubricant & pump it off, install photocathode, and bake again.
- Pucks prepared for next run
- Gun rebuild schedule
- Minor SF6 leak in HV chamber identified; repair later...
Next Week:
- EES may start cabling downstream section & making UED updates.
2 weeks:
- Pull Heliax from Spectrum analyzer/Control room >> Buncher
- 4th terminal system in Control room under assembly/rebuild
- Items from To-do list...
Engineering Other business
Reports on Open Action Items:
Action Items:
- Formal run plan (McCaughan)