==== <u>Schedule</u> ==== | ==== <u>Schedule</u> ==== | ||
− | |||
Long Term Schedule: [[media:WWinstall-8.4.21.pdf|Gantt]] ([[media:WWinstall-Todo_8.4.21.pdf|Outstanding tasks]]) | Long Term Schedule: [[media:WWinstall-8.4.21.pdf|Gantt]] ([[media:WWinstall-Todo_8.4.21.pdf|Outstanding tasks]]) | ||
Line 31: | Line 30: | ||
'''[[E-beam_Irradiation_Experiment| Experiment]]:''' | '''[[E-beam_Irradiation_Experiment| Experiment]]:''' | ||
− | + | * [[UE-21-001_Experimental_Binder_Documents| COO/ESAD/RSAD prepared]]; committee response [[media:UE-21-001_ERR_response.docx| delivered]]. ERR walk-through yesterday. | |
− | |||
− | * [[UE-21-001_Experimental_Binder_Documents| COO/ESAD/RSAD prepared]]; committee response | ||
− | |||
− | |||
'''CIS/EGG:''' | '''CIS/EGG:''' | ||
* [https://logbooks.jlab.org/entry/3890263 Gun operating] at 180kV w/o Field Emission following rebuild, HV conditioning, and Kr processing (Many thanks to all involved!!) | * [https://logbooks.jlab.org/entry/3890263 Gun operating] at 180kV w/o Field Emission following rebuild, HV conditioning, and Kr processing (Many thanks to all involved!!) | ||
− | * | + | * [https://logbooks.jlab.org/entry/3890419 Y-dipole] interlock unbypassed in Glassman HVPS. [https://logbooks.jlab.org/entry/3890468 Resistor tank] removed; gun cabled directly to HVPS. |
− | |||
* Gun HVPS [https://logbooks.jlab.org/entry/3890297 locked out] , reconnect gun valve, charge NF3, degas heater/puck, get UITF laser on (8/4) | * Gun HVPS [https://logbooks.jlab.org/entry/3890297 locked out] , reconnect gun valve, charge NF3, degas heater/puck, get UITF laser on (8/4) | ||
− | * Make photocathode (8/5) [Joe/Max] | + | |
+ | * [https://logbooks.jlab.org/entry/3890466 Puck 8] moved to prep, [https://logbooks.jlab.org/entry/3890808 heated], and de-gased. Some [https://logbooks.jlab.org/entry/3890654 inhomogeneities] observed. [https://logbooks.jlab.org/entry/3891654 Puck heated and activated] with [https://logbooks.jlab.org/entry/3891783 low QE]; laser alignment today. | ||
+ | * [https://logbooks.jlab.org/entry/3890867 Puck 18] to chamber for [https://logbooks.jlab.org/entry/3890924 rough drive laser alignment]. | ||
+ | |||
+ | Gun bake [https://logbooks.jlab.org/entry/3890506 pump hi-potted]. | ||
+ | |||
+ | *Make photocathode (8/5) [Joe/Max] | ||
* Align laser to photocathode, using retro and QE (8/5) [Shukui] | * Align laser to photocathode, using retro and QE (8/5) [Shukui] | ||
* [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild wiki] | * [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild wiki] | ||
− | |||
[https://logbooks.jlab.org/entry/3876613 Old insulator (punctured)] & [https://logbooks.jlab.org/entry/3876061 Old puck manipulator/schneedle] for reference; both replaced. | [https://logbooks.jlab.org/entry/3876613 Old insulator (punctured)] & [https://logbooks.jlab.org/entry/3876061 Old puck manipulator/schneedle] for reference; both replaced. | ||
[https://logbooks.jlab.org/entry/3882796 Very modest SF6 leak id-ed on top of HV tank]; will repair when practical. | [https://logbooks.jlab.org/entry/3882796 Very modest SF6 leak id-ed on top of HV tank]; will repair when practical. | ||
Line 54: | Line 53: | ||
*# [https://logbooks.jlab.org/entry/3890236 Trim magnets] near gun re-cabled. | *# [https://logbooks.jlab.org/entry/3890236 Trim magnets] near gun re-cabled. | ||
*# [https://logbooks.jlab.org/entry/3889992 Wastewater beam line] trims cabled up. | *# [https://logbooks.jlab.org/entry/3889992 Wastewater beam line] trims cabled up. | ||
