Difference between revisions of "Phase 2"
Jump to navigation
Jump to search
Line 12: | Line 12: | ||
==ATLIS Tasks== | ==ATLIS Tasks== | ||
+ | ===Phase 1 Region=== | ||
* Install harp, remove top-hat from viewer | * Install harp, remove top-hat from viewer | ||
* Re-make A2 joint | * Re-make A2 joint | ||
− | |||
* Return gold target ladder, w/ larger nipple, original STAC5 | * Return gold target ladder, w/ larger nipple, original STAC5 | ||
* Replace both Wien 20A SCE with lower noise power supplies | * Replace both Wien 20A SCE with lower noise power supplies | ||
Line 21: | Line 21: | ||
* Test mode-locked laser | * Test mode-locked laser | ||
* Install gun which reaches 200 kV reliably w/o field emission | * Install gun which reaches 200 kV reliably w/o field emission | ||
+ | |||
+ | ===Phase 2 Region=== | ||
* Requested to Steve brighter lights from laser room to gate (like we have by gun) | * Requested to Steve brighter lights from laser room to gate (like we have by gun) | ||
+ | * Take advantage of harp/A2 vacuum work to install new solenoid + valve downstream chopper? |
Revision as of 07:42, 18 August 2021
Recent Updates
Planning, planning, planning...
Major Phase 2 Beamline Components
ATLIS Tasks
Phase 1 Region
- Install harp, remove top-hat from viewer
- Re-make A2 joint
- Return gold target ladder, w/ larger nipple, original STAC5
- Replace both Wien 20A SCE with lower noise power supplies
- Install Lakshmi's DR dipole
- Install/test new kicker
- Test mode-locked laser
- Install gun which reaches 200 kV reliably w/o field emission
Phase 2 Region
- Requested to Steve brighter lights from laser room to gate (like we have by gun)
- Take advantage of harp/A2 vacuum work to install new solenoid + valve downstream chopper?