Difference between revisions of "2021-08-18"

From Ciswikidb
Jump to navigation Jump to search
 
(4 intermediate revisions by the same user not shown)
Line 36: Line 36:
 
'''Software'''
 
'''Software'''
 
* Changes made in UED workspace for names and field maps; ready to merge soon. (Thanks Gary/Michele!)
 
* Changes made in UED workspace for names and field maps; ready to merge soon. (Thanks Gary/Michele!)
* [[https://accweb.acc.jlab.org/hco/reports/overall-status?destinationId=50&destinationId=54&destinationId=55&categoryId=&systemId=&regionId=&groupId=&qualified= HCO underway]
+
* [https://accweb.acc.jlab.org/hco/reports/overall-status?destinationId=50&destinationId=54&destinationId=55&categoryId=&systemId=&regionId=&groupId=&qualified= HCO underway]
  
 
'''CIS/EGG:'''
 
'''CIS/EGG:'''
* Make photocathode (8/5) [Joe/Max]
+
* Photocathodes in progress: One created - low QE; 2nd one being heated now. [Joe/Max]
 
* Align laser to photocathode, using retro and QE (8/5) [Shukui]
 
* Align laser to photocathode, using retro and QE (8/5) [Shukui]
 
* [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild wiki]
 
* [https://wiki.jlab.org/ciswiki/index.php/Spring_2021_-_Rebuilding_Photogun Gun rebuild wiki]
Line 54: Line 54:
  
 
''Vacuum (Ketchum/Kortze)''
 
''Vacuum (Ketchum/Kortze)''
* VFVM401 Fast Valve [https://logbooks.jlab.org/entry/3890917 limit switches adjusted]; Kortze working firmware
+
* VFVM401 Fast Valve [https://logbooks.jlab.org/entry/3890917 limit switches adjusted]; Kortze working firmware. Matt hooked air line up.
 
* VCGM604 Cathode Gauge cabled
 
* VCGM604 Cathode Gauge cabled
  
Line 78: Line 78:
 
* Mount [https://logbooks.jlab.org/entry/3877442 gas bottle rack] in Labyrinth (Staged); remove gas bottles to rack.
 
* Mount [https://logbooks.jlab.org/entry/3877442 gas bottle rack] in Labyrinth (Staged); remove gas bottles to rack.
 
* Eric Forman to update Quick Reference Drawing  
 
* Eric Forman to update Quick Reference Drawing  
 
 
 
  
 
'''Sys Admin:'''
 
'''Sys Admin:'''
 
* Need to configure wall monitors and install small networked printer.
 
* Need to configure wall monitors and install small networked printer.
  
 +
 +
'''Action items:'''
 +
# UITFList task creation for necessary beam studies
 +
#* RCG Test (Keith) (Done)
 +
#* Fast Valve Test (Leo/Jim)
 +
#* Chopper slit (Scott/Weiwei)
 +
#* Target Encoder Interlock (Scott/Weiwei/Gary)
 +
#* BLM test (Scott B.)
 +
#* Target Rail calibration
 +
#* Others...
 +
# Snap file for design optics (Dennis/Xi)
 +
# Daily Run Coordinator Meetings (Mike/Gigi)
 +
# Populate shift plans (Mike / Gigi)
 +
# Shift taker instructions (Mike)
 +
# HCO
 +
# Beam Authorization (Mike)
 +
# Hazard analysis for Randy (Mike)
  
  
 
* [[media:Engineering-support-jobs.docx| List of Engineering Jobs remaining]]
 
* [[media:Engineering-support-jobs.docx| List of Engineering Jobs remaining]]
 
[[Meeting_minutes | Back to Main Meeting Minutes Page]]
 
[[Meeting_minutes | Back to Main Meeting Minutes Page]]

Latest revision as of 08:18, 18 August 2021

Meeting Information

Connecting

To connect to the meeting, please do the following: Time: Wednesday at 9:00 AM EST.

  1. To join via a Web Browser, go to the page [1] https://bluejeans.com/984025598.
  2. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 984025598.
  3. To join via phone, use one of the following numbers and the Conference ID: 984025598.
    • Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

Agenda

Schedule

Long Term Schedule: Gantt (Outstanding tasks)

  1. 8/9/21 Start Hot Check-out
  2. 8/23/21 Start commissioning (2 weeks)
  3. 8/23 BNNT cooldown in CMTF
  4. 9/7/21 Perform experiment (3 weeks)
  5. 10/18 C50R in CMTF
  6. Booster qualification following experiment until cryo trade to CMTF

New items for discussion:

General:

Reports by Group:

Experiment:

Software

  • Changes made in UED workspace for names and field maps; ready to merge soon. (Thanks Gary/Michele!)
  • HCO underway

CIS/EGG:

  • Photocathodes in progress: One created - low QE; 2nd one being heated now. [Joe/Max]
  • Align laser to photocathode, using retro and QE (8/5) [Shukui]
  • Gun rebuild wiki

DC Power:

  • Trims: Complete - final tests awaiting UED merge
  • Solenoid UITFList Task: Interlock checks completed. Diagnostics on box supply reading incorrectly, measured input voltage at supply to be 470VAC. Diagnostic repair and powering load to be completed at first opportunity.
  • Replacement of cards and utility chassis' acquired for CEBAF under way...

Instrumentation and Controls: Chopper Controls (Windham/Lu)

Vacuum (Ketchum/Kortze)

  • VFVM401 Fast Valve limit switches adjusted; Kortze working firmware. Matt hooked air line up.
  • VCGM604 Cathode Gauge cabled

BCM

  • BCM project software integration under way between Musson/Seaton and Sue Witherspoon

SSG:

BLM installation underway:

  • Replace those previously removed
  • Additions
    1. In crotch of MeV/Wastewater selecting dipole.
    2. Near 1st new diagnostic cross d.s. of solenoid
    3. Near 2nd new diagnostic cross by FC4
    4. D.S. of target after lead shielding

FSD inputs (original)

  • BCM current clamp system
  • Update gold masking

ME / Installation:

  • Shielding package verified by RCG; RCG checklist Friday.
  • Songsheet being updated by Shaun; be sure to let him know when changes are made!
  • Mount gas bottle rack in Labyrinth (Staged); remove gas bottles to rack.
  • Eric Forman to update Quick Reference Drawing

Sys Admin:

  • Need to configure wall monitors and install small networked printer.


Action items:

  1. UITFList task creation for necessary beam studies
    • RCG Test (Keith) (Done)
    • Fast Valve Test (Leo/Jim)
    • Chopper slit (Scott/Weiwei)
    • Target Encoder Interlock (Scott/Weiwei/Gary)
    • BLM test (Scott B.)
    • Target Rail calibration
    • Others...
  2. Snap file for design optics (Dennis/Xi)
  3. Daily Run Coordinator Meetings (Mike/Gigi)
  4. Populate shift plans (Mike / Gigi)
  5. Shift taker instructions (Mike)
  6. HCO
  7. Beam Authorization (Mike)
  8. Hazard analysis for Randy (Mike)


Back to Main Meeting Minutes Page