− | *# Trim magnets near FC#3: 401H/V (completed) & 501H/V correctors + 501 quad | + | *# Trim magnets near FC#3: 401H/V (completed) & [https://logbooks.jlab.org/entry/3890985 501H/V correctors] + 501 quad. Many [https://logbooks.jlab.org/entry/3891455 polarity checks] completed. 501 correctors [https://logbooks.jlab.org/entry/3891699 re-designated] |
* Former PEPPo solenoid repaired, mapped, and installed. | * Former PEPPo solenoid repaired, mapped, and installed. | ||
* [http://devweb.acc.jlab.org/CSUEApps/uitflist/task/1672 Solenoid PS] being installed. Supply [https://logbooks.jlab.org/entry/3887222 placed, cables pulled], [https://logbooks.jlab.org/entry/3890134 cabled, and LCW hooked up]. | * [http://devweb.acc.jlab.org/CSUEApps/uitflist/task/1672 Solenoid PS] being installed. Supply [https://logbooks.jlab.org/entry/3887222 placed, cables pulled], [https://logbooks.jlab.org/entry/3890134 cabled, and LCW hooked up]. | ||
Line 66: | Line 65: | ||
''Viewer system status [IC; Norris/Vennekate/McCaughan]'' | ''Viewer system status [IC; Norris/Vennekate/McCaughan]'' | ||
* Recable 2 viewers in keV whose channels & hardware were appropriated for HDice (done) | * Recable 2 viewers in keV whose channels & hardware were appropriated for HDice (done) | ||
− | * Reconnect IYGM401 | + | * Reconnect IYGM401 [https://logbooks.jlab.org/entry/3891702 insertion depth adjusted] |
− | * | + | * ITVM703 limit switch requires attachment; 800-line viewers [https://logbooks.jlab.org/entry/3891709 non-communicating]. |
* Brian Freeman available for adViewer work for video camera for ITVM604A? Dome focusing still required... | * Brian Freeman available for adViewer work for video camera for ITVM604A? Dome focusing still required... | ||
''Wire Scanners [Delacruz/Poelker]'' | ''Wire Scanners [Delacruz/Poelker]'' | ||
− | * | + | * Harps all pass signal injection and stroke. |
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
''Chopper Controls (Windham/Lu)'' | ''Chopper Controls (Windham/Lu)'' | ||
Line 87: | Line 79: | ||
''BPMs (Windham / Hesse / McCaughan)'' | ''BPMs (Windham / Hesse / McCaughan)'' | ||
− | + | * Re-label IOCs/BPMs locally. | |
− | |||
− | |||
− | * Re-label locally. | ||
''Faraday Cups / Picoammeters (Francis)'' | ''Faraday Cups / Picoammeters (Francis)'' | ||
− | * | + | * FC2 unlocked for HCO |
− | |||
* Connections removed for shielding installation per RCG. | * Connections removed for shielding installation per RCG. | ||
* Picoammeters all good - some screen work required. | * Picoammeters all good - some screen work required. | ||
Line 102: | Line 90: | ||
''Vacuum (Ketchum/Kortze)'' | ''Vacuum (Ketchum/Kortze)'' | ||
* VBVM501 & VBVM602 slow valve connections. VBVM602 is new installation. | * VBVM501 & VBVM602 slow valve connections. VBVM602 is new installation. | ||
− | * VFVM401 Fast Valve | + | * VFVM401 Fast Valve [https://logbooks.jlab.org/entry/3890917 limit switches adjusted]; Kortze working firmware |
− | * VCGM604 Cathode Gauge | + | * VCGM604 Cathode Gauge cabled |
− | * | + | * NEG on MeV spectrometer line [https://logbooks.jlab.org/entry/3891467 reactivated]. |
− | + | * [https://logbooks.jlab.org/entry/3891718 VIPM301A/B hi-potted]. | |
− | * | ||
Line 113: | Line 100: | ||
− | '''RF:''' | + | '''RF/Cryo:''' |
− | * [https://logbooks.jlab.org/entry/ | + | * [https://logbooks.jlab.org/entry/3891503 Booster at 2K] and full |
− | |||
* Laser RF HCO | * Laser RF HCO | ||
Latest revision as of 07:54, 11 August 2021
Meeting Information
Connecting
To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.
- To join via a Web Browser, go to the page [1] https://bluejeans.com/984025598.
- To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 984025598.
- To join via phone, use one of the following numbers and the Conference ID: 984025598.
- Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada
Agenda
Schedule
Long Term Schedule: Gantt (Outstanding tasks)
- 8/9/21 Start Hot Check-out
- 8/16/21 Start commissioning (2 weeks)
- 8/23 BNNT cooldown in CMTF
- 8/30/21 Perform experiment (2 weeks)
- 10/18 C50R in CMTF
- Booster qualification following experiment until cryo trade to CMTF
New items for discussion:
General:
- Updated Ops Page
- Commissioning plan (basic)
- Commissioning plan (detailed, to break into shift plans)
Reports by Group:
- COO/ESAD/RSAD prepared; committee response delivered. ERR walk-through yesterday.
CIS/EGG:
- Gun operating at 180kV w/o Field Emission following rebuild, HV conditioning, and Kr processing (Many thanks to all involved!!)
- Y-dipole interlock unbypassed in Glassman HVPS. Resistor tank removed; gun cabled directly to HVPS.
- Gun HVPS locked out , reconnect gun valve, charge NF3, degas heater/puck, get UITF laser on (8/4)
- Puck 8 moved to prep, heated, and de-gased. Some inhomogeneities observed. Puck heated and activated with low QE; laser alignment today.
- Puck 18 to chamber for rough drive laser alignment.
Gun bake pump hi-potted.
- Make photocathode (8/5) [Joe/Max]
- Align laser to photocathode, using retro and QE (8/5) [Shukui]
- Gun rebuild wiki
Old insulator (punctured) & Old puck manipulator/schneedle for reference; both replaced. Very modest SF6 leak id-ed on top of HV tank; will repair when practical.
DC Power:
- Trims:
- Trim magnets near gun re-cabled.
- Wastewater beam line trims cabled up.
- Trim magnets near FC#3: 401H/V (completed) & 501H/V correctors + 501 quad. Many polarity checks completed. 501 correctors re-designated
- Former PEPPo solenoid repaired, mapped, and installed.
- Solenoid PS being installed. Supply placed, cables pulled, cabled, and LCW hooked up.
- MHB magnet re-designation to MLH to avoid confusion: Chris Gould making nomenclature changes / Gary Croke & Michele Joyce making controls changes / Eric Forman to update Quick Reference Drawing / Shaun to take care of song sheets
- Changes made in UED workspace for names and field maps; ready to merge soon. (Thanks Gary/Michele!)
- Replacement of cards and utility chassis' acquired for CEBAF under way...
Instrumentation and Controls:
Viewer system status [IC; Norris/Vennekate/McCaughan]
- Recable 2 viewers in keV whose channels & hardware were appropriated for HDice (done)
- Reconnect IYGM401 insertion depth adjusted
- ITVM703 limit switch requires attachment; 800-line viewers non-communicating.
- Brian Freeman available for adViewer work for video camera for ITVM604A? Dome focusing still required...
Wire Scanners [Delacruz/Poelker]
- Harps all pass signal injection and stroke.
Chopper Controls (Windham/Lu)
- Target Motion Control - Carriage remotely operable, step count needs some fine tuning.
- Control Screen complete?
BPMs (Windham / Hesse / McCaughan)
- Re-label IOCs/BPMs locally.
Faraday Cups / Picoammeters (Francis)
- FC2 unlocked for HCO
- Connections removed for shielding installation per RCG.
- Picoammeters all good - some screen work required.
Vacuum (Ketchum/Kortze)
- VBVM501 & VBVM602 slow valve connections. VBVM602 is new installation.
- VFVM401 Fast Valve limit switches adjusted; Kortze working firmware
- VCGM604 Cathode Gauge cabled
- NEG on MeV spectrometer line reactivated.
- VIPM301A/B hi-potted.
BCM
- BCM project software integration under way between Musson/Seaton and Sue Witherspoon
RF/Cryo:
- Booster at 2K and full
- Laser RF HCO
SSG:
BLM installation underway:
- Replace those previously removed
- Additions
- In crotch of MeV/Wastewater selecting dipole.
- Near 1st new diagnostic cross d.s. of solenoid
- Near 2nd new diagnostic cross by FC4
- D.S. of target after lead shielding
FSD inputs (original)
- Target motion (now software interlock)
- Solenoid (Now engineered control)
- BCM current clamp system
- Update gold masking
ME / Installation:
- Pb stacked; RCG required modification due to permanent shielding req delay.
- New designs for FC3 and FC4 with a great many thanks to Shaun for the design work and John/Xi for Pb arrangement and table construction!
- Songsheet being updated by Shaun; be sure to let him know when changes are made!
- Permanent shielding purchase in progress - FML (Russ) for most current details
- Unistrut mounting for cables when available
- Mount gas bottle rack in Labyrinth (Staged); remove gas bottles to rack.
Sys Admin:
- 4th terminal system in Control room under assembled/rebuilt
- Wall server configured
- Need to configure wall monitors and install small networked printer.